Peace Homes Development

Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date.

Under construction

9

Units

3,400

Delivered

1

Behind schedule

2

Cancelled

0

Handovers 2026
4
Handovers 2027
3
Handovers 2028
2
Handovers 2029
0
Handovers 2030
0

Projects

% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.

ProjectStatusBuiltHandover dateDLD planned dateNote
Sky Livings By Peace HomesBehind schedule60%Jun 2026–3 months past promised handover
Sky Suites By Peace HomesBehind schedule56%Jun 2026Dec 20253 months past promised handover
Sky Vista By Peace HomesSlower than needed61%Jun 2026–
Natuzzi Harmony Residences By Peace HomesEarly stage20%Sept 2026Sept 2026
Peace Lagoons By Peace HomesEarly stage3%Jun 2027Sept 2028 15 months later on DLD than advertised
Peace Avenue By Peace HomesEarly stage4%Dec 2027Jan 2029 13 months later on DLD than advertised
Sky Harmony By Peace HomesEarly stage13%Dec 2027Jan 2029 13 months later on DLD than advertised
Peace Lagoons Ii By Peace HomesEarly stage4%Jun 2028Jan 2029 6 months later on DLD than advertised
Sky Line By Peace HomesEarly stage0%Dec 2028May 2030 17 months later on DLD than advertised
Empire ResidenceDelivered100%Sept 2022Sept 2022