Iman Developers
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date.
Under construction
9
Units
3,438
Delivered
8
Behind schedule
1
Cancelled
0
Handovers 2026
2
Handovers 2027
1
Handovers 2028
3
Handovers 2029
2
Handovers 2030
0
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| 10 Oxford By Iman | Behind schedule | 91% | Dec 2025 | – | 9 months past promised handover |
| Gardens 2 | Slower than needed | 68% | Jun 2026 | Dec 2025 | |
| Oxford Cove | Early stage | 0% | Dec 2026 | Mar 2029 | 27 months later on DLD than advertised |
| One Park Central By Iman | Early stage | 20% | Jun 2027 | Jun 2027 | |
| One Sky Park By Iman | Early stage | 9% | Mar 2028 | Mar 2028 | |
| One Park Square By Iman | Early stage | 20% | Jun 2028 | Jun 2028 | |
| 15 Cascade | Early stage | 6% | Dec 2028 | Sept 2028 | |
| 113 Residences | Early stage | 0% | Feb 2029 | Feb 2029 | |
| Sierra By Iman | Early stage | 4% | Jun 2029 | Jun 2029 | |
| Oxford Residence | Delivered | 100% | Feb 2018 | Feb 2018 | |
| Oxford Residence 2 | Delivered | 100% | Apr 2020 | Apr 2020 | |
| Oxford Boulevard | Delivered | 100% | Oct 2021 | Oct 2021 | |
| Oxford 212 | Delivered | 100% | Feb 2023 | Feb 2023 | |
| Oxford Terraces | Delivered | 100% | Jan 2024 | Jan 2024 | |
| Oxford Gardens | Delivered | 100% | Mar 2025 | Mar 2025 | |
| Oxford Terraces 2 | Delivered | 100% | Nov 2024 | Nov 2024 | |
| The Grove By Iman | Delivered | 100% | Aug 2024 | Aug 2024 |
✦ Ask about any developer
Track record, projects handing over by year and construction progress — from official records.