Samana Developers

Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date.

Under construction

48

Units

14,881

Delivered

6

Behind schedule

7

Cancelled

0

Handovers 2026
12
Handovers 2027
10
Handovers 2028
19
Handovers 2029
5
Handovers 2030
0

Projects

% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.

ProjectStatusBuiltHandover dateDLD planned dateNote
Samana Waves 2Behind schedule47%Mar 2026Mar 20266 months past promised handover
Samana PortofinoBehind schedule47%Mar 2026–6 months past promised handover
Samana WavesBehind schedule90%Apr 2026Apr 20266 months past promised handover
Samana Mykonos SignatureBehind schedule80%Apr 2026Apr 20265 months past promised handover
Samana SkyrosBehind schedule60%Apr 2026Apr 20265 months past promised handover
Samana Ivy GardensBehind schedule27%Jun 2026–3 months past promised handover
Samana MykonosBehind schedule81%Jun 2026Apr 20263 months past promised handover
Samana Golf ViewsSlower than needed35%Jul 2026–
California 2 By SdSlower than needed34%Oct 2026Oct 2026
Ocean Pearl By SdSlower than needed25%Dec 2026Dec 2026
Samana Barari ViewsSlower than needed27%Mar 2027Mar 2027
Rome 2 By SdSlower than needed33%Jun 2027Jun 2027
Samana Park MeadowsSlower than needed27%Aug 2027Aug 2027
Rome By SdSlower than needed39%Dec 2027Dec 2027
Manhattan 1 By SdOn schedule30%––
Miami By SdOn schedule66%Jul 2026Jul 2026
California By SdEarly stage15%––
Manhattan 2 By SdEarly stage21%Nov 2026Nov 2026
Ocean Pearl 2 By SdEarly stage23%Mar 2027Mar 2027
Samana Barari Views 2Early stage20%Sept 2027–
Samana Lake ViewsEarly stage14%Oct 2027–
Samana Lake Views 2Early stage9%Dec 2027–
Samana Ivy Gardens 2Early stage15%Dec 2027Dec 2027
Samana AvenueEarly stage21%Dec 2027Dec 2027
Samana IbizaEarly stage3%Feb 2028Feb 2028
Samana Barari LagoonsEarly stage12%Mar 2028Mar 2028
Samana Hills SouthEarly stage5%May 2028May 2028
Samana ResortsEarly stage6%May 2028May 2028
Ocean Crest By SdEarly stage0%Jun 2028Jun 2028
Ocean Bay By Samana DevelopersEarly stage2%Jun 2028Jun 2028
Rome 3 By SdEarly stage2%Jun 2028Jun 2028
Samana Sky ViewsEarly stage2%Jul 2028Jul 2028
Samana Hills South 2Early stage5%Aug 2028Aug 2028
Samana Hills South 3Early stage5%Aug 2028Aug 2028
Samana Business ParkEarly stage6%Sept 2028Sept 2028
Samana ParkvilleEarly stage5%Sept 2028Sept 2028
Greenfield By Samana DevelopersEarly stage1%Oct 2028Oct 2028
Samana Business Park 2Early stage3%Oct 2028Oct 2028
Samana Barari HeightsEarly stage4%Oct 2028Oct 2028
Samana Barari AvenueEarly stage5%Oct 2028Oct 2028
Samana South HavenEarly stage0%Dec 2028Dec 2028
Samana Boulevard HeightsEarly stage3%Dec 2028Dec 2028
Samana Imperial GardenEarly stage4%Dec 2028Dec 2028
Portside By Samana DevelopersEarly stage0%Jun 2029Jun 2029
Samana South Haven 2Early stage0%Jun 2029Jun 2029
Greenfield 2 By Samana DevelopersEarly stage0%Aug 2029Aug 2029
Samana Business HubEarly stage0%Sept 2029Sept 2029
Portside 2 By Samana DevelopersEarly stage0%Dec 2029Dec 2029
Samana GreenDelivered100%Dec 2020Dec 2020
Samana HillsDelivered100%Jun 2022Jun 2022
Samana Golf AvenueDelivered100%Apr 2023Apr 2023
Samana Park ViewsDelivered100%Apr 2024Apr 2024
Samana MiamiDelivered100%Dec 2024Dec 2024
Samana SantoriniDelivered100%Apr 2025Apr 2025