Majid Al Futtaim (MAF)
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.
Under construction
13
Units
3,936
Delivered (all years)
3
Behind schedule
1
Cancelled (all years)
0
Sales in this developer's projects
Registered sales by period; the latest figures run to 11 Nov 2026.
| Period | Off-plan sales | Villa plots sold on plan | Resales in completed projects |
|---|---|---|---|
| Last 12 months | AED 2.1bn 640 sales | AED 2.3bn 121 sales | AED 1.2bn 212 sales |
| 2026 so far | AED 1.6bn 499 sales | AED 1.7bn 91 sales | AED 996.37M 166 sales |
| 2025 | AED 4.6bn 1,818 sales | AED 4.2bn 236 sales | AED 961.01M 190 sales |
| 2024 | AED 3.9bn 1,214 sales | AED 4.5bn 249 sales | AED 430.11M 124 sales |
| 2023 | AED 829.31M 286 sales | AED 6.0bn 423 sales | AED 439.33M 151 sales |
| 2022 | AED 601.27M 268 sales | AED 5.0bn 443 sales | – |
| 2021 | AED 2.1bn 896 sales | AED 3.1bn 718 sales | – |
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| Alaya | Behind schedule | 94% | Jul 2026Listing feed states | Jul 2026 | 4 months past promised handover |
| Lanai Island | Slower than needed | 61% | Sept 2026Listing feed states | Sept 2026 | |
| Plagette 32 | Slower than needed | 61% | Dec 2026Listing feed states | – | |
| Serra | Slower than needed | 42% | Sept 2027Listing feed states | – | |
| Cilia | Slower than needed | 44% | Sept 2027Listing feed states | – | |
| Lacina | Slower than needed | 30% | Dec 2027Listing feed states | Dec 2027 | |
| Serenity Mansions | Slower than needed | 40% | Dec 2027Listing feed states | – | |
| Elysian Mansions | On schedule | 95% | Dec 2026Listing feed states | Mar 2025 | |
| Amara | On schedule | 71% | Dec 2026Listing feed states | – | |
| Capria West | Early stage | 8% | May 2029Listing feed states | May 2029 | |
| Capria East | Early stage | 7% | May 2029Listing feed states | May 2029 | |
| Distrikt | Early stage | 8% | Jul 2029Listing feed states | Sept 2028 | |
| Lyra | Early stage | 0% | Dec 2029project register | Dec 2029 | |
| Elan | Delivered | 100% | Nov 2023 | Nov 2023 | |
| Harmony | Delivered | 100% | Jun 2024 | Jun 2024 | |
| Aura | Delivered | 100% | Aug 2024 | Aug 2024 |
Majid Al Futtaim (MAF): questions and answers
How many projects is Majid Al Futtaim (MAF) building in Dubai?
Majid Al Futtaim (MAF) has 13 projects under construction in Dubai, with 3,936 homes in total, according to the Dubai Land Department project register.
How many projects has Majid Al Futtaim (MAF) delivered in Dubai?
Majid Al Futtaim (MAF) has delivered 3 of the 16 projects the Dubai Land Department project register lists for it.
When do Majid Al Futtaim (MAF) projects hand over?
Handover years for Majid Al Futtaim (MAF)'s projects under construction, by the developer's date where it gave one, else the date in new-project listings, else the Dubai Land Department project register's date: 5 projects in 2026, 4 projects in 2027 and 4 projects in 2029.
Which Majid Al Futtaim (MAF) projects hand over next?
The next Majid Al Futtaim (MAF) projects to hand over are Elysian Mansions (December 2026), Plagette 32 (December 2026), Amara (December 2026) and Serra (September 2027), by the same dates (the developer's where it gave one, else the new-project listings', else the Dubai Land Department project register's).
How far is construction of Majid Al Futtaim (MAF)'s projects?
Among Majid Al Futtaim (MAF)'s projects under construction, the most advanced are Elysian Mansions (95% built), Alaya (94% built), Amara (71% built) and Plagette 32 (61% built), from official RERA site inspections.