Dubai project status

The official construction status of every project in the Dubai Land Department (DLD) project register: how far it is built at the latest RERA site inspection, when it was inspected and the completion date the developer registered. 1,571 projects are under construction; the latest inspection on record is from 14 Oct 2026. Project register as of 16 Oct 2026.

Under construction
1,571
registered projects
Completed
1,669
registered projects
Inspected in the last 90 days
830
site inspections by RERA
Past the registered date
250
still under construction
Under constructionCompletedCancelled1,570 projects, latest inspection first
ProjectDeveloperDistrict in the registerStatusBuiltLatest inspectionRegistered completion
The Heart Of Europe 132 unitsT H O EWorld IslandsUnder construction86%12 May 202630 Sept 2022 · passed
The Community Motor City433 unitsAqua Properties DeveloperAl Hebiah FirstUnder construction95%12 May 202631 Oct 2025 · passed
10 Oxford By Iman430 unitsIman DevelopersAl Barsha South FourthUnder construction91%12 May 2026—
Damac Hills (2) - Park Greens 3383 unitsDamac PropertiesMadinat Hind 4Under construction33%12 May 2026—
Art Bay East103 unitsEllington PropertiesAl JadafUnder construction10%12 May 2026—
Art Bay West173 unitsEllington PropertiesAl JadafUnder construction9%12 May 2026—
Zephyra Residences102 unitsArsenal EastPalm DeiraUnder construction31%12 May 202631 Dec 2027
Tavora Residences By Jhk Heights Real Estate Development95 unitsJHK DevelopmentsWarsan FourthUnder construction61%12 May 202615 Dec 2026
Il Vento331 unitsKora PropertiesMadinat Dubai AlmelaheyahUnder construction1%12 May 202630 Sept 2029
Solcasa Residence58 unitsMatrix DevelopmentNad Al Shiba FirstUnder construction94%11 May 20261 Aug 2026 · passed
Serenia District - West423 unitsPalma HoldingAl Thanyah FifthUnder construction3%11 May 202631 Dec 2028
California Village212 unitsGFH Real EstateWadi Al Safa 4Under construction95%8 May 202615 Jul 2025 · passed
Views Vii By Golden Woods68 unitsGolden Woods Real Estate DevelopmentMadinat Al MataarUnder construction90%8 May 202630 Jul 2026 · passed
Mirdif Hills - Asayel Avenue193 unitsDubai Investment Real EstateMirdifUnder construction33%8 May 20265 May 2027
Azizi Venice 62,965 unitsAzizi DevelopmentsMadinat Al MataarUnder construction12%8 May 202631 Dec 2027
Courtyard One47 unitsGolden Light DevelopmentsMadinat Al MataarUnder construction8%8 May 20261 Sept 2027
Symbolic Altus108 unitsSymbolic DevelopmentsWadi Al Safa 2Under construction1%8 May 20261 May 2027
Boulevard Living 1195 unitsWaslJabal Ali FirstUnder construction0%8 May 20269 Dec 2029
Boulevard Living 2194 unitsWaslJabal Ali FirstUnder construction0%8 May 20269 Dec 2029
Luxury Family Residence Iii72 unitsKappa Acca Real Estate DevelopmentBusiness BayUnder construction51%7 May 202630 Jun 2025 · passed
Parkside Hills370 unitsEmaarHadaeq Sheikh Mohammed Bin RashidUnder construction68%7 May 202630 Jun 2028
The Valley - Nima520 unitsEmaarAl Yufrah 1Under construction80%7 May 2026—
Vento Tower227 unitsAnax DevelopmentsBusiness BayUnder construction34%7 May 2026—
Lucky Oasis Residence144 unitsLucky Aeon Real Estate DevelopmentAl Barsha South FourthUnder construction20%7 May 202630 Jun 2026 · passed
The Orchard Place - Tower C196 unitsPeak Summit Real Estate DevelopmentAl Barsha South FourthUnder construction13%7 May 202631 Mar 2027
Azura Residences148 unitsIGO Real Estate DevelopmentPalm DeiraUnder construction69%7 May 2026—
Binghatti Haven501 unitsBinghatti DevelopersAl Hebiah FourthUnder construction76%7 May 202631 Mar 2026 · passed
Parkwood488 unitsEmaarHadaeq Sheikh Mohammed Bin RashidUnder construction15%7 May 202631 Jan 2029
Elle Residences98 unitsAnax DevelopmentsPalm DeiraUnder construction0%7 May 20261 Sept 2027
Elmora85 unitsNeoterra DevelopmentsAl SatwaUnder construction0%7 May 202615 Feb 2028
Greencrest195 unitsEmaarHadaeq Sheikh Mohammed Bin RashidUnder construction1%7 May 202630 Jun 2029
Golf Terrace Residences By Asak105 unitsAsak Real Estate DevelopmentMe'Aisem FirstUnder construction5%7 May 20262 Oct 2027
Verdana Residence 9256 unitsReportage PropertiesDubai Investment Park FirstUnder construction0%7 May 202631 Mar 2029
Seascape395 unitsEmaarMadinat Dubai AlmelaheyahUnder construction79%6 May 202630 Nov 2026
One Beverly389 unitsHMB Homes Real Estate DevelopmentAl Barshaa South ThirdUnder construction73%6 May 20261 Dec 2026
The Valley - Rivera378 unitsEmaarAl Yufrah 1Under construction4%6 May 202630 Nov 2028
Mbl Signature463 unitsMAG GroupAl Thanyah FifthUnder construction60%6 May 202631 Mar 2027
Grand Polo - Selvara 3138 unitsEmaarDubai Investment Park SecondUnder construction3%6 May 202631 May 2029
Grand Polo - Selvara 4173 unitsEmaarDubai Investment Park SecondUnder construction3%6 May 202631 May 2029
Coventry Living200 unitsGFS Real EstateAl Barsha South FourthUnder construction0%6 May 20261 Jul 2029
Azizi Venice 101,264 unitsAzizi DevelopmentsMadinat Al MataarUnder construction36%5 May 2026—
Damac Hills (2) - Evergreens131 unitsDamac PropertiesMadinat Hind 4Under construction26%5 May 2026—
Marina Views554 unitsEmaarMadinat Dubai AlmelaheyahUnder construction7%5 May 202631 Dec 2028
Sobha Solis2,351 unitsSobhaAl Hebiah FirstUnder construction13%5 May 202631 Dec 2028
Palace Residences Hillside A360 unitsEmaarHadaeq Sheikh Mohammed Bin RashidUnder construction8%5 May 202630 Jun 2029
Taraf 3 Residence151 unitsTarafAl Barsha South FourthUnder construction6%5 May 202631 Mar 2028
Club Drive529 unitsEmaarHadaeq Sheikh Mohammed Bin RashidUnder construction75%4 May 2026—
Address Residences L Dubai Creek Harbour326 unitsEmaarAl Khairan FirstUnder construction26%4 May 202631 Jan 2029
Damac Islands - Maldives 1397 unitsDamac PropertiesAl Yelayiss 1Under construction3%4 May 202631 Dec 2028
Damac Islands - Bali 1294 unitsDamac PropertiesAl Yelayiss 1Under construction3%4 May 202631 Dec 2028

Source: the official project register of the Dubai Land Department and the Real Estate Regulatory Agency (RERA), read every day. A project name with a link opens its page here, with prices, payment plan and site photos.

Percent built

The share of construction finished, measured by RERA inspectors on their latest visit to the site. It is the regulator's figure, not the developer's estimate.

Registered completion date

The date the developer registered for finishing the project. A project can pass it and still be under construction; the date a developer advertises for handover can differ.

Status

Under construction, completed or cancelled, as the register lists the project. Buyers' payments for a registered off-plan project go into its escrow account, which the regulator oversees.

Dubai project status: questions and answers

How many projects are under construction in Dubai?

1,571 projects are registered as under construction in the official project register of the Dubai Land Department (DLD) and its regulator RERA. Another 1,669 are completed and 610 are cancelled. The latest site inspection on record is from 14 October 2026.

How do I check the status of an off-plan project in Dubai?

Type the name of the project, its developer or its district in the search box on this page. All 3,850 registered projects are covered; each one shows its official status, the percent built at the latest site inspection, the date of that inspection and the registered completion date.

What does the percent built mean?

It is the share of construction finished, as measured by RERA inspectors on their latest visit to the site. It is not the developer's own estimate. 830 projects were inspected in the last 90 days.

What is the registered completion date?

It is the completion date the developer registered with the regulator. A project can still be under construction after it: 250 of the 1,571 projects under construction are past their registered date. A developer may also advertise a different handover date.

How often is the project status updated?

Every day. dxbpropy.ai reads the official register daily and re-reads every project once a week, so a new inspection or a change of status shows here within a day or a week.