Ellington Properties
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date.
Under construction
32
Units
8,866
Delivered
22
Behind schedule
4
Cancelled
0
Handovers 2026
10
Handovers 2027
5
Handovers 2028
8
Handovers 2029
3
Handovers 2030
0
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| The Portman | Behind schedule | 79% | Sept 2025 | Sept 2025 | 12 months past promised handover |
| Uh West By Ellington | Behind schedule | 71% | Mar 2026 | Mar 2026 | 7 months past promised handover |
| Uh East By Ellington | Behind schedule | 47% | Mar 2026 | Mar 2026 | 6 months past promised handover |
| The Quayside | Behind schedule | 55% | Mar 2026 | Mar 2026 | 6 months past promised handover |
| The Waterside Villas By Ellington | Slower than needed | 32% | Jun 2026 | Jun 2026 | |
| The Beachfront Villas By Ellington | Slower than needed | 35% | Aug 2026 | Aug 2026 | |
| Hillmont Residences By Ellington | Slower than needed | 26% | Dec 2026 | Dec 2026 | |
| One River Point | Slower than needed | 35% | Jun 2027 | Jun 2027 | |
| Ellington House Iv | On schedule | 70% | – | – | |
| The Crestmark | On schedule | 61% | – | – | |
| The Highbury | On schedule | 80% | – | – | |
| Rosemont Residences | On schedule | 43% | – | – | |
| Ocean House | On schedule | 81% | – | – | |
| The Lakeview Villas By Ellington | Early stage | 10% | Aug 2026 | Aug 2026 | |
| Art Bay West | Early stage | 9% | Sept 2026 | – | |
| Art Bay East | Early stage | 10% | Sept 2026 | – | |
| The Lakeshore Villas By Ellington | Early stage | 1% | Dec 2026 | – | |
| Claydon House By Ellington | Early stage | 16% | Jun 2027 | Dec 2027 | 6 months later on DLD than advertised |
| Mercer House | Early stage | 18% | Jul 2027 | Jul 2027 | |
| Belmore Residences | Early stage | 7% | Dec 2027 | Dec 2027 | |
| Riverton House | Early stage | 0% | Dec 2027 | Dec 2027 | |
| The Watercrest By Ellington | Early stage | 2% | Mar 2028 | Mar 2028 | |
| Eaton Square | Early stage | 5% | Jun 2028 | Jun 2028 | |
| The Hillgate | Early stage | 3% | Jun 2028 | Jun 2028 | |
| Belgravia Gardens | Early stage | 3% | Sept 2028 | Sept 2028 | |
| Ellington Sands Ii | Early stage | 0% | Dec 2028 | Dec 2028 | |
| Eltiera Heights | Early stage | 3% | Dec 2028 | Dec 2028 | |
| Ellington Sands I | Early stage | 0% | Dec 2028 | Dec 2028 | |
| The Highgrove | Early stage | 7% | Dec 2028 | Dec 2028 | |
| Windsor House | Early stage | 3% | Jul 2029 | Jul 2029 | |
| Windsor House Ii | Early stage | 1% | Sept 2029 | Jul 2029 | |
| Eltiera Views | Early stage | 0% | Dec 2029 | Dec 2029 | |
| Arbor View | Delivered | 100% | Apr 2026 | – | |
| Belmont Residences | Delivered | 100% | Aug 2026 | – | |
| Belgravia | Delivered | 100% | Apr 2017 | Apr 2017 | |
| Belgravia Square | Delivered | 100% | Nov 2023 | Nov 2023 | |
| Somerset Mews | Delivered | 100% | May 2018 | May 2018 | |
| Belgravia 2 | Delivered | 100% | Feb 2019 | Feb 2019 | |
| Eaton Place | Delivered | 100% | Sept 2019 | Sept 2019 | |
| Dt 1 | Delivered | 100% | Mar 2020 | Mar 2020 | |
| Belgravia Iii | Delivered | 100% | Dec 2021 | Dec 2021 | |
| Wilton Terraces | Delivered | 100% | Dec 2021 | Dec 2021 | |
| Belgravia Heights I | Delivered | 100% | Oct 2022 | Oct 2022 | |
| Harrington House | Delivered | 100% | Nov 2022 | Nov 2022 | |
| Wilton Park Residences | Delivered | 100% | Jun 2023 | Jun 2023 | |
| Oakley Square Residences | Delivered | 100% | Dec 2023 | Dec 2023 | |
| Kensington Waters | Delivered | 100% | Jun 2024 | Jun 2024 | |
| Ellington Beach House | Delivered | 100% | Jul 2024 | Jul 2024 | |
| Belgravia Heights Ii | Delivered | 100% | Sept 2024 | Sept 2024 | |
| Berkeley Place | Delivered | 100% | Dec 2024 | Dec 2024 | |
| Hamilton House | Delivered | 100% | Jan 2025 | Jan 2025 | |
| Ellington House | Delivered | 100% | Feb 2025 | Feb 2025 | |
| Ellington House Ii | Delivered | 100% | Apr 2025 | Apr 2025 | |
| Ellington House Iii | Delivered | 100% | Jul 2025 | Jul 2025 |
✦ Ask about any developer
Track record, projects handing over by year and construction progress — from official records.