Majid Al Futtaim (MAF)
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date.
Under construction
12
Units
3,587
Delivered
3
Behind schedule
0
Cancelled
0
Handovers 2026
5
Handovers 2027
4
Handovers 2028
0
Handovers 2029
3
Handovers 2030
0
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| Lanai Island | Slower than needed | 61% | Sept 2026 | Sept 2026 | |
| Plagette 32 | Slower than needed | 61% | Dec 2026 | – | |
| Cilia | Slower than needed | 44% | Sept 2027 | – | |
| Serra | Slower than needed | 42% | Sept 2027 | – | |
| Serenity Mansions | Slower than needed | 32% | Dec 2027 | – | |
| Alaya | On schedule | 91% | Jul 2026 | Jul 2026 | |
| Elysian Mansions | On schedule | 95% | Dec 2026 | Mar 2025 | |
| Amara | On schedule | 71% | Dec 2026 | – | |
| Lacina | Early stage | 21% | Dec 2027 | Dec 2027 | |
| Capria West | Early stage | 1% | May 2029 | May 2029 | |
| Capria East | Early stage | 1% | May 2029 | May 2029 | |
| Distrikt | Early stage | 8% | Jul 2029 | Sept 2028 | |
| Elan | Delivered | 100% | Nov 2023 | Nov 2023 | |
| Harmony | Delivered | 100% | Jun 2024 | Jun 2024 | |
| Aura | Delivered | 100% | Aug 2024 | Aug 2024 |