Expo City Dubai
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.
Under construction
9
Units
3,223
Delivered (all years)
0
Behind schedule
2
Cancelled (all years)
0
Sales in this developer's projects
Registered sales by period; the latest figures run to 11 Nov 2026.
| Period | Off-plan sales | Villa plots sold on plan | Resales in completed projects |
|---|---|---|---|
| Last 12 months | AED 1.0bn 372 sales | AED 36.38M 3 sales | – |
| 2026 so far | AED 770.06M 286 sales | AED 20.78M 2 sales | – |
| 2025 | AED 2.9bn 982 sales | AED 77.20M 4 sales | – |
| 2024 | AED 2.8bn 832 sales | AED 419.18M 28 sales | – |
| 2023 | AED 1.8bn 569 sales | AED 153.93M 11 sales | – |
Latest from developers
Offers, launches and news from developers' sales teams, updated through the day.
Sales-team items from the last 45 days, Instagram posts from the last 90 days; offers pinned to this developer show at any age while they are valid.
- 5 NovOfferExpo City Dubai offers 60/40 off-plan payment plan for Ghadeer at Expo Valley Views.Instagram ↗
- 27 OctOfferExpo City Dubai partners with Emirates NBD to offer pre-handover mortgage financing for off-plan homes.Instagram ↗
- 8 OctOfferExpo City Dubai partners with Mashreq Bank to offer off-plan home financing across selected residential projects.Instagram ↗
- 6 OctNewsExpo City Dubai partners with Dubai Islamic Bank to offer Shariah-compliant financing for off-plan homes.Instagram ↗
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| Expo City Mangrove Residences | Behind schedule | 91% | Jan 2026project register | Jan 2026 | 10 months past promised handover |
| Expo City Valley | Behind schedule | 66% | Jan 2026Listing feed states | Jan 2026 | 10 months past promised handover |
| Expo City Al Waha Residences 02 | Slower than needed | 61% | Jun 2027project register | Jun 2027 | |
| Expo City Sidr Residences | Slower than needed | 25% | Mar 2028project register | Mar 2028 | |
| Expo City Sky Residences | On schedule | 53% | – | – | |
| Expo City Al Waha Residences 01 | On schedule | 66% | Jun 2027project register | Jun 2027 | |
| Expo Valley Views 2 | Early stage | 0% | Oct 2029project register | Oct 2029 | |
| Expo Valley Views | Early stage | 0% | Oct 2029Developer states | Oct 2029 | |
| Expo Valley Views 1 | Early stage | 0% | Mar 2030project register | Mar 2030 |
Expo City Dubai: questions and answers
How many projects is Expo City Dubai building in Dubai?
Expo City Dubai has 9 projects under construction in Dubai, with 3,223 homes in total, according to the Dubai Land Department project register.
When do Expo City Dubai projects hand over?
Handover years for Expo City Dubai's projects under construction, by the developer's date where it gave one, else the date in new-project listings, else the Dubai Land Department project register's date: 2 projects in 2026, 2 projects in 2027, 1 project in 2028, 2 projects in 2029 and 1 project in 2030.
Which Expo City Dubai projects hand over next?
The next Expo City Dubai projects to hand over are Expo City Al Waha Residences 01 (June 2027), Expo City Al Waha Residences 02 (June 2027), Expo City Sidr Residences (March 2028) and Expo Valley Views 2 (October 2029), by the same dates (the developer's where it gave one, else the new-project listings', else the Dubai Land Department project register's).
How far is construction of Expo City Dubai's projects?
Among Expo City Dubai's projects under construction, the most advanced are Expo City Mangrove Residences (91% built), Expo City Valley (66% built), Expo City Al Waha Residences 01 (66% built) and Expo City Al Waha Residences 02 (61% built), from official RERA site inspections.