Stamn Development

Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.

Under construction

3

Units

228

Delivered (all years)

0

Behind schedule

1

Cancelled (all years)

0

Promised for 2026
1
Promised for 2027
2
Promised for 2028
0
Promised for 2029
0
Promised for 2030
0

Sales in this developer's projects

Registered sales by period; the latest figures run to 11 Nov 2026.

PeriodOff-plan salesVilla plots sold on planResales in completed projects
Last 12 months
AED 95.24M
59 sales
––
2026 so far
AED 75.13M
47 sales
––
2025
AED 114.39M
83 sales
––

Projects

% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.

ProjectStatusBuiltHandover dateDLD planned dateNote
Stamn OneBehind schedule42%Jun 2026Listing feed statesOct 20265 months past promised handover 4 months later on DLD than advertised
Stamn YuniEarly stage12%Mar 2027Listing feed statesMar 2027
Nautis ResidencesEarly stage1%Aug 2027Listing feed statesAug 2027

Stamn Development: questions and answers

How many projects is Stamn Development building in Dubai?

Stamn Development has 3 projects under construction in Dubai, with 228 homes in total, according to the Dubai Land Department project register.

When do Stamn Development projects hand over?

Handover years for Stamn Development's projects under construction, by the developer's date where it gave one, else the date in new-project listings, else the Dubai Land Department project register's date: 1 project in 2026 and 2 projects in 2027.

Which Stamn Development projects hand over next?

The next Stamn Development projects to hand over are Stamn Yuni (March 2027) and Nautis Residences (August 2027), by the same dates (the developer's where it gave one, else the new-project listings', else the Dubai Land Department project register's).

How far is construction of Stamn Development's projects?

Among Stamn Development's projects under construction, the most advanced are Stamn One (42% built), Stamn Yuni (12% built) and Nautis Residences (1% built), from official RERA site inspections.