Wasl
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date.
Under construction
22
Units
7,237
Delivered
5
Behind schedule
0
Cancelled
0
Handovers 2026
1
Handovers 2027
7
Handovers 2028
7
Handovers 2029
5
Handovers 2030
2
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| Park Views Residences A | On schedule | 96% | Dec 2026 | – | |
| Park Views Residences B | On schedule | 91% | Feb 2027 | Mar 2027 | |
| Hillside Residences 2 | Early stage | 12% | Sept 2027 | – | |
| Hillside Residences 1 | Early stage | 15% | Sept 2027 | – | |
| South Garden B | Early stage | 16% | Dec 2027 | Dec 2027 | |
| South Garden C | Early stage | 16% | Dec 2027 | Dec 2027 | |
| South Garden A | Early stage | 16% | Dec 2027 | Dec 2027 | |
| Hillside Residences 3 | Early stage | 5% | Dec 2027 | – | |
| South Garden D | Early stage | 6% | May 2028 | May 2028 | |
| South Garden E | Early stage | 8% | May 2028 | May 2028 | |
| Ashwood Estates | Early stage | 0% | Sept 2028 | Sept 2028 | |
| Cedarwood Estates | Early stage | 0% | Oct 2028 | Oct 2028 | |
| Pinewood Estate Homes | Early stage | 0% | Nov 2028 | Nov 2028 | |
| Avenue Park Towers | Early stage | 8% | Dec 2028 | Dec 2028 | |
| One.B Tower | Early stage | 6% | Dec 2028 | Dec 2028 | |
| Cedarwood Estates-South | Early stage | 0% | Jan 2029 | Jan 2029 | |
| Boulevard Park 2 | Early stage | 0% | Jun 2029 | Nov 2029 | 5 months later on DLD than advertised |
| Boulevard Park 1 | Early stage | 0% | Jun 2029 | Apr 2030 | 10 months later on DLD than advertised |
| Boulevard Living 2 | Early stage | 0% | Dec 2029 | Dec 2029 | |
| Boulevard Living 1 | Early stage | 0% | Dec 2029 | Dec 2029 | |
| Avenue Park Towers Ii | Early stage | 0% | Mar 2030 | Mar 2030 | |
| Nine Collective | Early stage | 0% | Apr 2030 | Apr 2030 | |
| Gardeniatownhomes @ Wasl Gate | Delivered | 100% | Mar 2020 | Mar 2020 | |
| Park Gate Residences | Delivered | 100% | Oct 2020 | Oct 2020 | |
| The Nook | Delivered | 100% | Jan 2022 | Jan 2022 | |
| 1 Residences | Delivered | 100% | Sept 2022 | Sept 2022 | |
| Gardenia Townhomes Ii | Delivered | 100% | Jun 2024 | Jun 2024 |
✦ Ask about any developer
Track record, projects handing over by year and construction progress — from official records.