T H O E
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date.
Under construction
4
Units
1,426
Delivered
0
Behind schedule
3
Cancelled
0
Handovers 2026
0
Handovers 2027
0
Handovers 2028
0
Handovers 2029
0
Handovers 2030
0
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| The Heart Of Europe 1 | Behind schedule | 86% | Sept 2022 | Sept 2022 | 48 months past promised handover |
| The Heart Of Europe | Behind schedule | 82% | Sept 2022 | Sept 2022 | 48 months past promised handover |
| The Heart Of Europe 2 | Behind schedule | 93% | Apr 2025 | Apr 2025 | 17 months past promised handover |
| Sea Horse Villa | Not enough data | 50% | – | – |
✦ Ask about any developer
Track record, projects handing over by year and construction progress — from official records.