Vision Developments

Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.

Under construction

5

Units

1,203

Delivered (all years)

6

Behind schedule

0

Cancelled (all years)

0

Promised for 2026
2
Promised for 2027
2
Promised for 2028
1
Promised for 2029
0
Promised for 2030
0

Sales in this developer's projects

Registered sales by period; the latest figures run to 11 Nov 2026.

PeriodOff-plan salesVilla plots sold on planResales in completed projects
Last 12 months
AED 1.0bn
926 sales
–
AED 94.49M
78 sales
2026 so far
AED 931.66M
836 sales
–
AED 77.61M
67 sales
2025
AED 499.88M
485 sales
–
AED 105.81M
87 sales
2024
AED 247.37M
221 sales
––

Projects

% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.

ProjectStatusBuiltHandover dateDLD planned dateNote
Reem By VisionOn schedule70%Dec 2026project registerDec 2026
Soul By VisionOn schedule77%Dec 2026project registerDec 2026
Vista By VisionEarly stage12%Sept 2027project registerSept 2027
Verde By VisionEarly stage12%Sept 2027project registerSept 2027
Sera Gardens By VisionEarly stage0%Apr 2028project registerApr 2028
KarmaDelivered100%Jan 2025–
Platinum By VisionDelivered100%Jan 2025–
Pearls By VisionDelivered100%Aug 2025Aug 2025
Dgm VisionDelivered100%Aug 2025Aug 2025
Coral By VisionDelivered100%Dec 2025Dec 2025
Celine By VisionDelivered100%Feb 2026Feb 2026

Vision Developments: questions and answers

How many projects is Vision Developments building in Dubai?

Vision Developments has 5 projects under construction in Dubai, with 1,203 homes in total, according to the Dubai Land Department project register.

How many projects has Vision Developments delivered in Dubai?

Vision Developments has delivered 6 of the 11 projects the Dubai Land Department project register lists for it.

When do Vision Developments projects hand over?

Handover years for Vision Developments's projects under construction, by the developer's date where it gave one, else the date in new-project listings, else the Dubai Land Department project register's date: 2 projects in 2026, 2 projects in 2027 and 1 project in 2028.

Which Vision Developments projects hand over next?

The next Vision Developments projects to hand over are Reem By Vision (December 2026), Soul By Vision (December 2026), Vista By Vision (September 2027) and Verde By Vision (September 2027), by the same dates (the developer's where it gave one, else the new-project listings', else the Dubai Land Department project register's).

How far is construction of Vision Developments's projects?

Among Vision Developments's projects under construction, the most advanced are Soul By Vision (77% built), Reem By Vision (70% built), Vista By Vision (12% built) and Verde By Vision (12% built), from official RERA site inspections.