AYS Developer
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.
Under construction
4
Units
760
Delivered (all years)
1
Behind schedule
1
Cancelled (all years)
0
Sales in this developer's projects
Registered sales by period; the latest figures run to 11 Nov 2026.
| Period | Off-plan sales | Villa plots sold on plan | Resales in completed projects |
|---|---|---|---|
| Last 12 months | AED 111.22M 112 sales | – | AED 14.95M 12 sales |
| 2026 so far | AED 91.93M 83 sales | – | AED 9.57M 9 sales |
| 2025 | AED 99.69M 143 sales | – | AED 22.00M 17 sales |
| 2024 | AED 60.43M 77 sales | – | AED 22.94M 21 sales |
| 2023 | AED 26.41M 24 sales | – | AED 49.94M 43 sales |
| 2022 | AED 25.83M 33 sales | – | AED 51.61M 49 sales |
| 2021 | AED 15.66M 16 sales | – | – |
Latest from developers
Offers, launches and news from developers' sales teams, updated through the day.
Sales-team items from the last 45 days, Instagram posts from the last 90 days; offers pinned to this developer show at any age while they are valid.
- 14 NovLaunchAYS Developers and Kusto Group announce a new development in IMPZ, Dubai, coming soon.Instagram ↗
- 30 OctLaunchAYS Developers teases The Heritage Collection at Dubai Islands; register interest before waitlist opens.Instagram ↗
- 6 OctNewsQ Gardens Lofts in JVC is handing over, AYS Developers confirms.Instagram ↗
- 29 AugOfferAYS Developers offers 1 year free service charge, a 2% DLD waiver and a BMW X3 raffle entry on purchases in any of its projects until 31 December 2026.Instagram ↗
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| Q Gardens Lofts | Behind schedule | 91% | Apr 2025Listing feed states | Dec 2025 | 19 months past promised handover 8 months later on DLD than advertised |
| Q Gardens Lofts 2 | Slower than needed | 36% | Mar 2028Developer states | – | |
| Tivanno Residence | Early stage | 5% | Dec 2027project register | Dec 2027 | |
| Q Gardens Aliya | Early stage | 8% | Dec 2027Developer states | Jun 2027 | |
| Q Gardens Boutique Residences | Delivered | 100% | Mar 2022 | Mar 2022 |
AYS Developer: questions and answers
How many projects is AYS Developer building in Dubai?
AYS Developer has 4 projects under construction in Dubai, with 760 homes in total, according to the Dubai Land Department project register.
How many projects has AYS Developer delivered in Dubai?
AYS Developer has delivered 1 of the 5 projects the Dubai Land Department project register lists for it.
When do AYS Developer projects hand over?
Handover years for AYS Developer's projects under construction, by the developer's date where it gave one, else the date in new-project listings, else the Dubai Land Department project register's date: 2 projects in 2027 and 1 project in 2028.
Which AYS Developer projects hand over next?
The next AYS Developer projects to hand over are Tivanno Residence (December 2027), Q Gardens Aliya (December 2027) and Q Gardens Lofts 2 (March 2028), by the same dates (the developer's where it gave one, else the new-project listings', else the Dubai Land Department project register's).
How far is construction of AYS Developer's projects?
Among AYS Developer's projects under construction, the most advanced are Q Gardens Lofts (91% built), Q Gardens Lofts 2 (36% built), Q Gardens Aliya (8% built) and Tivanno Residence (5% built), from official RERA site inspections.