Symbolic Developments

Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.

Under construction

3

Units

278

Delivered (all years)

1

Behind schedule

1

Cancelled (all years)

0

Promised for 2026
1
Promised for 2027
2
Promised for 2028
0
Promised for 2029
0
Promised for 2030
0

Sales in this developer's projects

Registered sales by period; the latest figures run to 11 Nov 2026.

PeriodOff-plan salesVilla plots sold on planResales in completed projects
Last 12 months
AED 117.54M
78 sales
–
AED 10.63M
10 sales
2026 so far
AED 106.93M
71 sales
–
AED 9.18M
9 sales
2025
AED 74.78M
40 sales
–
AED 26.30M
27 sales
2024
AED 161.17M
132 sales
––
2023
AED 11.84M
14 sales
––

Projects

% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.

ProjectStatusBuiltHandover dateDLD planned dateNote
Symbolic AuraBehind schedule70%Mar 2026Developer states–8 months past promised handover
Symbolic AltusEarly stage1%May 2027Listing feed statesMay 2027
Symbolic Zen ResidencesEarly stage2%Jun 2027project registerJun 2027
Symbolic AlphaDelivered100%Feb 2025Feb 2025

Symbolic Developments: questions and answers

How many projects is Symbolic Developments building in Dubai?

Symbolic Developments has 3 projects under construction in Dubai, with 278 homes in total, according to the Dubai Land Department project register.

How many projects has Symbolic Developments delivered in Dubai?

Symbolic Developments has delivered 1 of the 4 projects the Dubai Land Department project register lists for it.

When do Symbolic Developments projects hand over?

Handover years for Symbolic Developments's projects under construction, by the developer's date where it gave one, else the date in new-project listings, else the Dubai Land Department project register's date: 1 project in 2026 and 2 projects in 2027.

Which Symbolic Developments projects hand over next?

The next Symbolic Developments projects to hand over are Symbolic Altus (May 2027) and Symbolic Zen Residences (June 2027), by the same dates (the developer's where it gave one, else the new-project listings', else the Dubai Land Department project register's).

How far is construction of Symbolic Developments's projects?

Among Symbolic Developments's projects under construction, the most advanced are Symbolic Aura (70% built), Symbolic Zen Residences (2% built) and Symbolic Altus (1% built), from official RERA site inspections.