HABN Real Estate Development
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.
This developer has 2 project(s) in the register, too few for a track record: read the counts as single projects.
Under construction
2
Units
931
Delivered (all years)
0
Behind schedule
2
Cancelled (all years)
0
Sales in this developer's projects
Registered sales by period; the latest figures run to 11 Nov 2026.
| Period | Off-plan sales | Villa plots sold on plan | Resales in completed projects |
|---|---|---|---|
| Last 12 months | AED 24.02M 32 sales | – | – |
| 2026 so far | AED 22.63M 29 sales | – | – |
| 2025 | AED 20.41M 27 sales | – | – |
| 2024 | AED 36.31M 54 sales | – | – |
| 2023 | AED 22.28M 45 sales | – | – |
| 2022 | AED 19.98M 39 sales | – | – |
| 2021 | AED 2.63M 7 sales | – | – |
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| The Wind Tower Ii | Behind schedule | 85% | Jun 2023project register | Jun 2023 | 41 months past promised handover |
| The Wind Tower I | Behind schedule | 75% | Jun 2023project register | Jun 2023 | 41 months past promised handover |
✦ Ask about any developer
Track record, projects handing over by year and construction progress — from official records.