Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.
This developer has 2 project(s) in the register, too few for a track record: read the counts as single projects.
Under construction
1
Units
253
Delivered (all years)
1
Behind schedule
1
Cancelled (all years)
0
Sales in this developer's projects
Registered sales by period; the latest figures run to 11 Nov 2026.
| Period | Off-plan sales | Villa plots sold on plan | Resales in completed projects |
|---|---|---|---|
| Last 12 months | AED 56.27M 27 sales | – | AED 8.16M 10 sales |
| 2026 so far | AED 45.27M 21 sales | – | AED 6.52M 8 sales |
| 2025 | AED 57.36M 36 sales | – | AED 21.54M 23 sales |
| 2024 | AED 62.51M 34 sales | – | AED 46.87M 57 sales |
| 2023 | AED 20.65M 19 sales | – | AED 18.52M 24 sales |
| 2022 | AED 49.35M 48 sales | – | – |
| 2021 | AED 5.64M 6 sales | – | – |
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| West Bay Tower | Behind schedule | 83% | Feb 2024Listing feed states | Feb 2024 | 33 months past promised handover |
| Orion Building | Delivered | 100% | Jul 2022 | Jul 2022 |
✦ Ask about any developer
Track record, projects handing over by year and construction progress — from official records.