Ellington Properties

Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.

Under construction

33

Units

9,279

Delivered (all years)

22

Behind schedule

5

Cancelled (all years)

0

Promised for 2026
10
Promised for 2027
5
Promised for 2028
8
Promised for 2029
4
Promised for 2030
0

Sales in this developer's projects

Registered sales by period; the latest figures run to 11 Nov 2026.

PeriodOff-plan salesVilla plots sold on planResales in completed projects
Last 12 months
AED 10.1bn
3,680 sales
–
AED 804.53M
404 sales
2026 so far
AED 8.2bn
3,021 sales
–
AED 678.20M
346 sales
2025
AED 7.3bn
2,724 sales
–
AED 987.82M
517 sales
2024
AED 7.7bn
2,502 sales
–
AED 613.28M
426 sales
2023
AED 4.1bn
1,747 sales
–
AED 293.60M
215 sales
2022
AED 1.1bn
870 sales
–
AED 312.40M
244 sales
2021
AED 209.58M
199 sales
–
AED 197.32M
99 sales

Latest from developers

Offers, launches and news from developers' sales teams, updated through the day.

Sales-team items from the last 45 days, Instagram posts from the last 90 days; offers pinned to this developer show at any age while they are valid.

  • 23 OctLaunchEllington Properties launches Berkeley Tower, a commercial development in Business Bay.Instagram ↗
  • 21 OctLaunchEllington Properties launches Berkeley Tower, Grade A commercial high-rise in Business Bay.
  • 17 OctLaunchEllington Properties to launch Grade A 60-storey commercial tower in Business Bay, EOI open.
  • 16 OctLaunchEllington Properties launches Berkeley Tower, a commercial development in Business Bay.
  • 15 OctLaunchEllington Properties teases a new project coming soon to Business Bay.Instagram ↗
  • 30 SeptNewsEllington Properties won International Property Awards for The Crestmark bathroom design and Ocean House kitchen design.Instagram ↗

Projects

% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.

ProjectStatusBuiltHandover dateDLD planned dateNote
The PortmanBehind schedule79%Sept 2025project registerSept 202514 months past promised handover
Uh West By EllingtonBehind schedule84%Mar 2026project registerMar 20268 months past promised handover
Uh East By EllingtonBehind schedule63%Mar 2026project registerMar 20268 months past promised handover
The QuaysideBehind schedule70%Mar 2026project registerMar 20268 months past promised handover
The Waterside Villas By EllingtonBehind schedule45%Jun 2026project registerJun 20265 months past promised handover
The Lakeview Villas By EllingtonSlower than needed20%Aug 2026Listing feed statesAug 2026
The Beachfront Villas By EllingtonSlower than needed47%Aug 2026project registerAug 2026
Art Bay WestSlower than needed15%Sept 2026Listing feed states–
Art Bay EastSlower than needed19%Sept 2026Listing feed states–
Hillmont Residences By EllingtonSlower than needed26%Dec 2026project registerDec 2026
One River PointSlower than needed35%Jun 2027project registerJun 2027
Ellington House IvOn schedule70%––
Rosemont ResidencesOn schedule68%––
The CrestmarkOn schedule61%––
The HighburyOn schedule80%––
Ocean HouseOn schedule81%––
The Lakeshore Villas By EllingtonEarly stage1%Dec 2026Listing feed states–
Claydon House By EllingtonEarly stage16%Jun 2027Developer statesDec 2027 6 months later on DLD than advertised
Mercer HouseEarly stage18%Jul 2027project registerJul 2027
Belmore ResidencesEarly stage7%Dec 2027project registerDec 2027
Riverton HouseEarly stage0%Dec 2027project registerDec 2027
The Watercrest By EllingtonEarly stage2%Mar 2028project registerMar 2028
Eaton SquareEarly stage5%Jun 2028project registerJun 2028
The HillgateEarly stage3%Jun 2028project registerJun 2028
Belgravia GardensEarly stage3%Sept 2028project registerSept 2028
Eltiera HeightsEarly stage3%Dec 2028project registerDec 2028
Ellington Sands IiEarly stage0%Dec 2028Listing feed statesDec 2028
Ellington Sands IEarly stage0%Dec 2028project registerDec 2028
The HighgroveEarly stage7%Dec 2028project registerDec 2028
Windsor HouseEarly stage3%Jul 2029project registerJul 2029
Windsor House IiEarly stage1%Sept 2029Listing feed statesJul 2029
Eltiera ViewsEarly stage0%Dec 2029project registerDec 2029
Portside SquareEarly stage0%Dec 2029project registerDec 2029
Arbor ViewDelivered100%Apr 2026–
Belmont ResidencesDelivered100%Aug 2026–
BelgraviaDelivered100%Apr 2017Apr 2017
Belgravia SquareDelivered100%Nov 2023Nov 2023
Somerset MewsDelivered100%May 2018May 2018
Belgravia 2Delivered100%Feb 2019Feb 2019
Eaton PlaceDelivered100%Sept 2019Sept 2019
Dt 1Delivered100%Mar 2020Mar 2020
Belgravia IiiDelivered100%Dec 2021Dec 2021
Wilton TerracesDelivered100%Dec 2021Dec 2021
Belgravia Heights IDelivered100%Oct 2022Oct 2022
Harrington HouseDelivered100%Nov 2022Nov 2022
Wilton Park ResidencesDelivered100%Jun 2023Jun 2023
Oakley Square ResidencesDelivered100%Dec 2023Dec 2023
Kensington WatersDelivered100%Jun 2024Jun 2024
Ellington Beach HouseDelivered100%Jul 2024Jul 2024
Belgravia Heights IiDelivered100%Sept 2024Sept 2024
Berkeley PlaceDelivered100%Dec 2024Dec 2024
Hamilton HouseDelivered100%Jan 2025Jan 2025
Ellington HouseDelivered100%Feb 2025Feb 2025
Ellington House IiDelivered100%Apr 2025Apr 2025
Ellington House IiiDelivered100%Jul 2025Jul 2025

Ellington Properties: questions and answers

How many projects is Ellington Properties building in Dubai?

Ellington Properties has 33 projects under construction in Dubai, with 9,279 homes in total, according to the Dubai Land Department project register.

How many projects has Ellington Properties delivered in Dubai?

Ellington Properties has delivered 22 of the 55 projects the Dubai Land Department project register lists for it.

When do Ellington Properties projects hand over?

Handover years for Ellington Properties's projects under construction, by the developer's date where it gave one, else the date in new-project listings, else the Dubai Land Department project register's date: 10 projects in 2026, 5 projects in 2027, 8 projects in 2028 and 4 projects in 2029.

Which Ellington Properties projects hand over next?

The next Ellington Properties projects to hand over are Hillmont Residences By Ellington (December 2026), The Lakeshore Villas By Ellington (December 2026), One River Point (June 2027) and Claydon House By Ellington (June 2027), by the same dates (the developer's where it gave one, else the new-project listings', else the Dubai Land Department project register's).

How far is construction of Ellington Properties's projects?

Among Ellington Properties's projects under construction, the most advanced are Uh West By Ellington (84% built), Ocean House (81% built), The Highbury (80% built) and The Portman (79% built), from official RERA site inspections.