Trident International
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 22 Nov 2026.
Under construction
0
Units
0
Delivered (all years)
4
Behind schedule
0
Cancelled (all years)
1
Promised for 2026
0
Promised for 2027
0
Promised for 2028
0
Promised for 2029
0
Promised for 2030
0
Sales in this developer's projects
Registered sales by period; the latest figures run to 13 Nov 2026.
| Period | Off-plan sales | Villa plots sold on plan | Resales in completed projects |
|---|---|---|---|
| Last 12 months | – | – | AED 111.70M 33 sales |
| 2026 so far | – | – | AED 105.18M 30 sales |
| 2025 | – | – | AED 190.58M 56 sales |
| 2024 | – | – | AED 315.64M 100 sales |
| 2023 | – | – | AED 187.18M 71 sales |
| 2022 | – | – | AED 170.14M 74 sales |
| 2021 | – | – | AED 124.41M 53 sales |
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| Marinascape | Delivered | 100% | – | – | |
| Bayside Residence | Delivered | 100% | – | – | |
| Trident Grand | Delivered | 100% | Aug 2010 | Aug 2010 | |
| The Water Front | Delivered | 100% | Jun 2011 | Jun 2011 | |
| Pentominium A+B | Cancelled | 22% | Dec 2013project register | Dec 2013 |