Dubai project status

The official construction status of every project in the Dubai Land Department (DLD) project register: how far it is built at the latest RERA site inspection, when it was inspected and the completion date the developer registered. 1,570 projects are under construction; the latest inspection on record is from 14 Oct 2026. Project register as of 15 Oct 2026.

Under construction
1,570
registered projects
Completed
1,670
registered projects
Inspected in the last 90 days
829
site inspections by RERA
Past the registered date
250
still under construction
Under constructionCompletedCancelled1,568 projects, latest inspection first
ProjectDeveloperDistrict in the registerStatusBuiltLatest inspectionRegistered completion
Eden Hills281 unitsH&H DevelopmentHadaeq Sheikh Mohammed Bin RashidUnder construction4%22 Sept 202625 Dec 2026
One Park Square By Iman269 unitsIman DevelopersAl Barsha South FourthUnder construction20%22 Sept 202630 Jun 2028
Selora Residences32 unitsSwank DevelopmentWadi Al Safa 3Under construction3%22 Sept 202630 Apr 2027
Damac Riverside Views - Capri 1824 unitsDamac PropertiesDubai Investment Park SecondUnder construction8%22 Sept 202631 Mar 2029
Damac Riverside Views - Capri 2576 unitsDamac PropertiesDubai Investment Park SecondUnder construction8%22 Sept 202631 Mar 2029
Ocean Crest By Sd63 unitsSamana DevelopersPalm DeiraUnder construction1%22 Sept 202630 Jun 2028
Ocean Bay By Samana Developers143 unitsSamana DevelopersPalm DeiraUnder construction3%22 Sept 202630 Jun 2028
Damac District1,139 unitsDamac PropertiesAl Hebiah ThirdUnder construction4%22 Sept 202630 Mar 2029
Tonino Lamborghini Residences553 unitsGulf Land Property DevelopersNad Al Shiba FirstUnder construction60%21 Sept 202631 Dec 2026
Eywa Dubai53 unitsRvl Real EstateBusiness BayUnder construction64%21 Sept 20261 Apr 2026 · passed
The First Collection At Dubai Sports City478 unitsThe First GroupAl Hebiah FourthUnder construction66%21 Sept 202630 Nov 2027
Olivia Residences231 unitsKarma DevelopersDubai Investment Park FirstUnder construction38%21 Sept 202624 Dec 2026
Skyscape1,852 unitsSobhaBukadraUnder construction38%21 Sept 202631 Dec 2029
Saray Prime Residence121 unitsUnique Saray DevelopmentWadi Al Safa 5Under construction2%21 Sept 202631 Oct 2027
Azra Residence126 unitsENAAM Properties DevelopmentWadi Al Safa 5Under construction28%21 Sept 202631 Dec 2027
Sakura Gardens By Hre1,429 unitsHRE DevelopmentWadi Al Safa 2Under construction4%21 Sept 202630 Jun 2029
Elitz 3 By Danube692 unitsDanube PropertiesAl Barsha South FourthUnder construction38%18 Sept 2026—
Sobha Seahaven Tower B & C451 unitsSobhaMarsa DubaiUnder construction40%18 Sept 202631 Oct 2028
Parkwood Residences174 unitsArabian Gulf PropertiesAl Barsha South FourthUnder construction57%18 Sept 202630 Apr 2026 · passed
Ag Central96 unitsAG PropertiesWadi Al Safa 5Under construction59%17 Sept 202631 Oct 2026
Ag Square372 unitsAG PropertiesWadi Al Safa 5Under construction69%17 Sept 202630 Sept 2026 · passed
Q Gardens Lofts 2221 unitsAYS DeveloperAl Barsha South FourthUnder construction36%17 Sept 2026—
Casa Canal68 unitsAHS PropertiesAl WaslUnder construction38%17 Sept 2026—
Luxur Tower By Imtiaz361 unitsImtiaz DevelopmentsAl Barsha South FourthUnder construction90%17 Sept 202615 Dec 2026
Manhattan 1 By Sd193 unitsSamana DevelopersAl Barsha South FourthUnder construction30%17 Sept 2026—
Manhattan 2 By Sd193 unitsSamana DevelopersAl Barsha South FourthUnder construction21%17 Sept 20261 Nov 2026
California 2 By Sd155 unitsSamana DevelopersJabal Ali FirstUnder construction34%17 Sept 202631 Oct 2026
Fia192 unitsNshamaAl Yelayiss 2Under construction85%17 Sept 2026—
Savannah154 unitsNshamaAl Yelayiss 2Under construction43%17 Sept 202630 Apr 2027
Ocean Pearl By Sd100 unitsSamana DevelopersPalm DeiraUnder construction25%17 Sept 202631 Dec 2026
Hillcrest171 unitsNshamaAl Yelayiss 2Under construction38%17 Sept 202630 Jun 2027
Ocean Pearl 2 By Sd96 unitsSamana DevelopersPalm DeiraUnder construction23%17 Sept 202631 Mar 2027
Ember At Park Five205 unitsDeyaarMe'Aisem FirstUnder construction18%17 Sept 20261 Jun 2027
Ellison148 unitsNshamaAl Yelayiss 2Under construction40%17 Sept 202630 Nov 2027
Binghatti Hillside411 unitsBinghatti DevelopersAl Barshaa South SecondUnder construction80%17 Sept 202630 Jun 2026 · passed
Bliss Tower131 unitsPure Bliss DevelopmentWadi Al Safa 5Under construction93%17 Sept 202615 Dec 2026
Avenue Residence 8104 unitsNabni DevelopmentsJabal Ali FirstUnder construction18%17 Sept 202630 Jun 2028
Sunset Bay Three By Imtiaz63 unitsImtiaz DevelopmentsPalm DeiraUnder construction60%17 Sept 202620 Mar 2027
Ivy At Park Five210 unitsDeyaarMe'Aisem FirstUnder construction6%17 Sept 202631 Dec 2027
Binghatti Hillcrest396 unitsBinghatti DevelopersAl Barshaa South ThirdUnder construction60%17 Sept 202631 Dec 2026
Binghatti Luxuria469 unitsBinghatti DevelopersAl Barsha South FifthUnder construction7%17 Sept 202630 Jul 2027
Prestige Gardens By Prestige One48 unitsPrestige One DevelopmentsAl SatwaUnder construction0%17 Sept 202630 Sept 2028
The Vault By Imtiaz54 unitsImtiaz DevelopmentsWadi Al Safa 3Under construction0%17 Sept 20261 Jun 2029
Creek Views108 unitsIrazAl JadafUnder construction39%16 Sept 2026—
360 Riverside Crescent910 unitsSobhaBukadraUnder construction51%16 Sept 2026—
Rome By Sd42 unitsSamana DevelopersWadi Al Safa 3Under construction39%16 Sept 202631 Dec 2027
Rome 2 By Sd42 unitsSamana DevelopersWadi Al Safa 3Under construction33%16 Sept 202630 Jun 2027
The One By Prestige One41 unitsPrestige One DevelopmentsAl Thanyah FirstUnder construction7%16 Sept 202630 Jun 2027
Essenlife Residence357 unitsObject One Real Estate DevelopmentAl Barsha South FifthUnder construction7%16 Sept 202630 Mar 2028
Alta View Skyhomes507 unitsObject One Real Estate DevelopmentAl Barsha South FourthUnder construction6%16 Sept 202630 Jun 2029

Source: the official project register of the Dubai Land Department and the Real Estate Regulatory Agency (RERA), read every day. A project name with a link opens its page here, with prices, payment plan and site photos.

Percent built

The share of construction finished, measured by RERA inspectors on their latest visit to the site. It is the regulator's figure, not the developer's estimate.

Registered completion date

The date the developer registered for finishing the project. A project can pass it and still be under construction; the date a developer advertises for handover can differ.

Status

Under construction, completed or cancelled, as the register lists the project. Buyers' payments for a registered off-plan project go into its escrow account, which the regulator oversees.

Dubai project status: questions and answers

How many projects are under construction in Dubai?

1,570 projects are registered as under construction in the official project register of the Dubai Land Department (DLD) and its regulator RERA. Another 1,670 are completed and 610 are cancelled. The latest site inspection on record is from 14 October 2026.

How do I check the status of an off-plan project in Dubai?

Type the name of the project, its developer or its district in the search box on this page. All 3,850 registered projects are covered; each one shows its official status, the percent built at the latest site inspection, the date of that inspection and the registered completion date.

What does the percent built mean?

It is the share of construction finished, as measured by RERA inspectors on their latest visit to the site. It is not the developer's own estimate. 829 projects were inspected in the last 90 days.

What is the registered completion date?

It is the completion date the developer registered with the regulator. A project can still be under construction after it: 250 of the 1,570 projects under construction are past their registered date. A developer may also advertise a different handover date.

How often is the project status updated?

Every day. dxbpropy.ai reads the official register daily and re-reads every project once a week, so a new inspection or a change of status shows here within a day or a week.