Dubai project status

The official construction status of every project in the Dubai Land Department (DLD) project register: how far it is built at the latest RERA site inspection, when it was inspected and the completion date the developer registered. 1,572 projects are under construction; the latest inspection on record is from 14 Oct 2026. Project register as of 17 Oct 2026.

Under construction
1,572
registered projects
Completed
1,669
registered projects, all years
Inspected in the last 90 days
831
site inspections by RERA
Past the registered date
251
still under construction
Under constructionCompletedCancelled1,668 projects, latest inspection first
ProjectDeveloperDistrict in the registerStatusBuiltLatest inspectionRegistered completion
Mohammed Bin Rashid Al Maktoum City , District One Phase Iii , Residences 2031 unitsNakheelAl MerkadhCompleted100%31 May 202330 Jan 2023
Mohammed Bin Rashid Al Maktoum City , District One Phase Iii , Residences 2131 unitsNakheelAl MerkadhCompleted100%31 May 202330 Dec 2022
Mohammed Bin Rashid Al Maktoum City , District One Phase Iii , Residences 3131 unitsNakheelAl MerkadhCompleted100%31 May 202330 Dec 2022
Parkside 2422 unitsEmaarMadinat Al MataarCompleted100%30 May 202330 Jun 2023
180 Degree24 unitsAl Sayyah GroupWadi Al Safa 2Completed72%29 May 2023—
Azizi Riviera 5221 unitsAzizi DevelopmentsAl MerkadhCompleted100%25 May 202325 May 2023
Azizi Riviera 14228 unitsAzizi DevelopmentsAl MerkadhCompleted100%25 May 202330 Sept 2022
Royal Park South 135 unitsMetrical Real Estate DevelopmentAl Barsha South FourthCompleted100%25 May 202325 Jun 2023
The Sterling West House195 unitsOmniyatBusiness BayCompleted100%24 May 202324 May 2023
Creek Beach - Vida Residences233 unitsEmaarAl Khairan FirstCompleted100%15 May 202312 Apr 2023
Oxford 212212 unitsIman DevelopersAl Barsha South FourthCompleted100%15 May 202328 Feb 2023
Equiti Residence90 unitsBNH Real Estate DeveloperJabal Ali FirstCompleted100%10 May 202331 Dec 2022
Damac Hills (2) - Navitas (A & B)218 unitsDamac PropertiesMadinat Hind 4Completed100%4 May 202330 Jun 2023
Sobha Hartland Waves604 unitsSobhaAl MerkadhCompleted100%4 May 202331 Mar 2024
Azizi Riviera 262 unitsAzizi DevelopmentsAl MerkadhCompleted100%3 May 202330 Sept 2022
Beach Isle397 unitsEmaarMarsa DubaiCompleted100%2 May 202330 Apr 2023
V2160 unitsTabeer DevelopmentsAl Hebiah FourthCompleted100%1 May 202315 Aug 2022
15 Northside358 unitsSelect GroupBusiness BayCompleted100%25 Apr 202325 Apr 2023
Midtown - Noor606 unitsDeyaarMe'Aisem FirstCompleted100%24 Apr 202328 Feb 2023
Orion Building196 unitsOrion Real Estate DevelopmentAl Barshaa South ThirdCompleted100%17 Apr 202315 Jul 2022
Burj Crown433 unitsEmaarBurj KhalifaCompleted100%12 Apr 202317 Aug 2023
Port De La Mer - La Voile183 unitsPdlm ResidentialJumeirah FirstCompleted100%11 Apr 20233 Apr 2022
Damac Hills (2) - Viridis870 unitsDamac PropertiesMadinat Hind 4Completed100%3 Apr 202326 Aug 2022
Golf Place158 unitsEmaarHadaeq Sheikh Mohammed Bin RashidCompleted100%3 Apr 202328 Feb 2023
Binghatti Creek680 unitsBinghatti DevelopersAl JadafCompleted100%30 Mar 202330 Apr 2023
The Address Dubai Opera873 unitsEmaarBurj KhalifaCompleted100%28 Mar 202330 Mar 2023
Chorisia 1 VillasAbwab Real Estate Limited CoWadi Al Safa 3Completed100%21 Mar 202330 Mar 2023
Creek Beach - Sunset151 unitsEmaarAl Khairan FirstCompleted100%7 Mar 20236 Oct 2022
Creek Beach - Bayshore305 unitsEmaarAl Khairan FirstCompleted100%7 Mar 20236 Oct 2022
Creek Beach - Summer305 unitsEmaarAl Khairan FirstCompleted100%7 Mar 20237 Mar 2023
Creek Beach - Surf173 unitsEmaarAl Khairan FirstCompleted100%7 Mar 20237 Mar 2023
Damac Hills (2) - Amargo398 unitsDamac PropertiesMadinat Hind 4Completed100%27 Feb 202325 Dec 2022
Chaimaa Avenue 292 unitsChaimaa HoldingAl Barsha South FourthCompleted100%27 Feb 202330 Nov 2022
Marina Vista625 unitsEmaarMarsa DubaiCompleted100%23 Feb 202330 Mar 2023
Luma21238 unitsTownXAl Barsha South FourthCompleted100%22 Feb 202330 Apr 2023
Seven Hotel And Apartments The Palm1,124 unitsSeven TidesPalm JumeirahCompleted100%16 Feb 202331 Oct 2022
Creek Beach - Breeze202 unitsEmaarAl Khairan FirstCompleted100%14 Feb 20236 Oct 2022
Arabian Ranches Iii - Joy486 unitsEmaarWadi Al Safa 5Completed100%9 Feb 202330 Aug 2022
Sobha Creek Vistas Reserve784 unitsSobhaAl MerkadhCompleted100%9 Feb 202330 Aug 2023
Myka Residence120 unitsMyka LuxeMe'Aisem FirstCompleted100%6 Feb 2023—
The Royal Atlantis,Resort And Residences232 unitsAtlantis The Palm 2Palm JumeirahCompleted100%1 Feb 202312 Feb 2023
Blue Wave578 unitsTiger PropertiesWadi Al Safa 5Completed100%30 Jan 202330 Jan 2023
Zada Tower703 unitsDamac PropertiesBusiness BayCompleted100%23 Jan 202330 Jun 2023
Taraf 2 Residence94 unitsTarafAl Barsha South FifthCompleted100%19 Jan 202319 Jan 2023
Mohammed Bin Rashid Al Maktoum City , District One Phase Iii , Residences 1595 unitsNakheelAl MerkadhCompleted100%17 Jan 20236 Nov 2022
Intima Villas21 unitsDubai Sports CityAl Hebiah FourthCompleted100%17 Jan 20231 Sept 2022
Edison House65 unitsArabian Gulf PropertiesWadi Al Safa 5Completed100%16 Jan 202330 Dec 2022
Zubaida Residency62 unitsZubaidaWadi Al Safa 3Completed100%16 Jan 2023—
Address Harbour Point814 unitsEmaarAl Khairan FirstCompleted100%12 Jan 202312 Jan 2023
Mohammed Bin Rashid Al Maktoum City , District One Phase Iii , Residences 1695 unitsNakheelAl MerkadhCompleted100%12 Jan 20236 Nov 2022

Source: the official project register of the Dubai Land Department and the Real Estate Regulatory Agency (RERA), read every day. A project name with a link opens its page here, with prices, payment plan and site photos.

Percent built

The share of construction finished, measured by RERA inspectors on their latest visit to the site. It is the regulator's figure, not the developer's estimate.

Registered completion date

The date the developer registered for finishing the project. A project can pass it and still be under construction; the date a developer advertises for handover can differ.

Status

Under construction, completed or cancelled, as the register lists the project. Buyers' payments for a registered off-plan project go into its escrow account, which the regulator oversees.

Dubai project status: questions and answers

How many projects are under construction in Dubai?

1,572 projects are registered as under construction in the official project register of the Dubai Land Department (DLD) and its regulator RERA. Another 1,669 are completed and 610 are cancelled. The latest site inspection on record is from 14 October 2026.

How do I check the status of an off-plan project in Dubai?

Type the name of the project, its developer or its district in the search box on this page. All 3,851 registered projects are covered; each one shows its official status, the percent built at the latest site inspection, the date of that inspection and the registered completion date.

What does the percent built mean?

It is the share of construction finished, as measured by RERA inspectors on their latest visit to the site. It is not the developer's own estimate. 831 projects were inspected in the last 90 days.

What is the registered completion date?

It is the completion date the developer registered with the regulator. A project can still be under construction after it: 251 of the 1,572 projects under construction are past their registered date. A developer may also advertise a different handover date.

How often is the project status updated?

Every day. dxbpropy.ai reads the official register daily and re-reads every project once a week, so a new inspection or a change of status shows here within a day or a week.

More on Dubai off-plan projects