Prescott Real Estate Development
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date.
Under construction
6
Units
1,466
Delivered
5
Behind schedule
2
Cancelled
0
Handovers 2026
2
Handovers 2027
2
Handovers 2028
1
Handovers 2029
0
Handovers 2030
0
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| Serene Gardens By Prescott | Behind schedule | 52% | Dec 2025 | – | 9 months past promised handover |
| Serene Gardens 2 By Prescott | Behind schedule | 63% | Jun 2026 | – | 3 months past promised handover |
| Fairway Residences By Prescott | Slower than needed | 43% | Sept 2026 | – | |
| Verano By Prescott | Slower than needed | 33% | Sept 2027 | Dec 2026 | |
| Legado By Prescott | Early stage | 20% | Dec 2027 | Aug 2027 | |
| The Caden By Prescott | Early stage | 0% | May 2028 | May 2028 | |
| Prime Views | Delivered | 100% | Apr 2020 | Apr 2020 | |
| Prime Townhouses | Delivered | 100% | Sept 2022 | Sept 2022 | |
| Prime Residency 3 | Delivered | 100% | Dec 2024 | Dec 2024 | |
| Prime Gardens | Delivered | 100% | Apr 2024 | Apr 2024 | |
| Elevate By Prescott | Delivered | 100% | Mar 2025 | Mar 2025 |
✦ Ask about any developer
Track record, projects handing over by year and construction progress — from official records.