LIV Developers
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.
Under construction
3
Units
605
Delivered (all years)
2
Behind schedule
0
Cancelled (all years)
0
Sales in this developer's projects
Registered sales by period; the latest figures run to 11 Nov 2026.
| Period | Off-plan sales | Villa plots sold on plan | Resales in completed projects |
|---|---|---|---|
| Last 12 months | AED 656.41M 157 sales | – | AED 142.77M 42 sales |
| 2026 so far | AED 564.75M 138 sales | – | AED 93.62M 25 sales |
| 2025 | AED 757.16M 259 sales | – | AED 214.45M 72 sales |
| 2024 | AED 216.97M 46 sales | – | AED 81.33M 23 sales |
| 2023 | AED 807.26M 239 sales | – | AED 127.34M 39 sales |
| 2022 | AED 503.76M 190 sales | – | AED 87.46M 34 sales |
| 2021 | – | – | AED 73.90M 32 sales |
Latest from developers
Offers, launches and news from developers' sales teams, updated through the day.
Sales-team items from the last 45 days, Instagram posts from the last 90 days; offers pinned to this developer show at any age while they are valid.
- 13 OctNewsLIV LUX logo installed on the tower in Dubai Marina, marking a construction milestone.Instagram ↗
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| Liv Maritime | Slower than needed | 28% | Dec 2028project register | Dec 2028 | |
| Liv Lux | On schedule | 87% | Dec 2026project register | Dec 2026 | |
| Liv Oceanside | Early stage | 14% | Nov 2027project register | Nov 2027 | |
| Liv Residence | Delivered | 100% | Apr 2020 | Apr 2020 | |
| Liv Marina | Delivered | 100% | May 2025 | May 2025 |
LIV Developers: questions and answers
How many projects is LIV Developers building in Dubai?
LIV Developers has 3 projects under construction in Dubai, with 605 homes in total, according to the Dubai Land Department project register.
How many projects has LIV Developers delivered in Dubai?
LIV Developers has delivered 2 of the 5 projects the Dubai Land Department project register lists for it.
When do LIV Developers projects hand over?
Handover years for LIV Developers's projects under construction, by the developer's date where it gave one, else the date in new-project listings, else the Dubai Land Department project register's date: 1 project in 2026, 1 project in 2027 and 1 project in 2028.
Which LIV Developers projects hand over next?
The next LIV Developers projects to hand over are Liv Lux (December 2026), Liv Oceanside (November 2027) and Liv Maritime (December 2028), by the same dates (the developer's where it gave one, else the new-project listings', else the Dubai Land Department project register's).
How far is construction of LIV Developers's projects?
Among LIV Developers's projects under construction, the most advanced are Liv Lux (87% built), Liv Maritime (28% built) and Liv Oceanside (14% built), from official RERA site inspections.
✦ Ask about any developer
Track record, projects handing over by year and construction progress — from official records.