Vincitore Real Estate Development LLC
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date.
Under construction
5
Units
4,138
Delivered
3
Behind schedule
1
Cancelled
0
Handovers 2026
0
Handovers 2027
0
Handovers 2028
1
Handovers 2029
0
Handovers 2030
1
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| Vincitore Volare | Behind schedule | 63% | Jun 2025 | Jun 2025 | 16 months past promised handover |
| Vincitore Aqua Dimore | Early stage | 7% | – | – | |
| Vincitore Dolce Vita | Early stage | 22% | – | – | |
| Vincitore Aqua Flora | Early stage | 1% | Jun 2028 | Jun 2028 | |
| Vincitore Wellness Estate | Early stage | 0% | Feb 2030 | Feb 2030 | |
| Vincitore Palacio | Delivered | 100% | May 2017 | May 2017 | |
| Vincitore Boulevard | Delivered | 100% | Oct 2020 | Oct 2020 | |
| Vincitore Benessere | Delivered | 100% | Jan 2023 | Jan 2023 |