Dubai project status
The official construction status of every project in the Dubai Land Department (DLD) project register: how far it is built at the latest RERA site inspection, when it was inspected and the completion date the developer registered. 1,571 projects are under construction; the latest inspection on record is from 14 Oct 2026. Project register as of 16 Oct 2026.
| Project | Developer | District in the register | Status | Built | Latest inspection | Registered completion |
|---|---|---|---|---|---|---|
| The Residences, Al Habtoor Grand272 units | Al Habtoor | Marsa Dubai | Under construction | 35% | 11 Jun 2026 | — |
| Amali Island24 units | Amali Properties | World Islands | Under construction | 16% | 11 Jun 2026 | 31 Mar 2027 |
| One By Nine46 units | Nine Developments | Nad Al Shiba First | Under construction | 50% | 11 Jun 2026 | 8 Nov 2025 · passed |
| Rome 3 By Sd85 units | Samana Developers | Wadi Al Safa 3 | Under construction | 2% | 11 Jun 2026 | 30 Jun 2028 |
| Golden Woods Albab Views132 units | Golden Woods Real Estate Development | Madinat Al Mataar | Under construction | 30% | 11 Jun 2026 | 28 Feb 2027 |
| Greenfield By Samana Developers310 units | Samana Developers | Warsan Fourth | Under construction | 1% | 11 Jun 2026 | 31 Oct 2028 |
| Samana Lake Views 2548 units | Samana Developers | Me'Aisem First | Under construction | 9% | 10 Jun 2026 | — |
| Address Residences L Dubai Hills Estate582 units | Emaar | Hadaeq Sheikh Mohammed Bin Rashid | Under construction | 26% | 10 Jun 2026 | 28 Feb 2029 |
| Golf Grove By Regent98 units | Regent Developments | Me'Aisem First | Under construction | 9% | 10 Jun 2026 | 2 Jan 2028 |
| Ashley Hills616 units | TownX | Al Barshaa South Third | Under construction | 74% | 10 Jun 2026 | 31 Mar 2027 |
| Vue Doree50 units | Crystal Bay | Palm Deira | Under construction | 1% | 10 Jun 2026 | 14 Nov 2028 |
| Avarra By Palace694 units | Emaar | Business Bay | Under construction | 0% | 10 Jun 2026 | 30 Jun 2031 |
| Damac Islands 2 - Bermuda469 units | Damac Properties | Al Yelayiss 1 | Under construction | 0% | 10 Jun 2026 | 30 Jun 2030 |
| Damac Islands 2 - Cuba540 units | Damac Properties | Al Yelayiss 1 | Under construction | 0% | 10 Jun 2026 | 30 Jun 2030 |
| Damac Islands 2 - Barbados 1382 units | Damac Properties | Al Yelayiss 1 | Under construction | 0% | 10 Jun 2026 | 30 Jun 2030 |
| Damac Islands 2 - Barbados 2362 units | Damac Properties | Al Yelayiss 1 | Under construction | 0% | 10 Jun 2026 | 30 Jun 2030 |
| Damac Islands 2 - Maui434 units | Damac Properties | Al Yelayiss 1 | Under construction | 0% | 10 Jun 2026 | 30 Jun 2030 |
| The Waterside Villas By Ellington17 units | Ellington Properties | Wadi Al Safa 3 | Under construction | 32% | 9 Jun 2026 | 30 Jun 2026 · passed |
| Rove Home Residences By Irth349 units | Irth Developments | Burj Khalifa | Under construction | 63% | 9 Jun 2026 | 30 Apr 2026 · passed |
| The Quayside119 units | Ellington Properties | Business Bay | Under construction | 55% | 9 Jun 2026 | 31 Mar 2026 · passed |
| The Lakeview Villas By Ellington22 units | Ellington Properties | Wadi Al Safa 3 | Under construction | 10% | 9 Jun 2026 | 30 Aug 2026 · passed |
| Violet Tower287 units | Dubai Investment Real Estate | Al Barsha South Fourth | Under construction | 70% | 9 Jun 2026 | 30 Jun 2026 · passed |
| The Beachfront Villas By Ellington21 units | Ellington Properties | Wadi Al Safa 3 | Under construction | 35% | 9 Jun 2026 | 31 Aug 2026 · passed |
| Casa Vista Residence By Golden Woods90 units | Golden Woods Real Estate Development | Al Barsha South Fourth | Under construction | 90% | 9 Jun 2026 | 30 Jun 2026 · passed |
| Palace Residences Creek Blue512 units | Emaar | Al Khairan First | Under construction | 21% | 9 Jun 2026 | 31 Mar 2029 |
| The Valley - Velora488 units | Emaar | Al Yufrah 1 | Under construction | 50% | 9 Jun 2026 | 31 Aug 2028 |
| The Oasis - Palmiera 359 units | Emaar | Me'Aisem Second | Under construction | 73% | 9 Jun 2026 | 31 Oct 2028 |
| The Valley - Kaia156 units | Emaar | Al Yufrah 1 | Under construction | 19% | 9 Jun 2026 | 31 Jul 2028 |
| The Valley - Elva244 units | Emaar | Al Yufrah 1 | Under construction | 26% | 9 Jun 2026 | 31 Oct 2028 |
| The Valley - Avelia139 units | Emaar | Al Yufrah 1 | Under construction | 0% | 9 Jun 2026 | 31 Dec 2029 |
| Serro The Heights383 units | Emaar | Al Yelayiss 5 | Under construction | 1% | 9 Jun 2026 | 31 Mar 2030 |
| Serro 2 The Heights397 units | Emaar | Al Yelayiss 5 | Under construction | 1% | 9 Jun 2026 | 31 May 2030 |
| Salva The Heights483 units | Emaar | Al Yelayiss 5 | Under construction | 1% | 9 Jun 2026 | 31 Jul 2030 |
| Raw District By Imtiaz Cr610 units | Imtiaz Developments | Jabal Ali Industrial Second | Under construction | 0% | 9 Jun 2026 | 15 Dec 2029 |
| Raw District By Imtiaz R672 units | Imtiaz Developments | Jabal Ali Industrial Second | Under construction | 0% | 9 Jun 2026 | 15 Dec 2029 |
| Rosemont Residences49 units | Ellington Properties | Al Barsha South Fifth | Under construction | 43% | 8 Jun 2026 | — |
| 171 Garden Heights159 units | JAD Global | Al Satwa | Under construction | 34% | 8 Jun 2026 | 31 Dec 2026 |
| Oasis Loft164 units | Uniestate Properties | Nadd Hessa | Under construction | 50% | 8 Jun 2026 | 30 Sept 2026 · passed |
| Bellavion By Sunrise275 units | Sunrise Capital Real Estate Development L. L. C | Jabal Ali First | Under construction | 10% | 8 Jun 2026 | 1 Dec 2027 |
| Park Gate 217 units | Emaar | Hadaeq Sheikh Mohammed Bin Rashid | Under construction | 55% | 8 Jun 2026 | 28 Feb 2027 |
| Maison Cannelle Residences By Casa Moderna40 units | Casa Moderna | Jabal Ali First | Under construction | 40% | 8 Jun 2026 | 1 Jun 2026 · passed |
| Samana Hills South 2140 units | Samana Developers | Saih Shuaib 2 | Under construction | 5% | 8 Jun 2026 | 31 Aug 2028 |
| Terra Gardens561 units | Emaar | Madinat Al Mataar | Under construction | 0% | 8 Jun 2026 | 31 Oct 2029 |
| Waada - Altura 1381 units | BT Properties | Madinat Al Mataar | Under construction | 2% | 8 Jun 2026 | 12 Apr 2029 |
| Lawncrest By Zimaya183 units | Zimaya Properties | Me'Aisem First | Under construction | 0% | 8 Jun 2026 | 14 Jun 2029 |
| Avenue Park Towers Ii596 units | Wasl | Al Kifaf | Under construction | 0% | 8 Jun 2026 | 6 Mar 2030 |
| Damac Hills - Autograph Collection55 units | Damac Properties | Al Hebiah Third | Under construction | 9% | 6 Jun 2026 | 30 May 2027 |
| Hillsedge406 units | Emaar | Hadaeq Sheikh Mohammed Bin Rashid | Under construction | 26% | 6 Jun 2026 | 31 Jan 2029 |
| Rose Gardens 349 units | Roz Real Estate Development | Al Barshaa South Third | Under construction | 76% | 5 Jun 2026 | 2 May 2026 · passed |
| Ellington Sands I471 units | Ellington Properties | Palm Deira | Under construction | 0% | 5 Jun 2026 | 31 Dec 2028 |
Source: the official project register of the Dubai Land Department and the Real Estate Regulatory Agency (RERA), read every day. A project name with a link opens its page here, with prices, payment plan and site photos.
Percent built
The share of construction finished, measured by RERA inspectors on their latest visit to the site. It is the regulator's figure, not the developer's estimate.
Registered completion date
The date the developer registered for finishing the project. A project can pass it and still be under construction; the date a developer advertises for handover can differ.
Status
Under construction, completed or cancelled, as the register lists the project. Buyers' payments for a registered off-plan project go into its escrow account, which the regulator oversees.
Dubai project status: questions and answers
How many projects are under construction in Dubai?
1,571 projects are registered as under construction in the official project register of the Dubai Land Department (DLD) and its regulator RERA. Another 1,669 are completed and 610 are cancelled. The latest site inspection on record is from 14 October 2026.
How do I check the status of an off-plan project in Dubai?
Type the name of the project, its developer or its district in the search box on this page. All 3,850 registered projects are covered; each one shows its official status, the percent built at the latest site inspection, the date of that inspection and the registered completion date.
What does the percent built mean?
It is the share of construction finished, as measured by RERA inspectors on their latest visit to the site. It is not the developer's own estimate. 830 projects were inspected in the last 90 days.
What is the registered completion date?
It is the completion date the developer registered with the regulator. A project can still be under construction after it: 250 of the 1,571 projects under construction are past their registered date. A developer may also advertise a different handover date.
How often is the project status updated?
Every day. dxbpropy.ai reads the official register daily and re-reads every project once a week, so a new inspection or a change of status shows here within a day or a week.