Gulf Land Property Developers

Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date.

Under construction

3

Units

999

Delivered

1

Behind schedule

2

Cancelled

0

Handovers 2026
1
Handovers 2027
0
Handovers 2028
0
Handovers 2029
0
Handovers 2030
0

Projects

% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.

ProjectStatusBuiltHandover dateDLD planned dateNote
Tonino Lamborghini ResidencesBehind schedule60%Dec 2024Dec 202621 months past promised handover 24 months later on DLD than advertised
Serenity Lakes 2Behind schedule50%Nov 2025Nov 202511 months past promised handover
Paradise HillsSlower than needed84%Dec 2026Dec 2025
Serenity Lakes 5Delivered100%Sept 2022Sept 2022