Oksa Developer
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.
This developer has 2 project(s) in the register, too few for a track record: read the counts as single projects.
Under construction
2
Units
136
Delivered (all years)
0
Behind schedule
0
Cancelled (all years)
0
Sales in this developer's projects
Registered sales by period; the latest figures run to 11 Nov 2026.
| Period | Off-plan sales | Villa plots sold on plan | Resales in completed projects |
|---|---|---|---|
| Last 12 months | AED 20.11M 21 sales | – | – |
| 2026 so far | AED 12.74M 15 sales | – | – |
| 2025 | AED 32.27M 36 sales | – | – |
Latest from developers
Offers, launches and news from developers' sales teams, updated through the day.
Sales-team items from the last 45 days, Instagram posts from the last 90 days; offers pinned to this developer show at any age while they are valid.
- 9 NovNewsAristo by OKSA Developer in Dubai South completes excavation, rafting and plain cement concrete works.Instagram ↗
- 26 SeptNewsOKSA Developer opens new office and sales showroom reflecting its design and development standards.Instagram ↗
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| The Eighty Three | On schedule | 60% | Dec 2026project register | Dec 2026 | |
| Aristo | Early stage | 0% | Dec 2028project register | Dec 2028 |
Oksa Developer: questions and answers
How many projects is Oksa Developer building in Dubai?
Oksa Developer has 2 projects under construction in Dubai, with 136 homes in total, according to the Dubai Land Department project register.
When do Oksa Developer projects hand over?
Handover years for Oksa Developer's projects under construction, by the developer's date where it gave one, else the date in new-project listings, else the Dubai Land Department project register's date: 1 project in 2026 and 1 project in 2028.
Which Oksa Developer projects hand over next?
The next Oksa Developer projects to hand over are The Eighty Three (December 2026) and Aristo (December 2028), by the same dates (the developer's where it gave one, else the new-project listings', else the Dubai Land Department project register's).
How far is construction of Oksa Developer's projects?
Among Oksa Developer's projects under construction, the most advanced are The Eighty Three (60% built) and Aristo (0% built), from official RERA site inspections.