The official construction status of every project in the Dubai Land Department (DLD) project register: how far it is built at the latest RERA site inspection, when it was inspected and the completion date the developer registered. 1,571 projects are under construction; the latest inspection on record is from 14 Oct 2026. Project register as of 16 Oct 2026.
| Project | Developer | District in the register | Status | Built | Latest inspection | Registered completion |
|---|---|---|---|---|---|---|
| Aykon City 31,300 units | Damac Properties | Business Bay | Under construction | 31% | 12 Apr 2026 | 30 Dec 2027 |
| Damac Riverside - Olive208 units | Damac Properties | Dubai Investment Park Second | Under construction | 5% | 11 Apr 2026 | 30 Jun 2028 |
| Damac City 2731 units | Pinnacle Developers | Al Wasl | Under construction | 6% | 9 Apr 2026 | — |
| Lincoln Star Residence Ii56 units | Lincoln Star Real Estate Development LLC | Madinat Al Mataar | Under construction | 5% | 9 Apr 2026 | 31 Aug 2027 |
| Vibe212 units | Arsenal East | Al Satwa | Under construction | 1% | 9 Apr 2026 | 31 Aug 2028 |
| Cavalli Couture95 units | Damac Properties | Al Wasl | Under construction | 20% | 8 Apr 2026 | 31 May 2025 · passed |
| Villea West229 units | Palmridge Real Estate Development | Al Satwa | Under construction | 0% | 8 Apr 2026 | 1 Nov 2027 |
| Iluka Residences57 units | MS Homes Developers | Palm Deira | Under construction | 36% | 7 Apr 2026 | 15 Aug 2026 · passed |
| Eira271 units | Neoterra Developments | Me'Aisem First | Under construction | 0% | 7 Apr 2026 | 30 Jun 2029 |
| Sera Gardens By Vision246 units | Vision Developments | Me'Aisem First | Under construction | 0% | 7 Apr 2026 | 1 Apr 2028 |
| Trussardi Residences142 units | Mira Developments | Jabal Ali First | Under construction | 36% | 6 Apr 2026 | 31 Jan 2026 · passed |
| Evora Residences77 units | Anax Developments | Jabal Ali First | Under construction | 21% | 6 Apr 2026 | 29 Aug 2026 · passed |
| Lilian Residences66 units | London Gate | Madinat Al Mataar | Under construction | 5% | 6 Apr 2026 | 1 Apr 2028 |
| Vayla Residences53 units | Blue Square Real Estate Development L. L. C | Palm Deira | Under construction | 22% | 6 Apr 2026 | 14 Jul 2026 · passed |
| Marina Place 1162 units | Emaar | Madinat Dubai Almelaheyah | Under construction | 4% | 3 Apr 2026 | 31 Dec 2028 |
| Babette Sapphire Residence66 units | Babette Realty Development | Al Jadaf | Under construction | 78% | 3 Apr 2026 | 15 May 2026 · passed |
| Havencia286 units | ALA Developments | Wadi Al Safa 5 | Under construction | 0% | 3 Apr 2026 | 31 Mar 2028 |
| Aryene Greens125 units | Diamond Star | Al Barshaa South Third | Under construction | 80% | 2 Apr 2026 | 30 Nov 2022 · passed |
| Lime Light Twin Towers734 units | Lime Light | Al Hebiah Fourth | Under construction | 71% | 2 Apr 2026 | 30 Jun 2026 · passed |
| Tomorrow 16654 units | Tomorrow World Group | Palm Deira | Under construction | 2% | 1 Apr 2026 | 31 May 2027 |
| Moonsa Residences93 units | Dugasta Properties | Warsan Fourth | Under construction | 95% | 31 Mar 2026 | 25 Aug 2025 · passed |
| White Opals49 units | AIZN Developers | Wadi Al Safa 3 | Under construction | 1% | 31 Mar 2026 | 1 Sept 2028 |
| Vincitore Aqua Flora546 units | Vincitore Development | Al Barshaa South Second | Under construction | 1% | 30 Mar 2026 | 30 Jun 2028 |
| Red Square835 units | Tiger Properties | Al Barsha South Fifth | Under construction | 27% | 27 Mar 2026 | — |
| Greenz By Danube1,458 units | Danube Properties | Al Rowaiyah First | Under construction | 0% | 27 Mar 2026 | 31 Dec 2029 |
| Celestara Residences121 units | Aldhana Development | Al Barsha South Fourth | Under construction | 3% | 26 Mar 2026 | 19 May 2028 |
| Franck Muller Yachting585 units | London Gate | Madinat Dubai Almelaheyah | Under construction | 0% | 26 Mar 2026 | 29 Jul 2028 |
| Hayat 5112 units | Dubai South | Madinat Al Mataar | Under construction | 0% | 26 Mar 2026 | 30 Jul 2028 |
| Faro The Heights291 units | Emaar | Al Yelayiss 5 | Under construction | 0% | 26 Mar 2026 | 30 Jun 2030 |
| Faro 2 The Heights200 units | Emaar | Al Yelayiss 5 | Under construction | 0% | 26 Mar 2026 | 30 Jun 2030 |
| Mayfair Nexus By Seven Mayfair473 units | Seven Mayfair | Wadi Al Safa 7 | Under construction | 1% | 25 Mar 2026 | 31 Dec 2028 |
| Raffi By Azizi171 units | Azizi Developments | Jabal Ali First | Under construction | 2% | 25 Mar 2026 | 15 Jan 2028 |
| Azizi Ruby264 units | Azizi Developments | Al Barsha South Fourth | Under construction | 3% | 25 Mar 2026 | 23 Jan 2028 |
| Lumena By Omniyat112 units | Omniyat | Business Bay | Under construction | 0% | 25 Mar 2026 | 30 Dec 2029 |
| Ag Aum Residence260 units | AG Properties | Wadi Al Safa 5 | Under construction | 2% | 24 Mar 2026 | 30 Nov 2028 |
| 77 Boulevard By Bam58 units | Bam Eskan Real Estate Development | Al Barsha South Fourth | Under construction | 18% | 24 Mar 2026 | 10 Sept 2026 · passed |
| Arian By Azizi631 units | Azizi Developments | Jabal Ali Industrial Second | Under construction | 2% | 24 Mar 2026 | 16 Jan 2028 |
| Azizi Emerald102 units | Azizi Developments | Um Hurair Second | Under construction | 3% | 24 Mar 2026 | 13 Feb 2028 |
| Talea354 units | Beyond | Madinat Dubai Almelaheyah | Under construction | 0% | 24 Mar 2026 | 30 Jun 2028 |
| Passo By Beyond552 units | Beyond | Palm Jumeirah | Under construction | 0% | 24 Mar 2026 | 31 Dec 2029 |
| Azizi Abraham420 units | Azizi Developments | Jabal Ali Industrial Second | Under construction | 2% | 24 Mar 2026 | 4 Aug 2027 |
| Azizi David256 units | Azizi Developments | Al Jadaf | Under construction | 2% | 24 Mar 2026 | 30 Sept 2028 |
| Azizi Leily272 units | Azizi Developments | Al Jadaf | Under construction | 2% | 24 Mar 2026 | 30 Sept 2028 |
| Damac Hills - Gems Estates 136 units | Damac Properties | Al Hebiah Third | Under construction | 42% | 23 Mar 2026 | 30 Nov 2026 |
| Empire Lakeviews634 units | Empire Developments | Wadi Al Safa 2 | Under construction | 2% | 23 Mar 2026 | 24 Jun 2028 |
| Whitecliffs Residences73 units | AG Properties | Palm Deira | Under construction | 6% | 23 Mar 2026 | 31 Dec 2027 |
| Cresswell Homes70 units | Merath Development | Madinat Al Mataar | Under construction | 29% | 19 Mar 2026 | 31 Dec 2026 |
| Ag Ark Tower189 units | AG Properties | Wadi Al Safa 5 | Under construction | 3% | 18 Mar 2026 | 30 Nov 2028 |
| Wasl By Azizi227 units | Azizi Developments | Palm Deira | Under construction | 2% | 18 Mar 2026 | 12 Feb 2028 |
| Azizi Amir104 units | Azizi Developments | Jabal Ali First | Under construction | 2% | 18 Mar 2026 | 17 Jun 2027 |
Source: the official project register of the Dubai Land Department and the Real Estate Regulatory Agency (RERA), read every day. A project name with a link opens its page here, with prices, payment plan and site photos.
Percent built
The share of construction finished, measured by RERA inspectors on their latest visit to the site. It is the regulator's figure, not the developer's estimate.
Registered completion date
The date the developer registered for finishing the project. A project can pass it and still be under construction; the date a developer advertises for handover can differ.
Status
Under construction, completed or cancelled, as the register lists the project. Buyers' payments for a registered off-plan project go into its escrow account, which the regulator oversees.
Dubai project status: questions and answers
How many projects are under construction in Dubai?
1,571 projects are registered as under construction in the official project register of the Dubai Land Department (DLD) and its regulator RERA. Another 1,669 are completed and 610 are cancelled. The latest site inspection on record is from 14 October 2026.
How do I check the status of an off-plan project in Dubai?
Type the name of the project, its developer or its district in the search box on this page. All 3,850 registered projects are covered; each one shows its official status, the percent built at the latest site inspection, the date of that inspection and the registered completion date.
What does the percent built mean?
It is the share of construction finished, as measured by RERA inspectors on their latest visit to the site. It is not the developer's own estimate. 830 projects were inspected in the last 90 days.
What is the registered completion date?
It is the completion date the developer registered with the regulator. A project can still be under construction after it: 250 of the 1,571 projects under construction are past their registered date. A developer may also advertise a different handover date.
How often is the project status updated?
Every day. dxbpropy.ai reads the official register daily and re-reads every project once a week, so a new inspection or a change of status shows here within a day or a week.