Expo City Dubai
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date.
Under construction
4
Units
1,839
Delivered
0
Behind schedule
2
Cancelled
0
Handovers 2026
2
Handovers 2027
0
Handovers 2028
1
Handovers 2029
0
Handovers 2030
0
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| Expo City Valley | Behind schedule | 66% | Jan 2026 | Jan 2026 | 8 months past promised handover |
| Expo City Mangrove Residences | Behind schedule | 91% | Jan 2026 | Jan 2026 | 8 months past promised handover |
| Expo City Sidr Residences | Slower than needed | 25% | Mar 2028 | Mar 2028 | |
| Expo City Sky Residences | On schedule | 53% | – | – |