Seven Tides
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.
This developer has 2 project(s) in the register, too few for a track record: read the counts as single projects.
Under construction
1
Units
2,666
Delivered (all years)
1
Behind schedule
1
Cancelled (all years)
0
Sales in this developer's projects
Registered sales by period; the latest figures run to 11 Nov 2026.
| Period | Off-plan sales | Villa plots sold on plan | Resales in completed projects |
|---|---|---|---|
| Last 12 months | AED 83.14M 106 sales | – | AED 110.01M 59 sales |
| 2026 so far | AED 57.45M 72 sales | – | AED 84.31M 46 sales |
| 2025 | AED 161.19M 188 sales | – | AED 167.28M 99 sales |
| 2024 | AED 371.00M 426 sales | – | AED 237.77M 151 sales |
| 2023 | AED 714.50M 743 sales | – | – |
| 2022 | AED 432.15M 398 sales | – | – |
| 2021 | AED 1.4bn 1,754 sales | – | – |
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| Seven City Jlt | Behind schedule | 28% | Nov 2025project register | Nov 2025 | 12 months past promised handover |
| Seven Hotel And Apartments The Palm | Delivered | 100% | Oct 2022 | Oct 2022 |