Dubai project status

The official construction status of every project in the Dubai Land Department (DLD) project register: how far it is built at the latest RERA site inspection, when it was inspected and the completion date the developer registered. 1,570 projects are under construction; the latest inspection on record is from 14 Oct 2026. Project register as of 15 Oct 2026.

Under construction
1,570
registered projects
Completed
1,670
registered projects
Inspected in the last 90 days
829
site inspections by RERA
Past the registered date
250
still under construction
Under constructionCompletedCancelled1,669 projects, latest inspection first
ProjectDeveloperDistrict in the registerStatusBuiltLatest inspectionRegistered completion
Binghatti Apex552 unitsBinghatti DevelopersAl Barsha South FourthCompleted100%21 Apr 202630 Apr 2026
Volna By Kasco71 unitsKasco DevelopmentsAl JadafCompleted100%20 Apr 202631 May 2026
Cresswell Residences72 unitsMerath DevelopmentMadinat Al MataarCompleted100%15 Apr 202626 Jun 2025
Haven Living51 unitsMetac PropertiesPalm DeiraCompleted100%14 Apr 202626 Dec 2025
The Veranda Collection 112 unitsPacifique Global PropertiesAl Barsha South FourthCompleted100%14 Apr 202615 Sept 2025
Sobha Hartland - Crest Grande985 unitsSobhaAl MerkadhCompleted100%13 Apr 202630 Jun 2026
Divine Residencia69 unitsTakmeel Real Estate Development L. L. CAl Hebiah SecondCompleted100%13 Apr 2026—
Damac Lagoons - Santorini (3)96 unitsDamac PropertiesAl Hebiah FifthCompleted100%9 Apr 202629 Jul 2025
Damac Lagoons - Costa Brava (1)555 unitsDamac PropertiesAl Hebiah FifthCompleted100%9 Apr 202629 Jul 2025
Jannat362 unitsDeyaarMe'Aisem FirstCompleted100%8 Apr 2026—
Marquis Galleria126 unitsMarquis DevelopersAl Barshaa South ThirdCompleted100%7 Apr 202631 Dec 2024
The Fields At D11 - Mbrmc1,028 unitsG&Co - FzWadi Al Safa 3Completed100%6 Apr 202631 May 2023
Damac Lagoons - Malta (2)367 unitsDamac PropertiesAl Hebiah FifthCompleted100%6 Apr 202629 Sept 2025
The Haven Garden199 unitsMetrical Real Estate DevelopmentAl Barsha South FourthCompleted100%6 Apr 2026—
Waha Living By Al Yakka71 unitsAl Yakka DeveloperAl SatwaCompleted100%6 Apr 202630 Sept 2025
Nas3288 unitsRabdan DevelopmentsAl Barshaa South ThirdCompleted100%2 Apr 20261 Feb 2026
Arbor View171 unitsEllington PropertiesAl Barshaa South ThirdCompleted100%2 Apr 2026—
Vista By Prestige One140 unitsPrestige One DevelopmentsAl Hebiah FourthCompleted100%27 Mar 202630 Jun 2025
The Residence By Prestige One98 unitsPrestige One DevelopmentsAl Barsha South FourthCompleted100%25 Mar 202630 Nov 2025
The Valley - Farm Gardens146 unitsEmaarAl Yufrah 1Completed100%24 Mar 202631 Aug 2026
Pg One At Al Furjan121 unitsPure Gold Real Estate DevelopmentJabal Ali FirstCompleted100%23 Mar 2026—
Sunridge130 unitsEmaarMadinat Dubai AlmelaheyahCompleted100%17 Mar 2026—
Silver Park Residency76 unitsManjothi Real Estate DevelopmentWarsan FourthCompleted100%17 Mar 202630 Oct 2025
Ellington House Ii166 unitsEllington PropertiesHadaeq Sheikh Mohammed Bin RashidCompleted100%12 Mar 202630 Apr 2025
Neva Residences409 unitsTiger PropertiesAl Barsha South FourthCompleted100%11 Mar 202631 Dec 2025
Aras Heights73 unitsAras GroupWadi Al Safa 3Completed100%11 Mar 202631 Dec 2023
Cubix Residences72 unitsQUBE DevelopmentAl Barsha South FourthCompleted100%11 Mar 20261 Nov 2025
The Valley - Elora430 unitsEmaarAl Yufrah 1Completed100%10 Mar 202630 Sept 2026
Elegance By Chaimaa Holding118 unitsChaimaa HoldingAl Barsha South FourthCompleted100%10 Mar 20261 Nov 2024
Ra1n Residence146 unitsObject One Real Estate DevelopmentAl Barsha South FourthCompleted100%10 Mar 202623 Feb 2025
Stonehenge Residences 2156 unitsSegrex DevelopmentAl Barsha South FourthCompleted100%24 Feb 2026—
Ashton Park Residences111 unitsMirfa IBCAl Barsha South FourthCompleted100%20 Feb 2026—
Samana Santorini157 unitsSamana DevelopersAl Hebiah SecondCompleted100%19 Feb 20261 Apr 2025
Elevate By Prescott223 unitsPrescott Real Estate DevelopmentAl Barshaa South ThirdCompleted100%17 Feb 202631 Mar 2025
Century214 unitsAMBS Real Estate DevelopmentBusiness BayCompleted100%17 Feb 2026—
Peninsula Two462 unitsEast & West PropertiesBusiness BayCompleted100%12 Feb 20261 Sept 2024
Coral By Vision88 unitsVision DevelopmentsAl SatwaCompleted100%11 Feb 202631 Dec 2025
Park Lane 2 By Heilbronn83 unitsHeilbronn PropertiesAl Barsha South FourthCompleted100%11 Feb 202631 Mar 2026
Damac Lagoons - Santorini (2)388 unitsDamac PropertiesAl Hebiah FifthCompleted100%9 Feb 202629 Jul 2025
Aura Elegance109 unitsAura Infinite Real Estate Development L. L. CNadd HessaCompleted100%4 Feb 20261 Apr 2025
Milestone Residences53 unitsAxiom Prime DevelopmentAl Barsha South FifthCompleted100%4 Feb 202613 Mar 2026
The Roof Residence68 unitsSoboh Real Estate DevelopmentNad Al Shiba FirstCompleted100%4 Feb 202625 Dec 2025
Deansgate By Ade87 unitsADE PropertiesWadi Al Safa 3Completed100%2 Feb 2026—
Viera Residences144 unitsVantage PropertiesMe'Aisem FirstCompleted100%29 Jan 202631 Dec 2025
Orra The Embankment507 unitsOrra Real Estate DevelopmentAl Thanyah FifthCompleted100%29 Jan 20261 Aug 2023
Stonehenge Residences156 unitsSegrex DevelopmentAl Barsha South FourthCompleted100%22 Jan 202631 Mar 2025
Azizi Riviera 55124 unitsAzizi DevelopmentsAl MerkadhCompleted100%19 Jan 2026—
Golf Grand329 unitsEmaarHadaeq Sheikh Mohammed Bin RashidCompleted100%16 Jan 2026—
Mudon Al Ranim 4134 unitsDubai PropertiesAl Hebiah SixthCompleted100%15 Jan 202631 May 2026
Condor Golf Links 18256 unitsCondor GroupAl Hebiah FourthCompleted100%15 Jan 202630 Jun 2026

Source: the official project register of the Dubai Land Department and the Real Estate Regulatory Agency (RERA), read every day. A project name with a link opens its page here, with prices, payment plan and site photos.

Percent built

The share of construction finished, measured by RERA inspectors on their latest visit to the site. It is the regulator's figure, not the developer's estimate.

Registered completion date

The date the developer registered for finishing the project. A project can pass it and still be under construction; the date a developer advertises for handover can differ.

Status

Under construction, completed or cancelled, as the register lists the project. Buyers' payments for a registered off-plan project go into its escrow account, which the regulator oversees.

Dubai project status: questions and answers

How many projects are under construction in Dubai?

1,570 projects are registered as under construction in the official project register of the Dubai Land Department (DLD) and its regulator RERA. Another 1,670 are completed and 610 are cancelled. The latest site inspection on record is from 14 October 2026.

How do I check the status of an off-plan project in Dubai?

Type the name of the project, its developer or its district in the search box on this page. All 3,850 registered projects are covered; each one shows its official status, the percent built at the latest site inspection, the date of that inspection and the registered completion date.

What does the percent built mean?

It is the share of construction finished, as measured by RERA inspectors on their latest visit to the site. It is not the developer's own estimate. 829 projects were inspected in the last 90 days.

What is the registered completion date?

It is the completion date the developer registered with the regulator. A project can still be under construction after it: 250 of the 1,570 projects under construction are past their registered date. A developer may also advertise a different handover date.

How often is the project status updated?

Every day. dxbpropy.ai reads the official register daily and re-reads every project once a week, so a new inspection or a change of status shows here within a day or a week.