Aqua Properties Developer
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date.
Under construction
3
Units
2,083
Delivered
4
Behind schedule
3
Cancelled
0
Handovers 2026
2
Handovers 2027
0
Handovers 2028
0
Handovers 2029
0
Handovers 2030
0
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| The Community Motor City | Behind schedule | 95% | Dec 2025 | Oct 2025 | 9 months past promised handover |
| The Central Downtown | Behind schedule | 10% | Mar 2026 | Mar 2028 | 6 months past promised handover 24 months later on DLD than advertised |
| The Community - Sports Arena | Behind schedule | 22% | Mar 2026 | Oct 2027 | 6 months past promised handover 19 months later on DLD than advertised |
| J5 | Delivered | 100% | Aug 2015 | Aug 2015 | |
| J8 | Delivered | 100% | Sept 2016 | Sept 2016 | |
| O10 | Delivered | 100% | Nov 2022 | Nov 2022 | |
| The Community | Delivered | 100% | Sept 2024 | Sept 2024 |
✦ Ask about any developer
Track record, projects handing over by year and construction progress — from official records.