The First Group

Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.

Under construction

2

Units

1,063

Delivered (all years)

14

Behind schedule

0

Cancelled (all years)

0

Promised for 2026
0
Promised for 2027
1
Promised for 2028
1
Promised for 2029
0
Promised for 2030
0

Sales in this developer's projects

Registered sales by period; the latest figures run to 11 Nov 2026.

PeriodOff-plan salesVilla plots sold on planResales in completed projects
Last 12 months
AED 250.72M
331 sales
–
AED 457.84M
482 sales
2026 so far
AED 220.05M
302 sales
–
AED 423.82M
447 sales
2025
AED 613.10M
543 sales
–
AED 307.73M
316 sales
2024
AED 721.66M
670 sales
–
AED 281.73M
308 sales
2023
AED 705.06M
597 sales
–
AED 231.28M
272 sales
2022
AED 744.87M
557 sales
–
AED 364.43M
343 sales
2021
AED 609.49M
458 sales
–
AED 194.38M
195 sales

Projects

% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.

ProjectStatusBuiltHandover dateDLD planned dateNote
The First Collection At Dubai Studio CitySlower than needed32%Jan 2028project registerJan 2028
The First Collection At Dubai Sports CityOn schedule66%Nov 2027project registerNov 2027
Metro CentralDelivered100%May 2011May 2011
Grand CentralDelivered100%Jul 2012Jul 2012
The BridgeDelivered100%Apr 2013Apr 2013
The MatrixDelivered100%May 2014May 2014
Tfg MarinaDelivered100%Apr 2015Apr 2015
Sky CentralDelivered100%Sept 2016Sept 2016
Tfg One HotelDelivered100%Apr 2018Apr 2018
The One HotelDelivered100%May 2020May 2020
The OneDelivered100%Jun 2020Jun 2020
Avalon TowerDelivered100%Jun 2020Jun 2020
Dolphin TowerDelivered100%Oct 2020Oct 2020
Sky Bay HotelDelivered100%Mar 2021Mar 2021
The One At Jumeirah Village TriangleDelivered100%Jan 2022Jan 2022
CielDelivered100%Apr 2025Apr 2025

The First Group: questions and answers

How many projects is The First Group building in Dubai?

The First Group has 2 projects under construction in Dubai, with 1,063 homes in total, according to the Dubai Land Department project register.

How many projects has The First Group delivered in Dubai?

The First Group has delivered 14 of the 16 projects the Dubai Land Department project register lists for it.

When do The First Group projects hand over?

Handover years for The First Group's projects under construction, by the developer's date where it gave one, else the date in new-project listings, else the Dubai Land Department project register's date: 1 project in 2027 and 1 project in 2028.

Which The First Group projects hand over next?

The next The First Group projects to hand over are The First Collection At Dubai Sports City (November 2027) and The First Collection At Dubai Studio City (January 2028), by the same dates (the developer's where it gave one, else the new-project listings', else the Dubai Land Department project register's).

How far is construction of The First Group's projects?

Among The First Group's projects under construction, the most advanced are The First Collection At Dubai Sports City (66% built) and The First Collection At Dubai Studio City (32% built), from official RERA site inspections.