Roz Real Estate Development

Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date.

Under construction

3

Units

286

Delivered

0

Behind schedule

0

Cancelled

0

Handovers 2026
3
Handovers 2027
0
Handovers 2028
0
Handovers 2029
0
Handovers 2030
0

Projects

% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.

ProjectStatusBuiltHandover dateDLD planned dateNote
Rose Gardens 1Slower than needed28%Dec 2026Jul 2026
Rose Gardens 2Slower than needed32%Dec 2026Aug 2026
Rose Gardens 3On schedule76%Dec 2026May 2026