Citi Developers

Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.

Under construction

5

Units

719

Delivered (all years)

0

Behind schedule

1

Cancelled (all years)

0

Promised for 2026
1
Promised for 2027
4
Promised for 2028
0
Promised for 2029
0
Promised for 2030
0

Sales in this developer's projects

Registered sales by period; the latest figures run to 11 Nov 2026.

PeriodOff-plan salesVilla plots sold on planResales in completed projects
Last 12 months
AED 439.07M
232 sales
––
2026 so far
AED 378.89M
192 sales
––
2025
AED 389.23M
298 sales
––
2024
AED 129.12M
115 sales
––

Latest from developers

Offers, launches and news from developers' sales teams, updated through the day.

Sales-team items from the last 45 days, Instagram posts from the last 90 days; offers pinned to this developer show at any age while they are valid.

  • 5 OctNewsCiti Developers starts main construction of ARYA Residences after completing piling, with New System Engineering appointed main contractor.Instagram ↗
  • 2 OctNewsCiti Developers partners with Capital Zone Mortgages to help buyers explore financing options for their property.Instagram ↗

Projects

% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.

ProjectStatusBuiltHandover dateDLD planned dateNote
Aveline Residences By Citi DevelopersBehind schedule42%Jun 2026Developer statesJul 20265 months past promised handover
Agua Residences By Citi Developers - Tower 1Early stage5%Dec 2027project registerDec 2027
Agua Residences By Citi Developers - Tower 2Early stage3%Dec 2027project registerDec 2027
Arya Residences By Citi DevelopersEarly stage3%Dec 2027project registerDec 2027
Allura Residences By Citi DevelopersEarly stage8%Dec 2027Developer statesJul 2027

Citi Developers: questions and answers

How many projects is Citi Developers building in Dubai?

Citi Developers has 5 projects under construction in Dubai, with 719 homes in total, according to the Dubai Land Department project register.

When do Citi Developers projects hand over?

Handover years for Citi Developers's projects under construction, by the developer's date where it gave one, else the date in new-project listings, else the Dubai Land Department project register's date: 1 project in 2026 and 4 projects in 2027.

Which Citi Developers projects hand over next?

The next Citi Developers projects to hand over are Agua Residences By Citi Developers - Tower 1 (December 2027), Agua Residences By Citi Developers - Tower 2 (December 2027), Arya Residences By Citi Developers (December 2027) and Allura Residences By Citi Developers (December 2027), by the same dates (the developer's where it gave one, else the new-project listings', else the Dubai Land Department project register's).

How far is construction of Citi Developers's projects?

Among Citi Developers's projects under construction, the most advanced are Aveline Residences By Citi Developers (42% built), Allura Residences By Citi Developers (8% built), Agua Residences By Citi Developers - Tower 1 (5% built) and Agua Residences By Citi Developers - Tower 2 (3% built), from official RERA site inspections.