Premier Choice International
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.
Under construction
2
Units
301
Delivered (all years)
1
Behind schedule
0
Cancelled (all years)
0
Sales in this developer's projects
Registered sales by period; the latest figures run to 11 Nov 2026.
| Period | Off-plan sales | Villa plots sold on plan | Resales in completed projects |
|---|---|---|---|
| Last 12 months | AED 75.87M 132 sales | – | AED 8.18M 6 sales |
| 2026 so far | AED 72.49M 128 sales | – | AED 6.56M 5 sales |
| 2025 | AED 40.86M 42 sales | – | AED 1.63M 1 sales |
| 2024 | AED 37.24M 39 sales | – | – |
| 2023 | AED 27.43M 36 sales | – | – |
Latest from developers
Offers, launches and news from developers' sales teams, updated through the day.
Sales-team items from the last 45 days, Instagram posts from the last 90 days; offers pinned to this developer show at any age while they are valid.
- 12 NovLaunchPremier Choice launches South Lofts II in Dubai Industrial City from AED 515,000.
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| Gateway By Premier Choice | On schedule | 68% | – | – | |
| South Lofts By Premier Choice | Early stage | 0% | Jun 2028Developer states | Jan 2029 | 7 months later on DLD than advertised |
| Barari Views | Delivered | 100% | Mar 2024 | Mar 2024 |
Premier Choice International: questions and answers
How many projects is Premier Choice International building in Dubai?
Premier Choice International has 2 projects under construction in Dubai, with 301 homes in total, according to the Dubai Land Department project register.
How many projects has Premier Choice International delivered in Dubai?
Premier Choice International has delivered 1 of the 3 projects the Dubai Land Department project register lists for it.
When do Premier Choice International projects hand over?
Handover years for Premier Choice International's projects under construction, by the developer's date where it gave one, else the date in new-project listings, else the Dubai Land Department project register's date: 1 project in 2028.
How far is construction of Premier Choice International's projects?
Among Premier Choice International's projects under construction, the most advanced are Gateway By Premier Choice (68% built) and South Lofts By Premier Choice (0% built), from official RERA site inspections.