Sobha
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.
Under construction
27
Units
31,038
Delivered (all years)
20
Behind schedule
1
Cancelled (all years)
2
Sales in this developer's projects
Registered sales by period; the latest figures run to 11 Nov 2026.
| Period | Off-plan sales | Villa plots sold on plan | Resales in completed projects |
|---|---|---|---|
| Last 12 months | AED 11.8bn 4,427 sales | AED 2.2bn 243 sales | AED 1.8bn 783 sales |
| 2026 so far | AED 9.2bn 3,292 sales | AED 2.0bn 232 sales | AED 1.5bn 658 sales |
| 2025 | AED 20.8bn 10,004 sales | AED 3.9bn 282 sales | AED 1.6bn 742 sales |
| 2024 | AED 19.8bn 8,888 sales | AED 1.4bn 59 sales | AED 1.4bn 800 sales |
| 2023 | AED 10.1bn 3,972 sales | AED 264.51M 16 sales | AED 1.3bn 866 sales |
| 2022 | AED 3.4bn 2,067 sales | AED 551.66M 33 sales | AED 407.74M 256 sales |
| 2021 | AED 1.4bn 1,076 sales | AED 168.29M 12 sales | AED 811.14M 240 sales |
Latest from developers
Offers, launches and news from developers' sales teams, updated through the day.
Sales-team items from the last 45 days, Instagram posts from the last 90 days; offers pinned to this developer show at any age while they are valid.
- 14 OctNewsSobha Realty partners with RAK Bank to offer preferential home financing at select Sobha premises.Instagram ↗
- 18 SeptNewsSobha Realty has handed over Waves Opulence to its homeowners.Instagram ↗
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| Sobha Creek Vista Heights | Behind schedule | 92% | Jun 2026Listing feed states | – | 5 months past promised handover |
| Sobha Seahaven Tower A | Slower than needed | 45% | Apr 2028project register | Apr 2028 | |
| Sobha Reserve | On schedule | 75% | – | – | |
| Sobha One | On schedule | 86% | Dec 2026Listing feed states | – | |
| 330 Riverside Crescent | On schedule | 68% | Jun 2027Listing feed states | – | |
| Verde By Sobha | On schedule | 85% | Jun 2027project register | Jun 2027 | |
| 320 Riverside Crescent | On schedule | 57% | Sept 2027Listing feed states | – | |
| 350 Riverside Crescent | On schedule | 58% | Dec 2027Listing feed states | – | |
| 340 Riverside Crescent | On schedule | 55% | Dec 2027Listing feed states | – | |
| 360 Riverside Crescent | On schedule | 51% | Dec 2027Listing feed states | – | |
| Sobha Estates | On schedule | 68% | Dec 2027project register | Dec 2027 | |
| 310 Riverside Crescent | On schedule | 50% | Apr 2028Listing feed states | – | |
| Sobha Seahaven Tower B & C | On schedule | 40% | Oct 2028project register | Oct 2028 | |
| Skyscape | On schedule | 38% | Dec 2028Developer states | Dec 2029 | 12 months later on DLD than advertised |
| Elwood Estates | Early stage | 14% | Jun 2028project register | Jun 2028 | |
| Sobha Solis | Early stage | 18% | Dec 2028project register | Dec 2028 | |
| Sobha Orbis | Early stage | 18% | Dec 2028Listing feed states | Dec 2028 | |
| The Grove At Sobha Sanctuary | Early stage | 0% | Sept 2029Developer states | Aug 2030 | 11 months later on DLD than advertised |
| The Woods | Early stage | 0% | Dec 2029Developer states | Dec 2030 | 12 months later on DLD than advertised |
| The Element At Sobha One | Early stage | 11% | Dec 2029project register | Dec 2029 | |
| Sobha Central Phase Ii | Early stage | 6% | Jun 2030project register | Jun 2030 | |
| Sobha Central Phase I | Early stage | 7% | Jun 2030project register | Jun 2030 | |
| Skyvue | Early stage | 16% | Jun 2030Developer states | Mar 2030 | |
| The Brooks At Sobha Sanctuary | Early stage | 0% | Aug 2030project register | Aug 2030 | |
| The Greens At Sobha Sanctuary | Early stage | 0% | Aug 2030project register | Aug 2030 | |
| Sobha Central | Early stage | 2% | Dec 2030Developer states | Dec 2031 | 12 months later on DLD than advertised |
| Sobha Skyparks | Early stage | 0% | Dec 2032project register | Dec 2032 | |
| Sobha Daffodil | Delivered | 100% | Nov 2010 | Nov 2010 | |
| Sobha Ivory - Ii | Delivered | 100% | Dec 2010 | Dec 2010 | |
| Sobha Sapphire | Delivered | 100% | Jun 2011 | Jun 2011 | |
| Sobha Hartland Greens- Phase I | Delivered | 100% | Sept 2018 | Sept 2018 | |
| Sobha Hartland Greens Phase Ii | Delivered | 100% | Jan 2020 | Jan 2020 | |
| Sobha Hartland Villas-Phase 1 | Delivered | 100% | Jun 2020 | Jun 2020 | |
| Sobha Hartland Greens - Phase Iii | Delivered | 100% | Jan 2021 | Jan 2021 | |
| Sobha Hartland Estates - Townhouses | Delivered | 100% | Sept 2021 | Sept 2021 | |
| Sobha Hartland Villas - Phase Ii | Delivered | 100% | Dec 2021 | Dec 2021 | |
| Sobha Creek Vistas | Delivered | 100% | Jan 2022 | Jan 2022 | |
| Sobha Hartland One Park Avenue | Delivered | 100% | Apr 2023 | Apr 2023 | |
| Sobha Creek Vistas Reserve | Delivered | 100% | Aug 2023 | Aug 2023 | |
| Sobha Hartland Waves Grande | Delivered | 100% | Oct 2023 | Oct 2023 | |
| Sobha Hartland Waves | Delivered | 100% | Mar 2024 | Mar 2024 | |
| Sobha Hartland Villas Phase Iii | Delivered | 100% | Jun 2024 | Jun 2024 | |
| The S Tower | Delivered | 100% | Jun 2025 | Jun 2025 | |
| Sobha Creek Vistas Grande | Delivered | 100% | Jul 2025 | Jul 2025 | |
| Sobha Hartland - The Crest | Delivered | 100% | Dec 2025 | Dec 2025 | |
| Sobha Hartland - Crest Grande | Delivered | 100% | Jun 2026 | Jun 2026 | |
| Sobha Hartland Waves Opulence | Delivered | 100% | Sept 2026 | Sept 2026 | |
| Sobha Seahaven - Tower C | Cancelled | 0% | – | – | |
| Sobha One | Cancelled | 3% | – | – |
Sobha: questions and answers
How many projects is Sobha building in Dubai?
Sobha has 27 projects under construction in Dubai, with 31,038 homes in total, according to the Dubai Land Department project register.
How many projects has Sobha delivered in Dubai?
Sobha has delivered 20 of the 49 projects the Dubai Land Department project register lists for it.
When do Sobha projects hand over?
Handover years for Sobha's projects under construction, by the developer's date where it gave one, else the date in new-project listings, else the Dubai Land Department project register's date: 2 projects in 2026, 7 projects in 2027, 7 projects in 2028, 3 projects in 2029 and 6 projects in 2030.
Which Sobha projects hand over next?
The next Sobha projects to hand over are Sobha One (December 2026), 330 Riverside Crescent (June 2027), Verde By Sobha (June 2027) and 320 Riverside Crescent (September 2027), by the same dates (the developer's where it gave one, else the new-project listings', else the Dubai Land Department project register's).
How far is construction of Sobha's projects?
Among Sobha's projects under construction, the most advanced are Sobha Creek Vista Heights (92% built), Sobha One (86% built), Verde By Sobha (85% built) and Sobha Reserve (75% built), from official RERA site inspections.
✦ Ask about any developer
Track record, projects handing over by year and construction progress — from official records.