← All developers

Azizi Developments

Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.

Under construction

57

Units

38,809

Delivered (all years)

91

Behind schedule

10

Cancelled (all years)

7

Promised for 2026
4
Promised for 2027
28
Promised for 2028
12
Promised for 2029
0
Promised for 2030
1

Sales in this developer's projects

Registered sales by period; the latest figures run to 11 Nov 2026.

PeriodOff-plan salesVilla plots sold on planResales in completed projects
Last 12 months
AED 12.5bn
14,572 sales
–
AED 1.9bn
1,850 sales
2026 so far
AED 12.0bn
14,067 sales
–
AED 1.5bn
1,471 sales
2025
AED 3.0bn
3,365 sales
–
AED 2.3bn
2,410 sales
2024
AED 6.7bn
6,901 sales
–
AED 1.8bn
2,103 sales
2023
AED 2.7bn
3,366 sales
–
AED 901.38M
1,133 sales
2022
AED 1.6bn
1,992 sales
–
AED 503.03M
648 sales
2021
AED 692.81M
832 sales
–
AED 143.83M
196 sales

Latest from developers

Offers, launches and news from developers' sales teams, updated through the day.

Sales-team items from the last 45 days, Instagram posts from the last 90 days; offers pinned to this developer show at any age while they are valid.

  • 16 OctNewsAzizi Florence payment plan revised from 30/70 to 40/60 from 1 November 2026.
  • 1 OctNewsBurj Azizi partners with KONE to supply 59 elevators and 15 escalators for the 725-metre tower.Instagram ↗

Projects

% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.

ProjectStatusBuiltHandover dateDLD planned dateNote
Azizi GrandBehind schedule82%Feb 2025project registerFeb 202521 months past promised handover
Azizi Riviera ReveBehind schedule77%Jun 2025Listing feed statesFeb 202517 months past promised handover
Azizi Venice 5Behind schedule63%Oct 2025project registerOct 202513 months past promised handover
Azizi Venice 3Behind schedule76%Dec 2025project registerDec 202511 months past promised handover
Azizi Venice 4Behind schedule62%Dec 2025project registerDec 202511 months past promised handover
Azizi Venice 1Behind schedule67%Dec 2025project registerDec 202511 months past promised handover
Azizi Venice 2Behind schedule57%Dec 2025project registerDec 202511 months past promised handover
Azizi Venice 7Behind schedule29%Jan 2026project registerJan 202610 months past promised handover
Beach Oasis 2Behind schedule53%Apr 2026project registerApr 20267 months past promised handover
Azizi Venice 14Behind schedule30%May 2026project registerMay 20266 months past promised handover
Azizi Riviera 49Slower than needed54%Mar 2027Listing feed statesMar 2027
Azizi Riviera 50Slower than needed61%Mar 2027Listing feed statesMar 2027
Azizi NeilaSlower than needed39%Jul 2027Listing feed statesJul 2027
Azizi Venice 11Slower than needed26%Aug 2027project registerAug 2027
Azizi Venice 13Slower than needed46%Sept 2027Listing feed statesSept 2027
Azizi Venice 8On schedule53%––
Azizi Venice 9On schedule54%––
Adeba AziziOn schedule75%––
Azizi Venice 10On schedule36%––
Azizi JewelOn schedule43%––
Azizi Riviera 62On schedule91%Mar 2027Listing feed statesMar 2027
ِِAzizi Riviera 60On schedule97%Mar 2027Listing feed statesMar 2027
Azizi Riviera 53On schedule63%Mar 2027Listing feed statesMar 2027
Azizi Riviera 68On schedule75%May 2027Listing feed statesMay 2027
Azizi Riviera 54On schedule75%May 2027Listing feed statesMay 2027
Azizi Riviera 66On schedule91%May 2027Listing feed statesMay 2027
Azizi Riviera 64On schedule84%Jun 2027Listing feed statesMay 2027
Azizi ZainOn schedule80%Oct 2027project registerOct 2027
Azizi RubyEarly stage3%Dec 2026Listing feed statesJan 2028 13 months later on DLD than advertised
Azizi Milan 51Early stage0%Mar 2027Listing feed statesMar 2027
Azizi Milan 30Early stage0%Apr 2027Listing feed statesApr 2027
Azizi Milan 18Early stage0%Apr 2027Listing feed statesApr 2027
Azizi Milan 55Early stage0%Apr 2027Listing feed statesApr 2027
Azizi Milan 53Early stage0%Apr 2027Listing feed statesApr 2027
Azizi Milan 20Early stage0%Apr 2027Listing feed statesApr 2027
Azizi Venice 15Early stage0%May 2027Listing feed statesMay 2027
Azizi Milan 9Early stage0%May 2027Listing feed statesMay 2027
Azizi Venice 16Early stage0%Jun 2027project registerJun 2027
Azizi Milan 28Early stage0%Jun 2027Listing feed statesJun 2027
Azizi SikanderEarly stage2%Jun 2027project registerJun 2027
Azizi AmirEarly stage2%Jun 2027project registerJun 2027
Azizi AbrahamEarly stage2%Aug 2027Listing feed statesAug 2027
Azizi Venice 12Early stage22%Sept 2027Listing feed statesSept 2027
Azizi Venice 6Early stage12%Dec 2027project registerDec 2027
Raffi By AziziEarly stage2%Jan 2028project registerJan 2028
Arian By AziziEarly stage2%Jan 2028Listing feed statesJan 2028
Wasl By AziziEarly stage2%Feb 2028project registerFeb 2028
Azizi EmeraldEarly stage3%Feb 2028project registerFeb 2028
Azizi WaresEarly stage2%Mar 2028project registerMar 2028
Azizi RoseEarly stage0%Jul 2028project registerJul 2028
Azizi GabrielEarly stage0%Jul 2028project registerJul 2028
Azizi NouraEarly stage0%Jul 2028project registerJul 2028
Azizi Milan HeightsEarly stage0%Sept 2028Listing feed statesSept 2028
Azizi LeilyEarly stage2%Sept 2028project registerSept 2028
Azizi LinaEarly stage2%Sept 2028project registerSept 2028
Azizi DavidEarly stage2%Sept 2028project registerSept 2028
Burj AziziEarly stage7%Aug 2030project registerAug 2030
Azizi. TulipDelivered100%May 2016May 2016
Azizi. DaisyDelivered100%May 2016May 2016
Azizi. YasamineDelivered100%Jul 2016Jul 2016
Azizi. FeirouzDelivered100%Sept 2016Sept 2016
Azizi. LiatrisDelivered100%Oct 2016Oct 2016
Azizi. FreesiaDelivered100%Nov 2016Nov 2016
Azizi. OrchidDelivered100%Nov 2016Nov 2016
Royal BayDelivered100%Jan 2017Jan 2017
Azizi. IrisDelivered100%Feb 2017Feb 2017
Candace Aster Hotel ApartmentsDelivered100%Sept 2017Sept 2017
Candace Acacia Hotel ApartmentsDelivered100%Nov 2017Nov 2017
Roy Mediterranean Hotel ApartmentsDelivered100%Mar 2018Mar 2018
Montrell Hotel AprtmentsDelivered100%Mar 2018Mar 2018
Azizi Aliyah ResidencesDelivered100%Aug 2019Aug 2019
Azizi Samia ResidenceDelivered100%Jan 2020Jan 2020
Azizi Farishta ResidenceDelivered100%Mar 2020Mar 2020
Azizi Plaza Hotel ApartmentsDelivered100%May 2020May 2020
Azizi Aura ResidencesDelivered100%May 2020May 2020
Azizi MinaDelivered100%Jan 2021Jan 2021
Azizi Shaista ResidenceDelivered100%Mar 2021Mar 2021
Azizi Star Hotel ApartmentsDelivered100%Jan 2022Jan 2022
Azizi Riviera 13Delivered100%Apr 2022Apr 2022
Farhad Azizi ResidenceDelivered100%Jul 2022Jul 2022
Azizi Riviera 7Delivered100%Aug 2022Aug 2022
Azizi Riviera 2Delivered100%Sept 2022Sept 2022
Azizi Riviera 6Delivered100%Sept 2022Sept 2022
Azizi Riviera 12Delivered100%Sept 2022Sept 2022
Azizi Riviera 16Delivered100%Sept 2022Sept 2022
Azizi Riviera 11Delivered100%Sept 2022Sept 2022
Azizi Riviera 4Delivered100%Sept 2022Sept 2022
Azizi Riviera 17Delivered100%Sept 2022Sept 2022
Azizi Riviera 10Delivered100%Sept 2022Sept 2022
Azizi Riviera 14Delivered100%Sept 2022Sept 2022
Azizi Riviera 23Delivered100%Dec 2022Dec 2022
Azizi Riviera 20Delivered100%Dec 2022Dec 2022
Azizi Riviera 24Delivered100%Mar 2023Mar 2023
Azizi Riviera 5Delivered100%May 2023May 2023
Azizi Riviera 8Delivered100%Jun 2023Jun 2023
Azizi Riviera 9Delivered100%Jun 2023Jun 2023
Azizi Riviera 30Delivered100%Jun 2023Jun 2023
Azizi Riviera 32Delivered100%Jun 2023Jun 2023
Azizi Riviera 27Delivered100%Jun 2023Jun 2023
Azizi Riviera 21Delivered100%Jun 2023Jun 2023
Azizi Riviera 26Delivered100%Jun 2023Jun 2023
Azizi Riviera 25Delivered100%Jun 2023Jun 2023
Azizi Riviera 31Delivered100%Jun 2023Jun 2023
Azizi Riviera 22Delivered100%Jun 2023Jun 2023
Azizi Riviera 29Delivered100%Jun 2023Jun 2023
Azizi Riviera 18Delivered100%Jul 2023Jul 2023
Azizi Riviera 15Delivered100%Jul 2023Jul 2023
Azizi BertonDelivered100%Aug 2023Aug 2023
Azizi Riviera 28Delivered100%Sept 2023Sept 2023
Azizi Riviera 33Delivered100%Sept 2023Sept 2023
Azizi Riviera 34Delivered100%Sept 2023Sept 2023
Azizi Riviera 35Delivered100%Sept 2023Sept 2023
Azizi Riviera 19Delivered100%Oct 2023Oct 2023
Azizi GardensDelivered100%Dec 2023Dec 2023
Azizi Park AvenueDelivered100%Jan 2024Jan 2024
Azizi Riviera 47Delivered100%Jan 2024Jan 2024
Azizi Riviera 41Delivered100%Jan 2024Jan 2024
Azizi Riviera 42Delivered100%Jan 2024Jan 2024
Azizi Riviera 45Delivered100%Jan 2024Jan 2024
Azizi Riviera 36Delivered100%Jan 2024Jan 2024
Azizi Riviera 44Delivered100%Jan 2024Jan 2024
Azizi Riviera 46Delivered100%Jan 2024Jan 2024
Azizi Riviera 38Delivered100%Jan 2024Jan 2024
Azizi Riviera 43Delivered100%Jan 2024Jan 2024
Azizi Riviera 39Delivered100%Mar 2024Mar 2024
Azizi Riviera 48Delivered100%Mar 2024Mar 2024
Azizi Riviera 37Delivered100%Mar 2024Mar 2024
Fawad Azizi ResidenceDelivered100%Apr 2024Apr 2024
Azizi Riviera 3Delivered100%May 2024May 2024
Azizi Riviera 40Delivered100%May 2024May 2024
Azizi PearlDelivered100%Jun 2024Jun 2024
Azizi GreenfieldDelivered100%Mar 2024Mar 2024
Azizi Riviera 1Delivered100%Jul 2024Jul 2024
Azizi Riviera 61Delivered100%Mar 2025Mar 2025
Azizi Riviera 65Delivered100%Mar 2025Mar 2025
Azizi Riviera 63Delivered100%Feb 2025Feb 2025
Azizi Riviera 59Delivered100%Feb 2025Feb 2025
Azizi Riviera 67Delivered100%Mar 2025Mar 2025
Azizi Mirage 1Delivered100%Apr 2025Apr 2025
Azizi AmberDelivered100%Jul 2025Jul 2025
Azizi VistaDelivered100%Apr 2025Apr 2025
Azizi Riviera AzureDelivered100%Jul 2025Jul 2025
Azizi Riviera BeachfrontDelivered100%Dec 2025Dec 2025
Azizi CentralDelivered100%Jun 2026–
Azizi Riviera 69Delivered100%Mar 2026Mar 2026
Azizi Riviera 55Delivered100%Jan 2026Mar 2027
Azizi Riviera 56Delivered100%Apr 2026Mar 2027
Azizi Riviera 58Delivered100%Aug 2026May 2027
Al Masa IiCancelled0%––
Azizi Yasamine IiiCancelled0%––
Yasamine -VCancelled0%––
Al Masa ICancelled0%––
Azizi Yasamine 4Cancelled0%––
Azizi Victoria 4Cancelled7%Dec 2021project registerDec 2021
Azizi Victoria 5Cancelled0%Nov 2022project registerNov 2022

Azizi Developments: questions and answers

How many projects is Azizi Developments building in Dubai?

Azizi Developments has 57 projects under construction in Dubai, with 38,809 homes in total, according to the Dubai Land Department project register.

How many projects has Azizi Developments delivered in Dubai?

Azizi Developments has delivered 91 of the 155 projects the Dubai Land Department project register lists for it.

When do Azizi Developments projects hand over?

Handover years for Azizi Developments's projects under construction, by the developer's date where it gave one, else the date in new-project listings, else the Dubai Land Department project register's date: 4 projects in 2026, 28 projects in 2027, 12 projects in 2028 and 1 project in 2030.

Which Azizi Developments projects hand over next?

The next Azizi Developments projects to hand over are Azizi Ruby (December 2026), Azizi Riviera 49 (March 2027), Azizi Riviera 62 (March 2027) and ِِAzizi Riviera 60 (March 2027), by the same dates (the developer's where it gave one, else the new-project listings', else the Dubai Land Department project register's).

How far is construction of Azizi Developments's projects?

Among Azizi Developments's projects under construction, the most advanced are ِِAzizi Riviera 60 (97% built), Azizi Riviera 66 (91% built), Azizi Riviera 62 (91% built) and Azizi Riviera 64 (84% built), from official RERA site inspections.