MAK Developers

Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.

This developer has 2 project(s) in the register, too few for a track record: read the counts as single projects.

Under construction

2

Units

269

Delivered (all years)

0

Behind schedule

0

Cancelled (all years)

0

Promised for 2026
0
Promised for 2027
2
Promised for 2028
0
Promised for 2029
0
Promised for 2030
0

Sales in this developer's projects

Registered sales by period; the latest figures run to 11 Nov 2026.

PeriodOff-plan salesVilla plots sold on planResales in completed projects
Last 12 months
AED 70.83M
43 sales
––
2026 so far
AED 47.55M
30 sales
––
2025
AED 146.19M
140 sales
––
2024
AED 28.82M
31 sales
––

Projects

% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.

ProjectStatusBuiltHandover dateDLD planned dateNote
Mak I'Sola BellaSlower than needed27%Mar 2027Developer statesSept 2027 5 months later on DLD than advertised
Saddlewood ParkEarly stage12%Sept 2027Developer statesSept 2027

MAK Developers: questions and answers

How many projects is MAK Developers building in Dubai?

MAK Developers has 2 projects under construction in Dubai, with 269 homes in total, according to the Dubai Land Department project register.

When do MAK Developers projects hand over?

Handover years for MAK Developers's projects under construction, by the developer's date where it gave one, else the date in new-project listings, else the Dubai Land Department project register's date: 2 projects in 2027.

Which MAK Developers projects hand over next?

The next MAK Developers projects to hand over are Mak I'Sola Bella (March 2027) and Saddlewood Park (September 2027), by the same dates (the developer's where it gave one, else the new-project listings', else the Dubai Land Department project register's).

How far is construction of MAK Developers's projects?

Among MAK Developers's projects under construction, the most advanced are Mak I'Sola Bella (27% built) and Saddlewood Park (12% built), from official RERA site inspections.