AHS Properties
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date.
Under construction
5
Units
252
Delivered
0
Behind schedule
2
Cancelled
0
Handovers 2026
1
Handovers 2027
2
Handovers 2028
0
Handovers 2029
0
Handovers 2030
0
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| One Canal | Behind schedule | 77% | May 2025 | May 2025 | 16 months past promised handover |
| One Crescent | Behind schedule | 80% | Mar 2026 | Mar 2026 | 7 months past promised handover |
| Ahs Tower | Slower than needed | 67% | Jan 2027 | Jan 2027 | |
| Casa Canal | On schedule | 38% | – | – | |
| Casa Ahs | Early stage | 9% | May 2027 | May 2027 |
✦ Ask about any developer
Track record, projects handing over by year and construction progress — from official records.