HRE Development

Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date.

Under construction

6

Units

4,566

Delivered

1

Behind schedule

2

Cancelled

0

Handovers 2026
2
Handovers 2027
2
Handovers 2028
1
Handovers 2029
1
Handovers 2030
0

Projects

% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.

ProjectStatusBuiltHandover dateDLD planned dateNote
Skyhills Ii By HreBehind schedule95%Jun 2026Jun 20264 months past promised handover
Skyhills Iii By HreBehind schedule76%Jun 2026Jun 20264 months past promised handover
Skyhills Astra By HreSlower than needed47%Dec 2027Jun 2028 6 months later on DLD than advertised
CelesteEarly stage3%Jun 2027Feb 2027
Wadi Hills By HreEarly stage8%Mar 2028Jan 2028
Sakura Gardens By HreEarly stage4%Mar 2029Jun 2029
Skyhills I By HreDelivered100%Oct 2026Oct 2026