Dubai South

Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.

Under construction

19

Units

3,338

Delivered (all years)

13

Behind schedule

3

Cancelled (all years)

2

Promised for 2026
5
Promised for 2027
1
Promised for 2028
5
Promised for 2029
4
Promised for 2030
1

Sales in this developer's projects

Registered sales by period; the latest figures run to 11 Nov 2026.

PeriodOff-plan salesVilla plots sold on planResales in completed projects
Last 12 months
AED 4.1bn
962 sales
AED 54.80M
6 sales
AED 641.84M
225 sales
2026 so far
AED 2.9bn
705 sales
AED 51.20M
5 sales
AED 444.73M
165 sales
2025
AED 3.5bn
978 sales
AED 32.79M
6 sales
AED 946.92M
345 sales
2024
AED 2.6bn
665 sales
–
AED 373.08M
261 sales
2023
AED 1.9bn
618 sales
AED 550.60M
54 sales
AED 217.55M
207 sales
2022
AED 2.0bn
1,009 sales
–
AED 124.42M
155 sales
2021
AED 265.10M
234 sales
–
AED 48.86M
58 sales

Projects

% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.

ProjectStatusBuiltHandover dateDLD planned dateNote
South Bay 1Behind schedule94%Dec 2025Listing feed statesMar 202511 months past promised handover
South Bay 2Behind schedule94%May 2026Listing feed statesMay 20266 months past promised handover
South Bay 4 PremiumBehind schedule86%Jun 2026Listing feed states–5 months past promised handover
South LivingSlower than needed89%Sept 2026Developer statesFeb 2020
Beachfront Gates 2Slower than needed42%Dec 2026Listing feed statesDec 2026
Beachfront Gates 1Slower than needed36%Dec 2026Listing feed statesDec 2026
South Bay 5 PremiumOn schedule78%––
South Bay 3 PremiumOn schedule88%––
South Bay 6 PremiumOn schedule82%Dec 2027Listing feed states–
Hayat 3Early stage4%May 2028Listing feed statesMay 2028
Hayat 2Early stage2%May 2028Listing feed statesMay 2028
South SquareEarly stage3%Jun 2028Listing feed statesJun 2028
Hayat 4Early stage5%Jul 2028Listing feed statesJul 2028
Hayat 5Early stage3%Sept 2028Listing feed statesJul 2028
Hayat 7Early stage0%Mar 2029Listing feed statesMar 2029
Hayat 6Early stage0%Mar 2029Listing feed statesMar 2029
Hayat 1Early stage0%Mar 2029Listing feed statesMar 2029
Beachfront Gates 3Early stage0%May 2029project registerMay 2029
Hayat 8Early stage0%Apr 2030project registerApr 2030
The Pulse Residence IconDelivered100%Jan 2020Jan 2020
The Pulse ResidenceDelivered100%Feb 2020Feb 2020
The Pulse Boulevard ApartmentsDelivered100%Feb 2020Feb 2020
The Pulse TownhousesDelivered100%Feb 2020Feb 2020
The Pulse Residence ParkDelivered100%Mar 2020Mar 2020
The Pulse Boulevard Apartments - C3Delivered100%Dec 2020Dec 2020
The Pulse Boulevard Apartments-C1Delivered100%Jan 2021Jan 2021
The Pulse Residence PlazaDelivered100%Mar 2021Mar 2021
The Pulse VillasDelivered100%Jun 2023Jun 2023
The Pulse Villas 2Delivered100%Jan 2024Jan 2024
The Pulse Beachfront 2Delivered100%Dec 2024Dec 2024
The Pulse- BeachfrontDelivered100%Dec 2024Dec 2024
The Pulse Beachfront 3Delivered100%Apr 2025Apr 2025
Parklane ResidenceCancelled0%Feb 2020project registerFeb 2020
The Pulse Boulevard GroveCancelled0%Dec 2025Listing feed statesSept 2019

Dubai South: questions and answers

How many projects is Dubai South building in Dubai?

Dubai South has 19 projects under construction in Dubai, with 3,338 homes in total, according to the Dubai Land Department project register.

How many projects has Dubai South delivered in Dubai?

Dubai South has delivered 13 of the 34 projects the Dubai Land Department project register lists for it.

When do Dubai South projects hand over?

Handover years for Dubai South's projects under construction, by the developer's date where it gave one, else the date in new-project listings, else the Dubai Land Department project register's date: 5 projects in 2026, 1 project in 2027, 5 projects in 2028, 4 projects in 2029 and 1 project in 2030.

Which Dubai South projects hand over next?

The next Dubai South projects to hand over are Beachfront Gates 2 (December 2026), Beachfront Gates 1 (December 2026), South Bay 6 Premium (December 2027) and Hayat 3 (May 2028), by the same dates (the developer's where it gave one, else the new-project listings', else the Dubai Land Department project register's).

How far is construction of Dubai South's projects?

Among Dubai South's projects under construction, the most advanced are South Bay 2 (94% built), South Bay 1 (94% built), South Living (89% built) and South Bay 3 Premium (88% built), from official RERA site inspections.