Aqua Properties Developer

Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date.

Under construction

3

Units

2,083

Delivered

4

Behind schedule

3

Cancelled

0

Handovers 2026
2
Handovers 2027
0
Handovers 2028
0
Handovers 2029
0
Handovers 2030
0

Projects

% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.

ProjectStatusBuiltHandover dateDLD planned dateNote
The Community Motor CityBehind schedule95%Dec 2025Oct 20259 months past promised handover
The Central DowntownBehind schedule10%Mar 2026Mar 20286 months past promised handover 24 months later on DLD than advertised
The Community - Sports ArenaBehind schedule22%Mar 2026Oct 20276 months past promised handover 19 months later on DLD than advertised
J5Delivered100%Aug 2015Aug 2015
J8Delivered100%Sept 2016Sept 2016
O10Delivered100%Nov 2022Nov 2022
The CommunityDelivered100%Sept 2024Sept 2024