MAK Developers
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date.
Under construction
2
Units
269
Delivered
0
Behind schedule
0
Cancelled
0
Handovers 2026
0
Handovers 2027
2
Handovers 2028
0
Handovers 2029
0
Handovers 2030
0
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| Mak I'Sola Bella | Slower than needed | 27% | Mar 2027 | Sept 2027 | 5 months later on DLD than advertised |
| Saddlewood Park | Early stage | 12% | Sept 2027 | Sept 2027 |