Meraas
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.
Under construction
36
Units
8,640
Delivered (all years)
39
Behind schedule
1
Cancelled (all years)
1
Sales in this developer's projects
Registered sales by period; the latest figures run to 11 Nov 2026.
| Period | Off-plan sales | Villa plots sold on plan | Resales in completed projects |
|---|---|---|---|
| Last 12 months | AED 10.9bn 1,530 sales | AED 4.2bn 291 sales | AED 3.6bn 662 sales |
| 2026 so far | AED 7.8bn 1,307 sales | AED 3.0bn 204 sales | AED 3.0bn 564 sales |
| 2025 | AED 17.7bn 2,590 sales | AED 10.0bn 697 sales | AED 3.8bn 632 sales |
| 2024 | AED 9.1bn 2,185 sales | AED 11.0bn 1,127 sales | AED 4.7bn 722 sales |
| 2023 | AED 13.7bn 3,003 sales | AED 1.6bn 126 sales | AED 4.2bn 687 sales |
| 2022 | AED 6.1bn 2,181 sales | AED 1.5bn 154 sales | AED 3.4bn 712 sales |
| 2021 | AED 2.6bn 981 sales | – | AED 1.3bn 231 sales |
Latest from developers
Offers, launches and news from developers' sales teams, updated through the day.
Sales-team items from the last 45 days, Instagram posts from the last 90 days; offers pinned to this developer show at any age while they are valid.
- 12 NovLaunchMeraas opens EOI allocations for Solaya beachfront residences on 13 November 2026.
- 10 NovLaunchDubai Holding opens EOI for Palm Springs on 10 November 2026; EOI submissions close Tuesday 17 November 2026, 5:00 PM.
- 10 NovLaunchDubai Holding Real Estate opens paid EOI for Palm Springs villas and townhouses; EOI submissions close Tuesday 17 November 2026, 5:00 PM.
- 10 NovLaunchDubai Holding opens EOI for Palm Springs on 10 November 2026; EOI submissions close Tuesday 17 November 2026, 5:00 PM.· AED 3.80M
- 9 NovLaunchDubai Holding Real Estate opens EOI for Palm Springs villas and townhouses on 10 November 2026; EOI submissions close Tuesday 17 November 2026, 5:00 PM.
- 6 NovLaunchDubai Holding Real Estate opens EOI for Nad Al Sheba Gardens Phase 12 — 4BR and 5BR villas.
- 6 NovLaunchMeraas opens EOI for Nad Al Sheba Gardens Phase 12 on 6 November 2026.
- 28 OctOfferDubai Holding releases 1-bedroom cancellation units at The Edit at d3.
- 20 OctOfferDubai Holding lists Palm Central Private Residences on Palm Jebel Ali from AED 4.27M
- 20 OctOfferDubai Holding offers Palm Beach Tower apartments on Palm Jumeirah from AED 4.19M
- 20 OctOfferDubai Holding releases Solaya residences at La Mer Beach from AED 40.3M
- 20 OctOfferDubai Holding lists Crestlane apartments at Citywalk from AED 2.65M
- 16 OctNewsDubai rental yields rise to 6.76%; Bay Estate sells out at launch; Nakheel awards marine works contract for Dubai Islands.
- 14 OctLaunchMeraas opens EOI for Solaya on 14 October 2026; EOI submissions closed Wednesday 28 October 2026, 5:00 PM.
- 14 OctLaunchMeraas opens EOI for Solaya at La Mer on 14 October 2026; EOI submissions closed Wednesday 28 October 2026, 5:00 PM.
- 14 OctLaunchSolaya Building 8 coming soon at beachfront development; EOI submissions closed Wednesday 28 October 2026, 5:00 PM.
- 12 OctOfferPalm Central Private Residences at Palm Jebel Ali available with 70/30 payment plan.· AED 4.27M
- 12 OctOfferSolaya at La Mer Beach offers 3-bedroom units with handover set for June 2029.· AED 40.35M
- 12 OctOfferCrestlane at Citywalk launches 1 and 4-bedroom units with April 2030 handover.· AED 2.65M
- 12 OctOfferPalm Beach Tower on Palm Jumeirah nearing completion with handover set for March 2027.· AED 4.19M
- 12 OctOfferThe Edit at d3 in Dubai Design District available with 75/25 payment plan.· AED 4.15M
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| Nad Al Sheba Gardens Phase 3 | Behind schedule | 97% | Apr 2026Listing feed states | Apr 2026 | 7 months past promised handover |
| Central Park Plaza | Slower than needed | 44% | Oct 2026Listing feed states | Oct 2026 | |
| Design Quarter | Slower than needed | 41% | Feb 2027Listing feed states | Feb 2027 | |
| Bluewaters Bay | Slower than needed | 37% | Mar 2027project register | Mar 2027 | |
| Riwa | Slower than needed | 30% | Sept 2027Listing feed states | – | |
| City Walk Northline 2 | On schedule | 49% | – | – | |
| City Walk Northline 1 | On schedule | 46% | – | – | |
| Elara | On schedule | 78% | Nov 2026Listing feed states | Nov 2026 | |
| Bulgari Lighthouse Dubai | On schedule | 80% | Mar 2027project register | Mar 2027 | |
| Nad Al Sheba Gardens Phase 4 | On schedule | 76% | Mar 2027Listing feed states | – | |
| Nad Al Sheba Gardens Phase 5 | On schedule | 38% | Sept 2027Listing feed states | – | |
| The Acres | On schedule | 25% | Sept 2028Developer states | – | |
| Nad Al Sheba Gardens Phase 6 | Early stage | 14% | Sept 2027Listing feed states | – | |
| Nad Al Sheba Gardens Phase 7 | Early stage | 4% | Feb 2028Listing feed states | Feb 2028 | |
| The Acres 2 & Estates 2 | Early stage | 15% | May 2028Listing feed states | May 2028 | |
| The Acres 3 & Estates | Early stage | 15% | Aug 2028Listing feed states | Nov 2027 | |
| Verve City Walk | Early stage | 18% | Sept 2028project register | Sept 2028 | |
| Nad Al Sheba Gardens Phase 8 & 9 | Early stage | 1% | Oct 2028project register | Oct 2028 | |
| City Walk Crestlane 3 | Early stage | 5% | Dec 2028Listing feed states | Dec 2028 | |
| City Walk Crestlane 2 | Early stage | 7% | Dec 2028Listing feed states | Dec 2028 | |
| Nad Al Sheba Gardens Phase 10 | Early stage | 0% | Dec 2028Listing feed states | Oct 2028 | |
| Nourelle | Early stage | 6% | Mar 2029Listing feed states | Mar 2029 | |
| Jumeirah Residences - Asora Bay - Ocean Mansions | Early stage | 0% | Mar 2029project register | Mar 2029 | |
| Jumeirah Asora Bay | Early stage | 4% | Mar 2029project register | Mar 2029 | |
| Solaya (1,2,3) | Early stage | 0% | Jun 2029project register | Jun 2029 | |
| Nad Al Sheba Gardens Phase 11 | Early stage | 0% | Jul 2029Listing feed states | Jul 2029 | |
| Atelis At D3 | Early stage | 1% | Jul 2029Listing feed states | Aug 2029 | |
| Nad Al Sheba Gardens Phase 12 | Early stage | 0% | Aug 2029project register | Aug 2029 | |
| City Walk Crestlane 1 | Early stage | 1% | Sept 2029Listing feed states | Sept 2029 | |
| Solaya (4,6) | Early stage | 0% | Sept 2029project register | Sept 2029 | |
| Solaya (5,7) | Early stage | 0% | Sept 2029project register | Sept 2029 | |
| Solaya (8,9) | Early stage | 0% | Apr 2030project register | Apr 2030 | |
| City Walk Crestlane 4 | Early stage | 0% | Apr 2030Listing feed states | Apr 2030 | |
| City Walk Crestlane 5 | Early stage | 0% | Apr 2030Listing feed states | Apr 2030 | |
| The Edit At D3 | Early stage | 0% | Sept 2030Developer states | Jan 2030 | |
| Jumeirah Residences Emirates Towers | Early stage | 4% | Sept 2030Developer states | Sept 2030 | |
| Thyme | Delivered | 100% | Aug 2026 | – | |
| No. 4a, No.4b, No.5 Citywalk Residential | Delivered | 100% | Dec 2016 | Dec 2016 | |
| No. 6a And No.6b Citywalk Residential | Delivered | 100% | Dec 2016 | Dec 2016 | |
| No.9 & No.10 Citywalk Residential | Delivered | 100% | Dec 2016 | Dec 2016 | |
| No.17, No.18a,No.18b And No.19 Citywalk Residential | Delivered | 100% | Jan 2017 | Jan 2017 | |
| Bv Residences | Delivered | 100% | Feb 2017 | Feb 2017 | |
| No.1, No.2a, No.2b, No.3a And 3b Citywalk Residential | Delivered | 100% | Feb 2017 | Feb 2017 | |
| No.20, No.21a, No.21b And No.22 Citywalk Residential | Delivered | 100% | May 2017 | May 2017 | |
| No.15 & No.16 Citywalk Residential | Delivered | 100% | May 2017 | May 2017 | |
| No.23a And 23b Citywalk Residential | Delivered | 100% | Jul 2017 | Jul 2017 | |
| Bv Mansions | Delivered | 100% | Apr 2018 | Apr 2018 | |
| Bluewaters Residences | Delivered | 100% | Feb 2019 | Feb 2019 | |
| Madinat Jumeirah Living | Delivered | 100% | Mar 2021 | Mar 2021 | |
| Sur La Mer | Delivered | 100% | Aug 2021 | Aug 2021 | |
| Port De La Mer - La Cote | Delivered | 100% | Sept 2021 | Sept 2021 | |
| Port De La Mer - La Voile | Delivered | 100% | Apr 2022 | Apr 2022 | |
| Cherrywoods | Delivered | 100% | May 2022 | May 2022 | |
| Central Park At City Walk -Building 1 | Delivered | 94% | Jun 2022 | Jun 2022 | |
| Port De La Mer - Le Pont | Delivered | 100% | Jul 2022 | Jul 2022 | |
| La Rive | Delivered | 100% | Oct 2022 | Oct 2022 | |
| Sur La Mer 2 | Delivered | 100% | Nov 2022 | Nov 2022 | |
| Madinat Jumeriah Living - Phase 2 | Delivered | 100% | Dec 2022 | Dec 2022 | |
| Asayel At Madinat Jumeirah Living | Delivered | 100% | May 2023 | May 2023 | |
| Bulgari Ocean Mansions | Delivered | 100% | Feb 2024 | Feb 2024 | |
| Port De La Mer - La Sirene | Delivered | 100% | Feb 2024 | Feb 2024 | |
| Jadeel -Madinat Jumeirah Living | Delivered | 100% | Sept 2024 | Sept 2024 | |
| Celadon | Delivered | 100% | Nov 2024 | Nov 2024 | |
| Viridian | Delivered | 100% | Nov 2024 | Nov 2024 | |
| Nad Al Sheba Gardens Phase 2 | Delivered | 100% | Dec 2024 | Dec 2024 | |
| Port De La Mer - Le Soleil | Delivered | 100% | Dec 2024 | Dec 2024 | |
| Al Jazi - Madinat Jumeriah Living | Delivered | 100% | Dec 2024 | Dec 2024 | |
| Port De La Mer - La Sirene 2 | Delivered | 100% | Jun 2024 | Jun 2024 | |
| Myrtle | Delivered | 100% | Apr 2025 | Apr 2025 | |
| Laurel | Delivered | 100% | Dec 2025 | Dec 2025 | |
| Lamaa | Delivered | 100% | Jan 2026 | Jan 2026 | |
| Fern | Delivered | 100% | Mar 2026 | Mar 2026 | |
| Castleton | Delivered | 100% | Aug 2026 | – | |
| Jomana | Delivered | 100% | Apr 2026 | Apr 2026 | |
| Erin | Delivered | 100% | Aug 2026 | Aug 2026 | |
| Jumeirah Hills - The Palaces | Cancelled | 6% | Aug 2016project register | Aug 2016 |
Meraas: questions and answers
How many projects is Meraas building in Dubai?
Meraas has 36 projects under construction in Dubai, with 8,640 homes in total, according to the Dubai Land Department project register.
How many projects has Meraas delivered in Dubai?
Meraas has delivered 39 of the 76 projects the Dubai Land Department project register lists for it.
When do Meraas projects hand over?
Handover years for Meraas's projects under construction, by the developer's date where it gave one, else the date in new-project listings, else the Dubai Land Department project register's date: 3 projects in 2026, 7 projects in 2027, 9 projects in 2028, 10 projects in 2029 and 5 projects in 2030.
Which Meraas projects hand over next?
The next Meraas projects to hand over are Elara (November 2026), Design Quarter (February 2027), Bluewaters Bay (March 2027) and Bulgari Lighthouse Dubai (March 2027), by the same dates (the developer's where it gave one, else the new-project listings', else the Dubai Land Department project register's).
How far is construction of Meraas's projects?
Among Meraas's projects under construction, the most advanced are Nad Al Sheba Gardens Phase 3 (97% built), Bulgari Lighthouse Dubai (80% built), Elara (78% built) and Nad Al Sheba Gardens Phase 4 (76% built), from official RERA site inspections.