← All developers

Newbury Developments

Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date.

This developer has 1 project(s) in the register, too few for a track record: read the counts as single projects.

Under construction

1

Units

127

Delivered (all years)

0

Behind schedule

0

Cancelled (all years)

0

Promised for 2026
0
Promised for 2027
0
Promised for 2028
1
Promised for 2029
0
Promised for 2030
0

Sales in this developer's projects

Registered sales by period; the latest figures run to 11 Nov 2026.

PeriodOff-plan salesVilla plots sold on planResales in completed projects
Last 12 months
AED 51.21M
69 sales
––
2026 so far
AED 50.39M
68 sales
––
2025
AED 814,450
1 sales
––

Projects

% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.

ProjectStatusBuiltHandover dateDLD planned dateNote
Chapter 01 By Newbury DevelopmentsEarly stage2%Jun 2028Developer statesOct 2028 3 months later on DLD than advertised