Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date.

Under construction

37

Units

34,040

Delivered

42

Behind schedule

7

Cancelled

0

Handovers 2026
15
Handovers 2027
18
Handovers 2028
4
Handovers 2029
0
Handovers 2030
0

Projects

% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.

ProjectStatusBuiltHandover dateDLD planned dateNote
Binghatti RubyBehind schedule46%Mar 2026Feb 20266 months past promised handover
Binghatti HavenBehind schedule76%Mar 2026Mar 20266 months past promised handover
Binghatti TwilightBehind schedule55%Mar 2026Apr 20266 months past promised handover
Binghatti GroveBehind schedule84%Mar 2026Mar 20266 months past promised handover
Binghatti StarlightBehind schedule63%Mar 2026Mar 20266 months past promised handover
Binghatti AmberhallBehind schedule38%Mar 2026Feb 20266 months past promised handover
Binghatti HillsBehind schedule90%Jun 2026–3 months past promised handover
Binghatti EliteSlower than needed53%Jun 2026Jun 2026
Binghatti HillsideSlower than needed80%Jun 2026Jun 2026
Binghatti SkyhallSlower than needed31%Sept 2026Aug 2026
Binghatti HillviewsSlower than needed33%Dec 2026Apr 2026
One By BinghattiSlower than needed50%Dec 2026May 2026
Burj Binghatti Jacob & Co. ResidencesSlower than needed52%Jun 2027Jun 2026
Binghatti HillcrestOn schedule60%Dec 2026Dec 2026
Mercedes-Benz Places | BinghattiOn schedule65%Mar 2027Dec 2026
Binghatti MoonlightEarly stage19%Jun 2026Jun 2026
Binghatti SkyriseEarly stage22%Dec 2026Dec 2026
Binghatti TitaniaEarly stage0%Feb 2027Feb 2027
Binghatti VintageEarly stage0%Mar 2027Mar 2027
Binghatti AquariseEarly stage21%Mar 2027Oct 2026
Project MaybachEarly stage0%Jun 2027Jun 2027
Binghatti CircleEarly stage10%Jun 2027May 2027
Binghatti CullinanEarly stage0%Jun 2027Jun 2027
Binghatti Flare 01Early stage20%Jul 2027Jul 2027
Binghatti EthereaEarly stage7%Jul 2027Dec 2027 5 months later on DLD than advertised
Binghatti Flare 02Early stage18%Sept 2027Jun 2027
Binghatti LuxuriaEarly stage7%Sept 2027Jul 2027
Binghatti SkyterracesEarly stage0%Oct 2027Oct 2027
Binghatti WraithEarly stage0%Dec 2027Dec 2027
Binghatti Skyflame 1Early stage0%Dec 2027Dec 2027
Binghatti Skyflame 2Early stage0%Dec 2027Dec 2027
Binghatti SkybladeEarly stage17%Dec 2027Nov 2027
Maybach Ultimate LuxuryEarly stage0%Jun 2028Aug 2027
Maybach SixEarly stage0%Jun 2028Aug 2027
Binghatti StarfallEarly stage0%Sept 2028Oct 2027
Vision IconicEarly stage0%Dec 2028Dec 2028
Bugatti Residences By BinghattiNot enough data52%Sept 2027Dec 2025
Binghatti PhoenixDelivered100%Oct 2025–
Binghatti ApartmentsDelivered100%Sept 2015Sept 2015
Binghatti ViewsDelivered100%Apr 2017Apr 2017
Binghatti StarsDelivered100%Jan 2020Jan 2020
Binghatti GatewayDelivered100%Jun 2021Jun 2021
Millennium Binghatti Residences Business BayDelivered100%Jul 2021Jul 2021
Binghatti GateDelivered100%Jan 2022Jan 2022
Binghatti PointDelivered100%Feb 2022Feb 2022
Binghatti AvenueDelivered100%Apr 2022Apr 2022
Binghatti RoseDelivered100%Apr 2022Apr 2022
Binghatti MirageDelivered100%Jun 2022Jun 2022
Binghatti GemsDelivered100%Jun 2022Jun 2022
Binghatti JasmineDelivered100%Jan 2023Jan 2023
Binghatti CreekDelivered100%Apr 2023Apr 2023
Binghatti CanalDelivered100%Jun 2023Jun 2023
Binghatti HeightsDelivered100%Aug 2023Aug 2023
Binghatti CrescentDelivered100%Oct 2023Oct 2023
Binghatti LunaDelivered100%Oct 2023Oct 2023
Binghatti NovaDelivered100%Oct 2023Oct 2023
Binghatti CrestDelivered100%Oct 2023Oct 2023
Binghatti EmeraldDelivered100%Feb 2024Feb 2024
Binghatti CornerDelivered100%Mar 2024Mar 2024
Trillionaire Residences By BinghattiDelivered100%Jun 2024Jun 2024
Binghatti HouseDelivered100%Jul 2024Jul 2024
Binghatti VenusDelivered100%Aug 2024Aug 2024
Binghatti OrchidDelivered100%Dec 2024–
Binghatti GalaxyDelivered100%Mar 2025–
Binghatti GardeniaDelivered100%Jul 2024Jul 2024
Binghatti OnyxDelivered100%Oct 2024Oct 2024
Binghatti AmberDelivered100%Oct 2024Oct 2024
Binghatti LavenderDelivered100%Oct 2024Oct 2024
Dusk By BinghattiDelivered100%Dec 2024Dec 2024
Binghatti TulipDelivered100%Mar 2025–
Binghatti AzureDelivered100%Dec 2024Dec 2024
Dawn By BinghattiDelivered100%Dec 2024Dec 2024
Binghatti AuroraDelivered100%Dec 2025Dec 2025
Binghatti PhantomDelivered100%Oct 2025–
Binghatti RoyaleDelivered100%Oct 2025–
Binghatti PinnacleDelivered100%Dec 2025Dec 2025
Binghatti IvoryDelivered100%Dec 2025Dec 2025
Binghatti GhostDelivered100%Mar 2026Mar 2026
Binghatti ApexDelivered100%Apr 2026Apr 2026