BNH Real Estate Developer

Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date.

Under construction

2

Units

221

Delivered

5

Behind schedule

2

Cancelled

0

Handovers 2026
0
Handovers 2027
0
Handovers 2028
0
Handovers 2029
0
Handovers 2030
0

Projects

% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.

ProjectStatusBuiltHandover dateDLD planned dateNote
Equiti TowerBehind schedule70%Aug 2025Aug 202513 months past promised handover
Equiti GardenBehind schedule87%Dec 2025Dec 20259 months past promised handover
Equiti ApartmentsDelivered100%Dec 2022Dec 2022
Equiti ResidenceDelivered100%Dec 2022Dec 2022
Equiti ArcadeDelivered100%Dec 2023Dec 2023
Equiti GatesDelivered100%Oct 2025–
Equiti HomeDelivered100%Jan 2026–