SNK Real Estate Development
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.
This developer has 1 project(s) in the register, too few for a track record: read the counts as single projects.
Under construction
1
Units
8
Delivered (all years)
0
Behind schedule
1
Cancelled (all years)
0
Sales in this developer's projects
Registered sales by period; the latest figures run to 31 Dec 2025.
| Period | Off-plan sales | Villa plots sold on plan | Resales in completed projects |
|---|---|---|---|
| 2025 | AED 7.50M 2 sales | – | – |
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| Sunset Grove Homes | Behind schedule | 28% | Sept 2025project register | Sept 2025 | 14 months past promised handover |
✦ Ask about any developer
Track record, projects handing over by year and construction progress — from official records.