AYS Developer
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date.
Under construction
4
Units
760
Delivered
1
Behind schedule
1
Cancelled
0
Handovers 2026
1
Handovers 2027
2
Handovers 2028
0
Handovers 2029
0
Handovers 2030
0
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| Q Gardens Lofts | Behind schedule | 91% | Apr 2025 | Dec 2025 | 17 months past promised handover 8 months later on DLD than advertised |
| Q Gardens Lofts 2 | Slower than needed | 36% | Dec 2026 | – | |
| Tivanno Residence | Early stage | 5% | Dec 2027 | Dec 2027 | |
| Q Gardens Aliya | Early stage | 8% | Dec 2027 | Jun 2027 | |
| Q Gardens Boutique Residences | Delivered | 100% | Mar 2022 | Mar 2022 |
✦ Ask about any developer
Track record, projects handing over by year and construction progress — from official records.