← All developers

Sobha

Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.

Under construction

27

Units

31,038

Delivered (all years)

20

Behind schedule

1

Cancelled (all years)

2

Promised for 2026
2
Promised for 2027
7
Promised for 2028
7
Promised for 2029
3
Promised for 2030
6

Sales in this developer's projects

Registered sales by period; the latest figures run to 11 Nov 2026.

PeriodOff-plan salesVilla plots sold on planResales in completed projects
Last 12 months
AED 11.8bn
4,427 sales
AED 2.2bn
243 sales
AED 1.8bn
783 sales
2026 so far
AED 9.2bn
3,292 sales
AED 2.0bn
232 sales
AED 1.5bn
658 sales
2025
AED 20.8bn
10,004 sales
AED 3.9bn
282 sales
AED 1.6bn
742 sales
2024
AED 19.8bn
8,888 sales
AED 1.4bn
59 sales
AED 1.4bn
800 sales
2023
AED 10.1bn
3,972 sales
AED 264.51M
16 sales
AED 1.3bn
866 sales
2022
AED 3.4bn
2,067 sales
AED 551.66M
33 sales
AED 407.74M
256 sales
2021
AED 1.4bn
1,076 sales
AED 168.29M
12 sales
AED 811.14M
240 sales

Latest from developers

Offers, launches and news from developers' sales teams, updated through the day.

Sales-team items from the last 45 days, Instagram posts from the last 90 days; offers pinned to this developer show at any age while they are valid.

  • 14 OctNewsSobha Realty partners with RAK Bank to offer preferential home financing at select Sobha premises.Instagram ↗
  • 18 SeptNewsSobha Realty has handed over Waves Opulence to its homeowners.Instagram ↗

Projects

% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.

ProjectStatusBuiltHandover dateDLD planned dateNote
Sobha Creek Vista HeightsBehind schedule92%Jun 2026Listing feed states–5 months past promised handover
Sobha Seahaven Tower ASlower than needed45%Apr 2028project registerApr 2028
Sobha ReserveOn schedule75%––
Sobha OneOn schedule86%Dec 2026Listing feed states–
330 Riverside CrescentOn schedule68%Jun 2027Listing feed states–
Verde By SobhaOn schedule85%Jun 2027project registerJun 2027
320 Riverside CrescentOn schedule57%Sept 2027Listing feed states–
350 Riverside CrescentOn schedule58%Dec 2027Listing feed states–
340 Riverside CrescentOn schedule55%Dec 2027Listing feed states–
360 Riverside CrescentOn schedule51%Dec 2027Listing feed states–
Sobha EstatesOn schedule68%Dec 2027project registerDec 2027
310 Riverside CrescentOn schedule50%Apr 2028Listing feed states–
Sobha Seahaven Tower B & COn schedule40%Oct 2028project registerOct 2028
SkyscapeOn schedule38%Dec 2028Developer statesDec 2029 12 months later on DLD than advertised
Elwood EstatesEarly stage14%Jun 2028project registerJun 2028
Sobha SolisEarly stage18%Dec 2028project registerDec 2028
Sobha OrbisEarly stage18%Dec 2028Listing feed statesDec 2028
The Grove At Sobha SanctuaryEarly stage0%Sept 2029Developer statesAug 2030 11 months later on DLD than advertised
The WoodsEarly stage0%Dec 2029Developer statesDec 2030 12 months later on DLD than advertised
The Element At Sobha OneEarly stage11%Dec 2029project registerDec 2029
Sobha Central Phase IiEarly stage6%Jun 2030project registerJun 2030
Sobha Central Phase IEarly stage7%Jun 2030project registerJun 2030
SkyvueEarly stage16%Jun 2030Developer statesMar 2030
The Brooks At Sobha SanctuaryEarly stage0%Aug 2030project registerAug 2030
The Greens At Sobha SanctuaryEarly stage0%Aug 2030project registerAug 2030
Sobha CentralEarly stage2%Dec 2030Developer statesDec 2031 12 months later on DLD than advertised
Sobha SkyparksEarly stage0%Dec 2032project registerDec 2032
Sobha DaffodilDelivered100%Nov 2010Nov 2010
Sobha Ivory - IiDelivered100%Dec 2010Dec 2010
Sobha SapphireDelivered100%Jun 2011Jun 2011
Sobha Hartland Greens- Phase IDelivered100%Sept 2018Sept 2018
Sobha Hartland Greens Phase IiDelivered100%Jan 2020Jan 2020
Sobha Hartland Villas-Phase 1Delivered100%Jun 2020Jun 2020
Sobha Hartland Greens - Phase IiiDelivered100%Jan 2021Jan 2021
Sobha Hartland Estates - TownhousesDelivered100%Sept 2021Sept 2021
Sobha Hartland Villas - Phase IiDelivered100%Dec 2021Dec 2021
Sobha Creek VistasDelivered100%Jan 2022Jan 2022
Sobha Hartland One Park AvenueDelivered100%Apr 2023Apr 2023
Sobha Creek Vistas ReserveDelivered100%Aug 2023Aug 2023
Sobha Hartland Waves GrandeDelivered100%Oct 2023Oct 2023
Sobha Hartland WavesDelivered100%Mar 2024Mar 2024
Sobha Hartland Villas Phase IiiDelivered100%Jun 2024Jun 2024
The S TowerDelivered100%Jun 2025Jun 2025
Sobha Creek Vistas GrandeDelivered100%Jul 2025Jul 2025
Sobha Hartland - The CrestDelivered100%Dec 2025Dec 2025
Sobha Hartland - Crest GrandeDelivered100%Jun 2026Jun 2026
Sobha Hartland Waves OpulenceDelivered100%Sept 2026Sept 2026
Sobha Seahaven - Tower CCancelled0%––
Sobha OneCancelled3%––

Sobha: questions and answers

How many projects is Sobha building in Dubai?

Sobha has 27 projects under construction in Dubai, with 31,038 homes in total, according to the Dubai Land Department project register.

How many projects has Sobha delivered in Dubai?

Sobha has delivered 20 of the 49 projects the Dubai Land Department project register lists for it.

When do Sobha projects hand over?

Handover years for Sobha's projects under construction, by the developer's date where it gave one, else the date in new-project listings, else the Dubai Land Department project register's date: 2 projects in 2026, 7 projects in 2027, 7 projects in 2028, 3 projects in 2029 and 6 projects in 2030.

Which Sobha projects hand over next?

The next Sobha projects to hand over are Sobha One (December 2026), 330 Riverside Crescent (June 2027), Verde By Sobha (June 2027) and 320 Riverside Crescent (September 2027), by the same dates (the developer's where it gave one, else the new-project listings', else the Dubai Land Department project register's).

How far is construction of Sobha's projects?

Among Sobha's projects under construction, the most advanced are Sobha Creek Vista Heights (92% built), Sobha One (86% built), Verde By Sobha (85% built) and Sobha Reserve (75% built), from official RERA site inspections.