Time Properties

Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.

Under construction

2

Units

592

Delivered (all years)

6

Behind schedule

1

Cancelled (all years)

3

Promised for 2026
1
Promised for 2027
1
Promised for 2028
0
Promised for 2029
0
Promised for 2030
0

Sales in this developer's projects

Registered sales by period; the latest figures run to 11 Nov 2026.

PeriodOff-plan salesVilla plots sold on planResales in completed projects
Last 12 months
AED 31.99M
42 sales
–
AED 32.42M
51 sales
2026 so far
AED 28.56M
37 sales
–
AED 29.00M
46 sales
2025
AED 104.56M
127 sales
–
AED 26.78M
56 sales
2024
AED 136.43M
183 sales
–
AED 42.46M
82 sales
2023
AED 175.27M
299 sales
–
AED 6.57M
18 sales
2022
AED 63.80M
165 sales
–
AED 14.27M
38 sales
2021
AED 38.29M
110 sales
–
AED 29.84M
63 sales

Projects

% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.

ProjectStatusBuiltHandover dateDLD planned dateNote
Time 2Behind schedule87%Jun 2026project registerJun 20266 months past promised handover
Time 3Slower than needed47%Aug 2027project registerAug 2027
Silicon Gate 3Delivered100%Aug 2013Aug 2013
Silicon Gate 1Delivered100%Jan 2014Jan 2014
Silicon Gate2Delivered100%May 2014May 2014
Silicon Gates 4Delivered100%Jul 2016Jul 2016
Arabian GateDelivered100%Oct 2020Oct 2020
Time 1Delivered100%Dec 2022Dec 2022
Media Gate 2Cancelled0%––
Arabian GateCancelled0%––
Media Gate 1Cancelled0%––

Time Properties: questions and answers

How many projects is Time Properties building in Dubai?

Time Properties has 2 projects under construction in Dubai, with 592 homes in total, according to the Dubai Land Department project register.

How many projects has Time Properties delivered in Dubai?

Time Properties has delivered 6 of the 11 projects the Dubai Land Department project register lists for it.

When do Time Properties projects hand over?

Handover years for Time Properties's projects under construction, by the developer's date where it gave one, else the date in new-project listings, else the Dubai Land Department project register's date: 1 project in 2026 and 1 project in 2027.

How far is construction of Time Properties's projects?

Among Time Properties's projects under construction, the most advanced are Time 2 (87% built) and Time 3 (47% built), from official RERA site inspections.