Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.
Under construction
3
Units
228
Delivered (all years)
0
Behind schedule
1
Cancelled (all years)
0
Sales in this developer's projects
Registered sales by period; the latest figures run to 11 Nov 2026.
| Period | Off-plan sales | Villa plots sold on plan | Resales in completed projects |
|---|---|---|---|
| Last 12 months | AED 95.24M 59 sales | – | – |
| 2026 so far | AED 75.13M 47 sales | – | – |
| 2025 | AED 114.39M 83 sales | – | – |
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| Stamn One | Behind schedule | 42% | Jun 2026Listing feed states | Oct 2026 | 5 months past promised handover 4 months later on DLD than advertised |
| Stamn Yuni | Early stage | 12% | Mar 2027Listing feed states | Mar 2027 | |
| Nautis Residences | Early stage | 1% | Aug 2027Listing feed states | Aug 2027 |
Stamn Development: questions and answers
How many projects is Stamn Development building in Dubai?
Stamn Development has 3 projects under construction in Dubai, with 228 homes in total, according to the Dubai Land Department project register.
When do Stamn Development projects hand over?
Handover years for Stamn Development's projects under construction, by the developer's date where it gave one, else the date in new-project listings, else the Dubai Land Department project register's date: 1 project in 2026 and 2 projects in 2027.
Which Stamn Development projects hand over next?
The next Stamn Development projects to hand over are Stamn Yuni (March 2027) and Nautis Residences (August 2027), by the same dates (the developer's where it gave one, else the new-project listings', else the Dubai Land Department project register's).
How far is construction of Stamn Development's projects?
Among Stamn Development's projects under construction, the most advanced are Stamn One (42% built), Stamn Yuni (12% built) and Nautis Residences (1% built), from official RERA site inspections.
✦ Ask about any developer
Track record, projects handing over by year and construction progress — from official records.