Reportage Properties

Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.

Under construction

25

Units

9,066

Delivered (all years)

1

Behind schedule

4

Cancelled (all years)

0

Promised for 2026
2
Promised for 2027
2
Promised for 2028
13
Promised for 2029
4
Promised for 2030
0

Sales in this developer's projects

Registered sales by period; the latest figures run to 11 Nov 2026.

PeriodOff-plan salesVilla plots sold on planResales in completed projects
Last 12 months
AED 1.3bn
738 sales
–
AED 21.46M
33 sales
2026 so far
AED 1.2bn
639 sales
–
AED 13.15M
21 sales
2025
AED 1.7bn
1,103 sales
–
AED 57.48M
101 sales
2024
AED 1.3bn
1,011 sales
––
2023
AED 290.51M
321 sales
––
2022
AED 55.22M
123 sales
––
2021
AED 40.85M
85 sales
––

Latest from developers

Offers, launches and news from developers' sales teams, updated through the day.

Sales-team items from the last 45 days, Instagram posts from the last 90 days; offers pinned to this developer show at any age while they are valid.

  • 12 NovLaunchReportage Properties unveils VERSO and ÉPOQUE, its first two projects in Dubai's Meydan Horizon.Instagram ↗
  • 10 OctLaunchVerso by Reportage marks the developer's Meydan Horizon debut with 174 contemporary 1-, 2- and 4-bedroom apartments in a mixed-use tower.
  • 10 OctLaunchÉpoque by Reportage offers 60 boutique 2- to 4-bedroom residences overlooking the lagoon and boardwalk at Meydan Horizon.
  • 2 OctLaunchReportage Properties unveils VERSO and ÉPOQUE, its first two projects in Dubai's Meydan Horizon.
  • 2 OctLaunchReportage Properties unveils VERSO and ÉPOQUE, its first two projects in Dubai's Meydan Horizon.

Projects

% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.

ProjectStatusBuiltHandover dateDLD planned dateNote
Verdana (Phase 1)Behind schedule95%Dec 2025project registerDec 202511 months past promised handover
Verdana(Phase 2)Behind schedule94%Dec 2025project registerDec 202511 months past promised handover
Verdana ResidenceBehind schedule96%Dec 2025project registerDec 202511 months past promised handover
Verdana Residence 2Behind schedule20%Apr 2026Listing feed statesApr 20267 months past promised handover
BiancaSlower than needed56%Dec 2026project registerDec 2026
Reportage Village 1Slower than needed25%Dec 2027project registerDec 2027
Verdana 2On schedule56%––
Taormina Village 1Early stage20%Dec 2027Listing feed statesDec 2027
Reportage HillsEarly stage0%Jun 2028project registerJun 2028
Verdana 3Early stage0%Sept 2028project registerSept 2028
Verdana 4Early stage0%Sept 2028project registerSept 2028
Verdana Residence 5Early stage0%Sept 2028project registerSept 2028
Verdana 5Early stage0%Sept 2028Listing feed statesSept 2028
Verdana Residence 4Early stage0%Sept 2028Listing feed statesSept 2028
Verdana Residence 3Early stage0%Sept 2028Listing feed statesSept 2028
Verdana Residence 6Early stage0%Dec 2028project registerDec 2028
Verdana Residence 8Early stage0%Dec 2028project registerDec 2028
Verdana 6Early stage0%Dec 2028project registerDec 2028
Verdana 7Early stage0%Dec 2028project registerDec 2028
Verdana Residence 7Early stage0%Dec 2028Listing feed statesDec 2028
Verdana 8Early stage0%Dec 2028Listing feed statesDec 2028
Verdana 9Early stage0%Mar 2029project registerMar 2029
Verdana 10Early stage0%Mar 2029project registerMar 2029
Verdana Residence 9Early stage0%Mar 2029Listing feed statesMar 2029
Verdana Residence 10Early stage0%Mar 2029Listing feed statesMar 2029
Alexis TowerDelivered100%May 2024May 2024

Reportage Properties: questions and answers

How many projects is Reportage Properties building in Dubai?

Reportage Properties has 25 projects under construction in Dubai, with 9,066 homes in total, according to the Dubai Land Department project register.

How many projects has Reportage Properties delivered in Dubai?

Reportage Properties has delivered 1 of the 26 projects the Dubai Land Department project register lists for it.

When do Reportage Properties projects hand over?

Handover years for Reportage Properties's projects under construction, by the developer's date where it gave one, else the date in new-project listings, else the Dubai Land Department project register's date: 2 projects in 2026, 2 projects in 2027, 13 projects in 2028 and 4 projects in 2029.

Which Reportage Properties projects hand over next?

The next Reportage Properties projects to hand over are Bianca (December 2026), Taormina Village 1 (December 2027), Reportage Village 1 (December 2027) and Reportage Hills (June 2028), by the same dates (the developer's where it gave one, else the new-project listings', else the Dubai Land Department project register's).

How far is construction of Reportage Properties's projects?

Among Reportage Properties's projects under construction, the most advanced are Verdana Residence (96% built), Verdana (Phase 1) (95% built), Verdana(Phase 2) (94% built) and Bianca (56% built), from official RERA site inspections.