Dubai project status

The official construction status of every project in the Dubai Land Department (DLD) project register: how far it is built at the latest RERA site inspection, when it was inspected and the completion date the developer registered. 1,572 projects are under construction; the latest inspection on record is from 14 Oct 2026. Project register as of 17 Oct 2026.

Under construction
1,572
registered projects
Completed
1,669
registered projects, all years
Inspected in the last 90 days
831
site inspections by RERA
Past the registered date
251
still under construction
Under constructionCompletedCancelled1,668 projects, latest inspection first
ProjectDeveloperDistrict in the registerStatusBuiltLatest inspectionRegistered completion
The Lakes - Deema 166 unitsEmaarAl Thanyah ThirdCompleted100%—1 Jan 2003
The Lakes Deema 253 unitsEmaarAl Thanyah ThirdCompleted100%—1 Jan 2003
The Lakes Deema 355 unitsEmaarAl Thanyah ThirdCompleted100%—1 Jan 2003
The Lakes Deema 457 unitsEmaarAl Thanyah ThirdCompleted100%—1 Jan 2003
The Lakes Ghadeer138 unitsEmaarAl Thanyah ThirdCompleted100%—1 Jan 2007
The Lakes Zulal306 unitsEmaarAl Thanyah ThirdCompleted100%—1 Jan 2006
Phoenix Tower116 unitsPhoenix HoldingsWadi Al Safa 5Completed100%—1 Jun 2009
014 Tower42 unitsDistrict &Business BayCompleted100%—14 Jan 2010
Indigo Tower136 unitsIndigo Valley Inc LimitedWadi Al Safa 5Completed100%—7 Mar 2012
Mirabella 216 unitsFortis Plus Holdings LimitedAl Barsha South FourthCompleted100%—16 Dec 2010
Mirabella 416 unitsFortis Plus Holdings LimitedAl Barsha South FourthCompleted100%—18 Dec 2010
Mirabella 616 unitsFortis Plus Holdings LimitedAl Barsha South FourthCompleted100%—20 Dec 2010
Mirabella 518 unitsFortis Plus Holdings LimitedAl Barsha South FourthCompleted100%—19 Dec 2010
Mirabella 320 unitsFortis Plus Holdings LimitedAl Barsha South FourthCompleted100%—17 Dec 2010
Mirabella 116 unitsFortis Plus Holdings LimitedAl Barsha South FourthCompleted100%—15 Dec 2010
Mirabella 818 unitsFortis Plus Holdings LimitedAl Barsha South FourthCompleted100%—22 Dec 2010
Jumeirah Islands Mansions767 unitsJumeirah Islands CoAl Thanyah FifthCompleted100%—11 Jan 2012
Jumeirah Heights Clusters246 unitsJumeirah HeightsAl Thanyah FifthCompleted100%—1 Feb 2012
AriyanaAl Murjan Real Estate ( FzcMarsa DubaiCompleted100%—20 Jan 2011
Emirates Garden 1 (Lavender - Gardenia - Rose)190 unitsDamac PropertiesAl Barsha South FourthCompleted100%—8 Feb 2010
Emirates Garden 2 (Maple- Magnola - Mulberry)189 unitsDamac PropertiesAl Barsha South FourthCompleted100%—1 May 2012
Hds Business Centre312 unitsBaraq Holdings LimitedAl Thanyah FifthCompleted100%—20 Jul 2011
I - Rise Tower490 unitsCapital Middle EastAl Thanyah FirstCompleted100%—29 Mar 2011
Olympic Park 4126 unitsGulf General Co. (P.S.CAl Hebiah FourthCompleted100%—20 Sept 2010
Olympic Park 1126 unitsGulf General Co. (P.S.CAl Hebiah FourthCompleted100%—10 Nov 2010
Fairmont Palm Hotel & Resort34 unitsThe Palm Hotel And Resort FzcPalm JumeirahCompleted100%—9 Sept 2012
Mag218562 unitsDream Estate LimitedMarsa DubaiCompleted100%—3 May 2010
Two Towers292 unitsRashed Darwish Al KetbiAl Thanyah FirstCompleted100%—9 Jul 2009
Burj Dubai28 unitsEmaarBurj KhalifaCompleted100%—18 Jul 2011
Bayswater292 unitsOmniyatBusiness BayCompleted100%—30 May 2010
One Business Bay121 unitsOmniyatBusiness BayCompleted100%—5 Oct 2010
Churchill Tower1,168 unitsEmirates National CoBusiness BayCompleted100%—14 Feb 2009
V3331 unitsSheikh Suroor Bin Mohd AlnehayanAl Thanyah FifthCompleted100%—10 Nov 2009
Apex Atrium73 unitsAswan IncAl Hebiah FirstCompleted100%—25 Jul 2010
Western Residence - South1 unitsFalconcity Of WondersWadi Al Safa 2Completed100%—25 Jun 2009
Axis Residences 1316 unitsGulf General Co. (P.S.CNadd HessaCompleted100%—8 Sept 2009
Axis Residences 3128 unitsGulf General Co. (P.S.CNadd HessaCompleted100%—21 May 2009
Axis Residences 4128 unitsGulf General Co. (P.S.CNadd HessaCompleted100%—21 Oct 2009
Axis Residences 5112 unitsGulf General Co. (P.S.CNadd HessaCompleted100%—13 May 2010
Axis Residences 6112 unitsGulf General Co. (P.S.CNadd HessaCompleted100%—18 Sept 2013
Axis Residences 8112 unitsGulf General Co. (P.S.CNadd HessaCompleted100%—13 May 2010
Armada Towers1,166 unitsMohammad Rahif HakmiAl Thanyah FifthCompleted100%—10 Jan 2010
Axis Residences 7122 unitsGulf General Co. (P.S.CNadd HessaCompleted100%—1 Nov 2009
Hds Sunstar 1120 unitsMars Estates LimitedAl Warsan FirstCompleted100%—31 Aug 2010
Las Casas26 unitsShams Eldien Eissawy Naja & Tarek Mahmoud Fils Halim & Tarek Ossama AbdouAl Barsha South FourthCompleted100%—27 Feb 2012
Zumurud Dubai Marina331 unitsZumurud Real Estate - Sole ProprietorshipMarsa DubaiCompleted100%—10 May 2010
Metro Central210 unitsThe First GroupAl Thanyah FirstCompleted100%—3 May 2011
Claren 1329 unitsEmaarBurj KhalifaCompleted100%—30 Nov 2011
Jumeirah Park1 unitsJumeirah ParkAl Thanyah FifthCompleted100%—26 Feb 2014
Silverene596 unitsCayan Real Estate &Marsa DubaiCompleted100%—17 Aug 2011

Source: the official project register of the Dubai Land Department and the Real Estate Regulatory Agency (RERA), read every day. A project name with a link opens its page here, with prices, payment plan and site photos.

Percent built

The share of construction finished, measured by RERA inspectors on their latest visit to the site. It is the regulator's figure, not the developer's estimate.

Registered completion date

The date the developer registered for finishing the project. A project can pass it and still be under construction; the date a developer advertises for handover can differ.

Status

Under construction, completed or cancelled, as the register lists the project. Buyers' payments for a registered off-plan project go into its escrow account, which the regulator oversees.

Dubai project status: questions and answers

How many projects are under construction in Dubai?

1,572 projects are registered as under construction in the official project register of the Dubai Land Department (DLD) and its regulator RERA. Another 1,669 are completed and 610 are cancelled. The latest site inspection on record is from 14 October 2026.

How do I check the status of an off-plan project in Dubai?

Type the name of the project, its developer or its district in the search box on this page. All 3,851 registered projects are covered; each one shows its official status, the percent built at the latest site inspection, the date of that inspection and the registered completion date.

What does the percent built mean?

It is the share of construction finished, as measured by RERA inspectors on their latest visit to the site. It is not the developer's own estimate. 831 projects were inspected in the last 90 days.

What is the registered completion date?

It is the completion date the developer registered with the regulator. A project can still be under construction after it: 251 of the 1,572 projects under construction are past their registered date. A developer may also advertise a different handover date.

How often is the project status updated?

Every day. dxbpropy.ai reads the official register daily and re-reads every project once a week, so a new inspection or a change of status shows here within a day or a week.

More on Dubai off-plan projects