Amwaj Development

Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date.

Under construction

3

Units

371

Delivered

1

Behind schedule

0

Cancelled

0

Handovers 2026
1
Handovers 2027
1
Handovers 2028
1
Handovers 2029
0
Handovers 2030
0

Projects

% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.

ProjectStatusBuiltHandover dateDLD planned dateNote
The Cube Quarter ResidencesSlower than needed57%Dec 2026Dec 2026
Gate Eleven ResidencesOn schedule31%Dec 2027Mar 2028
KaiaEarly stage0%Dec 2028Dec 2028
Starlight ParkDelivered100%Sept 2026–