Dubai project status

The official construction status of every project in the Dubai Land Department (DLD) project register: how far it is built at the latest RERA site inspection, when it was inspected and the completion date the developer registered. 1,571 projects are under construction; the latest inspection on record is from 14 Oct 2026. Project register as of 16 Oct 2026.

Under construction
1,571
registered projects
Completed
1,669
registered projects
Inspected in the last 90 days
830
site inspections by RERA
Past the registered date
250
still under construction
Under constructionCompletedCancelled1,570 projects, latest inspection first
ProjectDeveloperDistrict in the registerStatusBuiltLatest inspectionRegistered completion
Allegro Park By Mill Hill Riviera Development52 unitsAbra GroupPalm DeiraUnder construction0%9 Jul 202625 Apr 2027
Arancia Yards 2 By Beyond380 unitsPeninsula AlteraWadi Al Safa 4Under construction0%9 Jul 202630 Jan 2029
1wood Residence227 unitsObject One Real Estate DevelopmentAl Barsha South FourthUnder construction94%8 Jul 2026—
Terra Tower366 unitsDugasta PropertiesWadi Al Safa 5Under construction7%8 Jul 202630 Apr 2027
Ayamore Residence94 unitsAyat DevelopmentPalm DeiraUnder construction68%8 Jul 20267 Mar 2027
Ayaan Heights I130 unitsInvest Group OverseasBukadraUnder construction20%8 Jul 202631 Mar 2028
Flora Shore By Calgary Properties76 unitsCalgary PropertiesPalm DeiraUnder construction2%8 Jul 202630 Sept 2027
Divine Elements90 unitsTakmeel Real Estate Development L. L. CMadinat Al MataarUnder construction0%8 Jul 202631 Dec 2027
Maravea Residences63 unitsEnzo DevelopersPalm DeiraUnder construction0%8 Jul 202630 Apr 2028
Villa Dell Arte64 unitsAmberton Residences Real EstatePalm DeiraUnder construction0%8 Jul 202627 Dec 2027
Noore43 unitsEight Square DeveloperWadi Al Safa 3Under construction16%8 Jul 202630 Jun 2027
Portside 2 By Samana Developers279 unitsSamana DevelopersJabal Ali Industrial SecondUnder construction0%8 Jul 202631 Dec 2029
Raw District 2 By Imtiaz770 unitsImtiaz DevelopmentsJabal Ali Industrial SecondUnder construction0%8 Jul 20261 Dec 2029
Azizi Venice 8778 unitsAzizi DevelopmentsMadinat Al MataarUnder construction53%7 Jul 2026—
Fairway Villas 372 unitsEmaarMadinat Al MataarUnder construction49%7 Jul 2026—
Valoria The Oasis257 unitsEmaarMe'Aisem SecondUnder construction1%7 Jul 202631 Dec 2029
Portside By Samana Developers148 unitsSamana DevelopersJabal Ali Industrial SecondUnder construction0%7 Jul 202630 Jun 2029
Samana South Haven 2137 unitsSamana DevelopersSaih Shuaib 2Under construction0%7 Jul 202630 Jun 2029
Sahara Livings84 unitsKifataSaih Shuaib 2Under construction93%7 Jul 202630 Jun 2013 · passed
Electra281 unitsAcube DevelopmentsAl Barsha South FourthUnder construction8%6 Jul 2026—
Maison Elysee I355 unitsPantheon DevelopmentAl Barsha South FourthUnder construction21%6 Jul 202631 Mar 2027
Rove Home Marasi Drive811 unitsIrth DevelopmentsBusiness BayUnder construction10%6 Jul 202631 Aug 2027
Minati Homes 182 unitsJanuss DeveloperJabal Ali FirstUnder construction51%6 Jul 202630 Sept 2026 · passed
The Valley - Velora 2312 unitsEmaarAl Yufrah 1Under construction40%6 Jul 202631 Jul 2028
Havelock Residences230 unitsHMB Homes Real Estate DevelopmentJabal Ali FirstUnder construction11%6 Jul 202631 Dec 2026
Voi Residence By Hvm Living68 unitsHvm LivingMadinat Al MataarUnder construction16%6 Jul 202630 Sept 2026 · passed
W Residences At Dubai Harbour494 unitsAradaMarsa DubaiUnder construction2%6 Jul 202631 Dec 2028
Lacina324 unitsMajid Al Futtaim (MAF)Wadi Al Safa 4Under construction21%6 Jul 202630 Dec 2027
Rove Home Dubai Marina682 unitsIrth DevelopmentsMarsa DubaiUnder construction8%6 Jul 202631 Mar 2028
Interstellar Tower285 unitsMr Eight DevelopmentAl Barsha South FifthUnder construction0%6 Jul 202630 Sept 2028
The Valley - Farm Grove 2290 unitsEmaarAl Yufrah 1Under construction10%6 Jul 202631 Oct 2028
Whitestone Residence46 unitsAxiom Prime DevelopmentAl SatwaUnder construction3%6 Jul 202631 Oct 2026
Tulip Oasis 11108 unitsMadar DevelopmentsWadi Al Safa 3Under construction70%6 Jul 202630 Jun 2026 · passed
Sol Levante674 unitsS O L PROPERTIES DEVELOPMENT L. L. C - 999Al Barsha South FifthUnder construction7%6 Jul 202615 Sept 2028
Grand Polo - Montura 2206 unitsEmaarDubai Investment Park SecondUnder construction5%6 Jul 202631 May 2029
Floarea Skies195 unitsMashriq EliteAl Barsha South FourthUnder construction5%6 Jul 202631 Dec 2028
Helvetia Verde109 unitsDHG HoldingBukadraUnder construction1%6 Jul 202630 Nov 2027
Hq By Rove414 unitsIrth UrbanBusiness BayUnder construction1%6 Jul 202631 Mar 2029
Hearth Heights By Enawt Real Estate Development142 unitsEnawt Real Estate DevelopmentAl Barsha South FourthUnder construction29%6 Jul 20261 Oct 2026 · passed
Mareva 2 The Oasis347 unitsEmaarMe'Aisem SecondUnder construction1%6 Jul 202628 Feb 2030
Q Gardens Aliya278 unitsAYS DeveloperAl Barsha South FourthUnder construction8%5 Jul 202630 Jun 2027
Damac Lagoons - Lagoon Views 131,509 unitsDamac PropertiesAl Hebiah FifthUnder construction6%3 Jul 202631 Dec 2027
15 Cascade442 unitsIman DevelopersAl Hebiah FirstUnder construction6%2 Jul 202630 Sept 2028
Altan479 unitsEmaarAl Khairan FirstUnder construction11%2 Jul 202631 Jul 2029
Albero479 unitsEmaarAl Khairan FirstUnder construction11%2 Jul 202630 Sept 2029
Best Town Villas3 unitsBest CityAl Barsha South FifthUnder construction76%2 Jul 202630 Mar 2026 · passed
The Cape286 unitsAl BarariWadi Al Safa 3Under construction1%2 Jul 202631 Dec 2028
South Lofts By Premier Choice149 unitsAbra GroupSaih Shuaib 2Under construction0%2 Jul 202630 Jan 2029
Sadaat Tower89 unitsGulabWarsan FourthUnder construction32%2 Jul 202631 Jan 2027
Azizi Riviera Reve455 unitsAzizi DevelopmentsAl MerkadhUnder construction77%1 Jul 20265 Feb 2025 · passed

Source: the official project register of the Dubai Land Department and the Real Estate Regulatory Agency (RERA), read every day. A project name with a link opens its page here, with prices, payment plan and site photos.

Percent built

The share of construction finished, measured by RERA inspectors on their latest visit to the site. It is the regulator's figure, not the developer's estimate.

Registered completion date

The date the developer registered for finishing the project. A project can pass it and still be under construction; the date a developer advertises for handover can differ.

Status

Under construction, completed or cancelled, as the register lists the project. Buyers' payments for a registered off-plan project go into its escrow account, which the regulator oversees.

Dubai project status: questions and answers

How many projects are under construction in Dubai?

1,571 projects are registered as under construction in the official project register of the Dubai Land Department (DLD) and its regulator RERA. Another 1,669 are completed and 610 are cancelled. The latest site inspection on record is from 14 October 2026.

How do I check the status of an off-plan project in Dubai?

Type the name of the project, its developer or its district in the search box on this page. All 3,850 registered projects are covered; each one shows its official status, the percent built at the latest site inspection, the date of that inspection and the registered completion date.

What does the percent built mean?

It is the share of construction finished, as measured by RERA inspectors on their latest visit to the site. It is not the developer's own estimate. 830 projects were inspected in the last 90 days.

What is the registered completion date?

It is the completion date the developer registered with the regulator. A project can still be under construction after it: 250 of the 1,571 projects under construction are past their registered date. A developer may also advertise a different handover date.

How often is the project status updated?

Every day. dxbpropy.ai reads the official register daily and re-reads every project once a week, so a new inspection or a change of status shows here within a day or a week.