Al Helal Al Zahaby Real Estate Development L. L. C
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.
Under construction
2
Units
412
Delivered (all years)
5
Behind schedule
0
Cancelled (all years)
1
Sales in this developer's projects
Registered sales by period; the latest figures run to 11 Nov 2026.
| Period | Off-plan sales | Villa plots sold on plan | Resales in completed projects |
|---|---|---|---|
| Last 12 months | AED 175.28M 152 sales | – | AED 28.30M 43 sales |
| 2026 so far | AED 120.65M 104 sales | – | AED 25.56M 38 sales |
| 2025 | AED 358.74M 372 sales | – | AED 23.60M 37 sales |
| 2024 | AED 16.22M 20 sales | – | AED 17.65M 30 sales |
| 2023 | AED 41.07M 71 sales | – | AED 4.00M 12 sales |
| 2022 | – | – | AED 2.67M 7 sales |
| 2021 | – | – | AED 3.63M 12 sales |
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| Forest City Tower | On schedule | 70% | Dec 2026Developer states | Apr 2027 | 3 months later on DLD than advertised |
| Oasis Residences | On schedule | 58% | Mar 2027Developer states | Jul 2027 | |
| Hz Residences 4 | Delivered | 100% | Apr 2025 | – | |
| Al Helal Al Zahaby Building | Delivered | 100% | Oct 2017 | Oct 2017 | |
| Al Helal Al Zahaby 2 | Delivered | 100% | Mar 2019 | Mar 2019 | |
| Al Helal Al Zahaby 3 | Delivered | 100% | Aug 2023 | Aug 2023 | |
| Sports View Residence By Al Helal Al Zahaby | Delivered | 100% | Aug 2026 | Aug 2026 | |
| Forest City Tower 3 | Cancelled | 0% | Apr 2032project register | Apr 2032 |
Al Helal Al Zahaby Real Estate Development L. L. C: questions and answers
How many projects is Al Helal Al Zahaby Real Estate Development L. L. C building in Dubai?
Al Helal Al Zahaby Real Estate Development L. L. C has 2 projects under construction in Dubai, with 412 homes in total, according to the Dubai Land Department project register.
How many projects has Al Helal Al Zahaby Real Estate Development L. L. C delivered in Dubai?
Al Helal Al Zahaby Real Estate Development L. L. C has delivered 5 of the 8 projects the Dubai Land Department project register lists for it.
When do Al Helal Al Zahaby Real Estate Development L. L. C projects hand over?
Handover years for Al Helal Al Zahaby Real Estate Development L. L. C's projects under construction, by the developer's date where it gave one, else the date in new-project listings, else the Dubai Land Department project register's date: 1 project in 2026 and 1 project in 2027.
Which Al Helal Al Zahaby Real Estate Development L. L. C projects hand over next?
The next Al Helal Al Zahaby Real Estate Development L. L. C projects to hand over are Forest City Tower (December 2026) and Oasis Residences (March 2027), by the same dates (the developer's where it gave one, else the new-project listings', else the Dubai Land Department project register's).
How far is construction of Al Helal Al Zahaby Real Estate Development L. L. C's projects?
Among Al Helal Al Zahaby Real Estate Development L. L. C's projects under construction, the most advanced are Forest City Tower (70% built) and Oasis Residences (58% built), from official RERA site inspections.
✦ Ask about any developer
Track record, projects handing over by year and construction progress — from official records.