Iman Developers
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.
Under construction
9
Units
3,438
Delivered (all years)
8
Behind schedule
2
Cancelled (all years)
0
Sales in this developer's projects
Registered sales by period; the latest figures run to 11 Nov 2026.
| Period | Off-plan sales | Villa plots sold on plan | Resales in completed projects |
|---|---|---|---|
| Last 12 months | AED 1.5bn 1,050 sales | – | AED 131.83M 126 sales |
| 2026 so far | AED 1.4bn 953 sales | – | AED 92.10M 89 sales |
| 2025 | AED 1.7bn 1,321 sales | – | AED 240.28M 206 sales |
| 2024 | AED 1.4bn 1,412 sales | – | AED 107.38M 121 sales |
| 2023 | AED 348.63M 335 sales | – | AED 105.55M 144 sales |
| 2022 | AED 156.81M 243 sales | – | AED 37.08M 66 sales |
| 2021 | AED 57.76M 103 sales | – | AED 16.37M 32 sales |
Latest from developers
Offers, launches and news from developers' sales teams, updated through the day.
Sales-team items from the last 45 days, Instagram posts from the last 90 days; offers pinned to this developer show at any age while they are valid.
- 28 OctNews10 Oxford by IMAN Developers receives Building Completion Certificate in Jumeirah Village Circle, Dubai.Instagram ↗
- 19 OctOffer6% discount available on Sierra retail units.
- 19 OctOffer6% discount available on Sierra retail units.
- 19 OctOfferFour retail units available at Sierra project.
- 16 OctNewsGardens 2 by IMAN Developers receives Building Completion Certificate in Arjan, Dubai.Instagram ↗
- 12 OctNews113 Residences by IMAN breaks ground in Al Sufouh, Dubai.Instagram ↗
- 30 SeptNewsOxford Cove by Iman Developers held its groundbreaking in Jumeirah Village Circle (JVC).Instagram ↗
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| Gardens 2 | Behind schedule | 68% | Jun 2026Developer states | Dec 2025 | 5 months past promised handover |
| 10 Oxford By Iman | Behind schedule | 91% | Jun 2026Developer states | – | 5 months past promised handover |
| One Park Central By Iman | Slower than needed | 32% | Jun 2027Developer states | Jun 2027 | |
| Oxford Cove | Early stage | 0% | Dec 2026Developer states | Mar 2029 | 27 months later on DLD than advertised |
| One Sky Park By Iman | Early stage | 22% | Mar 2028Developer states | Mar 2028 | |
| One Park Square By Iman | Early stage | 20% | Jun 2028Developer states | Jun 2028 | |
| 15 Cascade | Early stage | 6% | Dec 2028Developer states | Sept 2028 | |
| 113 Residences | Early stage | 0% | Feb 2029project register | Feb 2029 | |
| Sierra By Iman | Early stage | 4% | Jun 2029project register | Jun 2029 | |
| Oxford Residence | Delivered | 100% | Feb 2018 | Feb 2018 | |
| Oxford Residence 2 | Delivered | 100% | Apr 2020 | Apr 2020 | |
| Oxford Boulevard | Delivered | 100% | Oct 2021 | Oct 2021 | |
| Oxford 212 | Delivered | 100% | Feb 2023 | Feb 2023 | |
| Oxford Terraces | Delivered | 100% | Jan 2024 | Jan 2024 | |
| Oxford Gardens | Delivered | 100% | Mar 2025 | Mar 2025 | |
| Oxford Terraces 2 | Delivered | 100% | Nov 2024 | Nov 2024 | |
| The Grove By Iman | Delivered | 100% | Aug 2024 | Aug 2024 |
Iman Developers: questions and answers
How many projects is Iman Developers building in Dubai?
Iman Developers has 9 projects under construction in Dubai, with 3,438 homes in total, according to the Dubai Land Department project register.
How many projects has Iman Developers delivered in Dubai?
Iman Developers has delivered 8 of the 17 projects the Dubai Land Department project register lists for it.
When do Iman Developers projects hand over?
Handover years for Iman Developers's projects under construction, by the developer's date where it gave one, else the date in new-project listings, else the Dubai Land Department project register's date: 3 projects in 2026, 1 project in 2027, 3 projects in 2028 and 2 projects in 2029.
Which Iman Developers projects hand over next?
The next Iman Developers projects to hand over are Oxford Cove (December 2026), One Park Central By Iman (June 2027), One Sky Park By Iman (March 2028) and One Park Square By Iman (June 2028), by the same dates (the developer's where it gave one, else the new-project listings', else the Dubai Land Department project register's).
How far is construction of Iman Developers's projects?
Among Iman Developers's projects under construction, the most advanced are 10 Oxford By Iman (91% built), Gardens 2 (68% built), One Park Central By Iman (32% built) and One Sky Park By Iman (22% built), from official RERA site inspections.