← All developers

Deyaar

Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.

Under construction

9

Units

3,212

Delivered (all years)

29

Behind schedule

1

Cancelled (all years)

3

Promised for 2026
2
Promised for 2027
6
Promised for 2028
0
Promised for 2029
0
Promised for 2030
1

Sales in this developer's projects

Registered sales by period; the latest figures run to 11 Nov 2026.

PeriodOff-plan salesVilla plots sold on planResales in completed projects
Last 12 months
AED 2.3bn
1,258 sales
–
AED 706.83M
537 sales
2026 so far
AED 1.6bn
952 sales
–
AED 584.86M
447 sales
2025
AED 2.5bn
1,684 sales
–
AED 971.97M
749 sales
2024
AED 2.1bn
1,613 sales
–
AED 973.94M
866 sales
2023
AED 1.1bn
848 sales
–
AED 949.90M
886 sales
2022
AED 773.74M
760 sales
–
AED 321.04M
370 sales
2021
AED 765.93M
731 sales
–
AED 401.38M
480 sales

Latest from developers

Offers, launches and news from developers' sales teams, updated through the day.

Sales-team items from the last 45 days, Instagram posts from the last 90 days; offers pinned to this developer show at any age while they are valid.

  • 28 OctNewsDeyaar reports AED 541.5 million net profit before tax for first nine months of 2026, up 27% year-on-year.Instagram ↗

Projects

% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.

ProjectStatusBuiltHandover dateDLD planned dateNote
Rosalia ResidencesBehind schedule93%Jul 2026Developer states–4 months past promised handover
Mar CasaSlower than needed67%Oct 2026Developer statesOct 2026
Eleve By DeyaarEarly stage20%Jun 2027Developer states–
Ember At Park FiveEarly stage18%Sept 2027Listing feed statesJun 2027
Elm At Park FiveEarly stage16%Sept 2027Listing feed statesJun 2027
Neem At Park FiveEarly stage15%Dec 2027Listing feed statesDec 2027
Alder At Park FiveEarly stage6%Dec 2027Listing feed statesDec 2027
Ivy At Park FiveEarly stage6%Dec 2027Listing feed statesDec 2027
Downtown ResidencesEarly stage1%Dec 2030project registerDec 2030
Alseef IDelivered100%Apr 2005Apr 2005
Al Seef IiDelivered100%Nov 2008Nov 2008
Madison ResidencyDelivered100%Apr 2009Apr 2009
Jade ResidenceDelivered100%Oct 2009Oct 2009
Citadel TowerDelivered100%Jan 2010Jan 2010
Sapphire ResidenceDelivered100%Feb 2010Feb 2010
Ruby ResidenceDelivered100%Feb 2010Feb 2010
Coral ResidenceDelivered100%Feb 2010Feb 2010
Hamilton ResidencyDelivered100%May 2010May 2010
Mayfair ResidencyDelivered100%Jan 2011Jan 2011
Clayton ResidencyDelivered100%Mar 2011Mar 2011
Mayfair TowerDelivered100%Mar 2011Mar 2011
The MertopolisDelivered100%Mar 2011Mar 2011
51@Business BayDelivered100%Feb 2012Feb 2012
Oxford TowerDelivered100%Dec 2012Dec 2012
Burlington TowerDelivered100%Dec 2012Dec 2012
Oakwood ResidencyDelivered100%Jul 2012Jul 2012
Fair View ResidencyDelivered100%Feb 2014Feb 2014
MontroseDelivered100%Apr 2018Apr 2018
The AtriaDelivered100%Apr 2018Apr 2018
Midtown - AfnanDelivered100%Oct 2019Oct 2019
Midtown - DaniaDelivered100%Mar 2020Mar 2020
Midtown - MeskDelivered100%Aug 2022Aug 2022
Midtown - NoorDelivered100%Feb 2023Feb 2023
Amalia ResidencesDelivered100%Jan 2025Jan 2025
Talia ResidencesDelivered100%Apr 2025Apr 2025
Tria By DeyaarDelivered100%Jun 2025Jun 2025
RegaliaDelivered100%Dec 2024Dec 2024
JannatDelivered100%Apr 2026–
MirarCancelled0%––
Deyaar ParkCancelled0%Dec 2012project registerDec 2012
BristolCancelled14%Jun 2014project registerJun 2014

Deyaar: questions and answers

How many projects is Deyaar building in Dubai?

Deyaar has 9 projects under construction in Dubai, with 3,212 homes in total, according to the Dubai Land Department project register.

How many projects has Deyaar delivered in Dubai?

Deyaar has delivered 29 of the 41 projects the Dubai Land Department project register lists for it.

When do Deyaar projects hand over?

Handover years for Deyaar's projects under construction, by the developer's date where it gave one, else the date in new-project listings, else the Dubai Land Department project register's date: 2 projects in 2026, 6 projects in 2027 and 1 project in 2030.

Which Deyaar projects hand over next?

The next Deyaar projects to hand over are Eleve By Deyaar (June 2027), Ember At Park Five (September 2027), Elm At Park Five (September 2027) and Neem At Park Five (December 2027), by the same dates (the developer's where it gave one, else the new-project listings', else the Dubai Land Department project register's).

How far is construction of Deyaar's projects?

Among Deyaar's projects under construction, the most advanced are Rosalia Residences (93% built), Mar Casa (67% built), Eleve By Deyaar (20% built) and Ember At Park Five (18% built), from official RERA site inspections.